Applied Digital Corp.v3 4.5/10 · 2026-11-26Applied Digital Corporation designs, develops, and operates digital infrastructure solutions to high-performance computing (HPC) and artificial intelligence industries in North America. It operates through: Data Center Hosting Business, and HPC Hosting Business. The company offers infrastructure services to crypto mining customers; and GPU computing solutions for critical workloads related to AI, machine learning, and other HPC tasks. It also engages in the designing, constructing, and managing of data centers to support HPC applications. The company was formerly known as Applied Blockchain, Inc. and changed its name to Applied Digital Corporation in November 2022. Applied Digital Corporation has an lease agreement with CoreWeave for an additional 150MW at its Polaris Forge 1 Campus in Ellendale, North Dakota. Applied Digital Corporation is based in Dallas, Texas.
2-Year Price History
Valuation v3 Opus worker · 2026-11-26
Applied Digital builds and leases liquid-cooled AI data center campuses. It has 1.41 GW signed on 15-year take-or-pay leases worth $36.2B (~$2.4B a year at full run-rate), mostly with investment-grade hyperscalers, and it has delivered every building on time and on budget. The stock is $12.29 (Nov 25 close; markets shut Nov 26), down 75% from May's $49.65 in the AI-infrastructure rout. The leases are real, but the thesis test showed the pitch's $18 DCF rested on two errors. First, build cost: Polaris Forge 2 is a $3B campus for 200 MW of critical IT, so the true cost is ~$13-15M/MW, not $11M, which leaves ~$13-15B still to spend. Second, the capital stack: Macquarie's 12.75% PIK preferred (1.8x minimum MOIC) plus its 15% of the HPC common, and the Series G equity line priced at 95% of the 5-day low VWAP, take a far larger share of the value than the $2.0B deducted. Corrected, the 10% DCF gives about $12 at a 14x year-5 multiple: roughly the price. It swings from ~$3 to ~$25 on the terminal multiple (13x vs 16x) and CoreWeave's credit (15-16% bond yields, 400 MW of APLD's capacity). The common is a thin, levered option on a tight spread between yield on cost and the cost of capital, with a related-party $2.4B guarantee and a $2.0B market-cap covenant underneath. Rating 4.5, setup 4.0: fairly priced, with no edge we can name, so we pass.
Flow: Steady issuance is running: the Series G line (now $2.0B, about 50% of market cap) converts at 95% of the 5-day low VWAP, 5.2M shares landed just after Q1, the 2030 converts are in the money and SBC is $100M+ a year, with 800 MW still to finance over the next 12 months. Jane Street trimmed from 7.1% to 6.3% (Nov 12), BlackRock/Vanguard are below 5%, short interest is rising (66.5M shares), and there is no buyback.
A deep dive would have to establish: Can APLD finance PF3/DF1/DF2 (~$11B+) at near-IG cost without more Macquarie 12.75% preferred or Series G issued near today's price, so the ~11% yield on cost leaves real value for the common?
Research (expand)
What it does. APLD designs, builds and operates large AI data centers and leases them on 15-year take-or-pay terms. Polaris Forge 1 (400 MW, CoreWeave; 250 MW credit-enhanced to A3). Polaris Forge 2 (200 MW, an IG hyperscaler). PF3, DF1 and DF2 (810 MW, one high-IG hyperscaler, ~$20B). Total: 1.41 GW and $36.2B of base-term revenue. Also 286 MW of bitcoin hosting (~$50M a year of segment profit) and 96% of ChronoScale (CHRN, GPU cloud).
What the market believes. A levered AI-buildout proxy. The stock fell 75% with CoreWeave and Nebius, on 800 MW still unfinanced (Nov 2), debt at 1.2x+ market value, a Texas moratorium scare and CoreWeave concentration (56% of Q1 revenue). The pitch argued the market confuses IG lease cash flows with GPU beta. The test showed the market is mostly pricing the capital stack correctly: the leases are good, but most of their value accrues to lenders and Macquarie.
What it earns today. Q1 FY27 (Aug): NOI $58.8M (89% margin) plus hosting $13.3M. Cash overhead is about $35M a quarter and recurring SBC about $25M a quarter. Unlevered owner earnings run at about $50-180M a year with 250 MW in service. Operating cash flow was $64M; capex was $2.07B in the quarter.
Projected unlevered FCF ($M, FY27-31): about -8,000 / -4,000 / -1,300 / +500 / +1,500. Capex runs ~$13M per critical MW (PF2: $3B for 200 MW of critical IT) across 1.41 GW plus ~250 MW of expansions. NOI reaches ~$1.5M/MW a year, about $2.5B by FY31, against ~$270M of overhead and SBC. Yield on cost is ~11% NOI, against 7% project debt and 12.75% Macquarie preferred.
Year 5. A stabilized contracted infrastructure landlord growing modestly through campus expansions, with ~10 years left on its leases and powered, permitted sites. I use 14x unlevered FCF (a ~7% cap rate); the range is 12-16x. Confidence is moderate on the revenue and low on what is left for the common.
Fair value. The TV is ~$32B (PV $20B). Five years of FCF have a PV of about -$10.3B, giving an EV of ~$9.7B. Less net debt $3.3B, Macquarie ~$3.0B (PIK preferred PV plus 15% of HPC common) and Series G ~$0.1B. Plus hosting and ChronoScale ~$1.0B. That leaves ~$4.3B over ~350M diluted shares: DCF ~$12. At 13x it is ~$8; at 16x ~$19. We pay ~35x run-rate adj. EBITDA, ~5x FY29 EBITDA. Fair value is $11, a little under the DCF for the dilution loop and governance.
Management, risks, competition. CEO Cummins (~7.6% holder) has delivered on time and on budget. Red flags: Base Electron is owned by Cummins and other directors, and APLD unconditionally guarantees its ~$2.4B boiler contract and lent it $58.5M. SBC is $100M+ a year. The Series G line converts at 95% of the 5-day low VWAP. A Texas Capital covenant requires market cap above $2.0B (~$6.50 a share). Tenants can terminate on construction delays. Securities class action. CoreWeave's bonds yield 15-16%, and 150 MW of PF1 rests on its own credit. Competitors: IREN, CIFR, WULF, Crusoe, CoreWeave and hyperscaler self-builds.
Sentiment: 3/10. Hated after a 75% fall, with short interest at 66.5M shares (~22%) and put IV of 129%.
Thesis test
- Build cost (challenge right). PF2 is a $3B campus for 200 MW of critical IT. Some of that cost is campus and substation infrastructure that also serves the expansions, so I use ~$13M/MW rather than $15M; either way the pitch's $11M was too low. Remaining capex rises by ~$4B, cutting ~$3.5B of PV.
- Macquarie claim (challenge right). The 12.75% PIK (stepping up), the 1.8x minimum MOIC, 15% of the HPC common and a ROFR on future funding make it an expensive equity partner that takes value from the common. The deduction rises from $2.0B to ~$3.0B, and the same structure will repeat on PF3/DF1/DF2.
- Recomputed DCF (challenge mostly right). At 13x the value is ~$8. The pitch's $18 needed 16x and $11M/MW together. I settle on 14x and $13M/MW, which gives ~$12, roughly the price.
- CoreWeave credit (partly right). CoreWeave beat Q3 and raised guidance, so demand is fine. But at 15-16% bond yields the 400 MW tenant is a real tail. 250 MW is protected by the A3 SPV; 150 MW is not.
- Equity as funding valve (right). The Series G line at a 5% discount to the low VWAP, 800 MW still to finance, the $2.0B market-cap covenant and the related-party guarantee make the downside reflexive.
- Conclusion. The revenue case holds and execution is good, but the common equity is a thin residual behind 7% debt and a 12.75% preferred, earning an ~11% yield on cost. At $12.29 the stock is roughly fairly priced, with fat tails both ways (TV multiple, CoreWeave, dilution). There is no identifiable mispricing, so we pass.
- https://www.sec.gov/Archives/edgar/data/1144879/000114487926000059/apld-20260831.htm
- data/analysisv3/context/APLD.md (Q1 FY27 call 2026-10-07, 10-K 2026-07-29 forensics)
- https://www.nasdaq.com/press-release/applied-digital-agrees-build-partnership-macquarie-asset-management-funding-50
- https://www.barchart.com/story/news/34220215/applied-digital-to-break-ground-on-3-billion-polaris-forge-2-campus-in-september-2025-expanding-north-dakotas-role-as-a-national-ai-infrastructure-leader
- https://www.webpronews.com/coreweave-q3-2026-earnings-raised-outlook-backlog-unsecured-debt/
- https://247wallst.com/investing/2026/11/02/applied-digital-slumps-8-as-ceo-says-800-mw-still-needs-financing-nebius-and-coreweave-fall-6/
- https://www.tipranks.com/news/company-announcements/applied-digital-expands-capital-access-with-agreement-amendment
- https://www.tikr.com/blog/applied-digital-sinks-15-as-data-center-rout-deepens-remain-in-gridlock
| date | price | rating | research | fair value | DCF | base IRR | sentiment |
|---|---|---|---|---|---|---|---|
| 2026-10-15 | 20.39 | 5.0 | 7.0 | 24.00 | 14.00 | 10% | 4 |
| 2026-10-20 | 19.33 | 5.5 | 7.5 | 28.00 | 30.00 | 20% | 4 |
| 2026-11-26 | 12.29 | 4.5 | 4.0 | 11.00 | 12.00 | 10% | 3 |
Financials — Adjusted
Adjusted · TTM 2027-Q1 · USD
| TTM & Fiscal-Year P&L | TTM | 2026 | 2025 | 2024 | 2023 |
|---|---|---|---|---|---|
| Revenue | 854+290% | 576+167% | 216+58% | 137+147% | 55.4 |
| Gross profit | 173+445% | 129+468% | 22.7-24% | 30.0+172% | 11.0 |
| Operating expenses | 409+273% | 323+241% | 94.9+111% | 45.0-18% | 55.1 |
| ▸Adj EBITDA | -129 | -125 | 11.3-89% | 99.1 | -36.8 |
| ▸Adj OCF | -177 | -123 | 11.3 | -7.26 | -38.4 |
| CapEx | -4691 | -2866 | -682 | -139 | -131 |
| Adj FCF | -4868 | -2989 | -670 | -147 | -170 |
| ▸Interest expense | 99.5 | 26.1 | 41.5 | 18.6 | 1.98 |
| ▸Adj net income | -417 | -259 | -138 | -108 | -44.6 |
| ▸Owner's earnings | -100 | -- | -- | -- | -- |
claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2023→FY2026 +2027YTD
| Where the Cash Went | Total | 2027YTD | 2026 | 2025 | 2024 | 2023 |
|---|---|---|---|---|---|---|
| ▸Claimed: EBITDA | -228 | -46.8 | -111 | -91.8 | 58.5100% | -36.9 |
| FCF (OCF−capex) | -5784 | -2011 | -2776 | -797 | -128-219% | -72.5 |
| Net income | -904 | -236 | -244 | -231 | -149-255% | -44.6 |
| ▸Capital returned | -5090 | -1323 | -2648 | -922 | -130-222% | -66.6 |
| Buybacks | -1245 | 0.00 | -831 | -283 | -131 | 0.17 |
| Dividends | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest paid | 166 | 77.4 | 26.1 | 41.5 | 18.6 | 1.98 |
| Debt paid down | -4011 | -1401 | -1844 | -680 | -17.4 | -68.8 |
| ▸Reinvestment | 5492 | 2058 | 2474 | 686 | 134229% | 140 |
| Capex (PP&E) | 5893 | 2075 | 2866 | 682 | 139 | 131 |
| Intangibles & M&A | -501 | 0.00 | -501 | 0.00 | 0.00 | 0.00 |
| Leases signed (net Δ) | 101 | -17.2 | 109 | 4.38 | -5.04 | 9.07 |
| Retained / other | -27.7 | -610 | 399 | 167 | 20.435% | -3.95 |
negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.
Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.
Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).
SBC over the Total window: 359 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.
| Balance Sheet | TTM | 2026 | 2025 | 2024 | 2023 |
|---|---|---|---|---|---|
| ▸Assets (total) | 11707 | 9929 | 1870 | 763 | 264 |
| ▸Liabilities (total) | 7907 | 6186 | 1236 | 638 | 194 |
| Net debt (incl. leases) | 3533 | 3508 | 662 | 132 | 62.8 |
| Net debt / Adj EBITDA | -- | -- | 58.3 | 1.34 | -- |
| Net debt / Adj FCF | -- | -- | -- | -- | -- |
| Adj EBITDA / interest | -1.29 | -4.78 | 0.27 | 5.32 | -18.6 |
| Shares outstanding | 291 | 293 | 234 | 144 | 95.9 |
| Dilution (YoY) | +11.5% | +24.9% | +62.5% | +50.2% | -1.9% |
| Employees | 205 | -- | 205 | 150 | 121 |
| Margins | TTM | 2026 | 2025 | 2024 | 2023 |
|---|---|---|---|---|---|
| Gross margin | 20.2%+5.8 | 22.4%+11.8 | 10.5%-11.4 | 21.9%+2.1 | 19.9% |
| Adj EBITDA margin | -15.1%-3.8 | -21.6%-26.9 | 5.3%-67.3 | 72.5%+138.9 | -66.4% |
| Adj OCF margin | -20.7%-15.1 | -21.3%-26.6 | 5.2%+10.5 | -5.3%+63.9 | -69.3% |
| Adj FCF margin | -570.1%-164.5 | -518.7%-207.7 | -311.1%-203.8 | -107.2%+199.0 | -306.3% |
| Net income margin | -54.1%+57.1 | -42.3%+64.9 | -107.2%+2.0 | -109.3%-28.7 | -80.6% |
| Adj NI margin | -48.9%+11.1 | -44.9%+19.2 | -64.1%+14.8 | -78.9%+1.6 | -80.4% |
| ROIC (adj, after-tax) | -2.3% | -2.2% | -4.3% | -4.6% | -23.0% |
| Cost of debt | 2.3% | 0.9% | 5.7% | 10.4% | 4.3% |
Earnings Calls
Earnings Call · 2027 Q1
Applied Digital's fiscal first quarter 27 call (quarter ended August 31, 2026) centered on execution, financing, and a long-term strategy built around large, purpose-built AI factories leased to tier-1 investment-grade hyperscalers. Chairman and CEO Wesley Cummins said the company has roughly $36 billion of contracted revenue across five campuses in three states and two distinct geographic regions. The near-term focus is converting that contracted portfolio into profitable growth. Management expects to place over 600 megawatts into service over the next 12 months, compared with 250 megawatts over the past year. The company's target contracts are take-or-pay leases of at least 15 years with investment-grade customers. Management also expects about 250 megawatts of expansion leases to be executed by year-end at materially higher pricing than prior leases, which it defines as lease rates north of 15% higher and potentially longer durations. North Dakota remains the core region. Polaris Forge 1 has two buildings at full ready-for-service, with a third progressing on schedule, and the operating buildings support 250 megawatts of critical IT load. Management expects about 300 megawatts of critical IT online across North Dakota by the end of the calendar year, with the Harwood campus contributing. The company signed a long-term power purchase agreement with Base Electron, an independent power producer in which Applied Digital holds an approximate 10% equity stake, for an approximately 1.2 gigawatt natural gas facility in central North Dakota adjacent to the Polaris Forge 3 campus. Deliveries from that power are expected to begin in 2030. Management described this dedicated supply as a way to expand on its own timeline rather than waiting in interconnection queues. Revenue contribution from the Louisiana and Alabama campuses is expected to begin in the first half of calendar 2027. Applied Digital also signed an agreement for up to 1 gigawatt of potential power capacity in Finland. Management described it as a measured first step with limited initial exposure. The site was purchased, initial power of 100 megawatts is expected in 2028, and capacity ramps to the full gigawatt by 2031, with an off-ramp before additional payments are triggered. Management said Finland build costs should be similar in dollar terms to the US, though with a longer delivery timeline. On financials, reported total revenue was $341.9 million, up 322% from $80.9 million a year earlier. HPC hosting generated $262.6 million, including $65.8 million of base rent and $183.5 million of tenant fit-out services. The data center hosting segment, which runs 286 megawatts of Bitcoin mining capacity across two North Dakota sites, generated $37.8 million of revenue and $13.3 million of segment operating profit. ChronoScale, in which the company holds about a 96% stake, generated $41.5 million of revenue, including $23 million of GPU hardware sales. ChronoScale is included in GAAP results but excluded from non-GAAP measures. SG&A was $114.7 million, including $65.4 million of stock-based compensation, of which $41.3 million related to one-time performance stock units. The quarter also included a $67.5 million non-cash loss tied to the fair value change of Babcock & Wilcox warrants and common stock. Net loss from continuing operations attributable to common stockholders was $221 million, or $7.76 per share. Adjusted net loss was $4.1 million, or $0.01 per diluted share. Adjusted EBITDA was $64.4 million, versus about $0.5 million a year earlier. HPC net operating income was $58.8 million, an 89% margin. The company ended the quarter with about $2.9 billion of cash and equivalents, plus $700 million of restricted cash, against about $6.4 billion of debt, with more than 80% not due until fiscal 2031 or later. Stockholders' equity was about $1.6 billion. Financing progress was a major theme. The company closed a $1.59 billion offering of 7% senior secured notes due 2031 at par, which funded the final Polaris Forge 1 building and repaid a $300 million bridge facility. Management said the 7% coupon compared favorably with the 9.25% on earlier Polaris Forge 1 notes, reflecting CoreWeave's credit support and investor confidence. The Polaris Forge 1 campus (400 megawatts) and the 200 megawatts contracted at Polaris Forge 2 are now fully funded. The revolving credit facility was upsized to $430 million with a $120 million accordion. The next campuses to finance are Polaris Forge 3, Delta Forge 1, and Delta Forge 2, all leased to the same tier-1 hyperscaler under 15-year take-or-pay leases. The financing framework is Macquarie preferred equity followed by project-level debt, preserving majority ownership for shareholders. Management said project finance markets are open for high investment-grade offtakers and that it underwrites leases so a 50 to 100 basis point rate move would not impair economics, with plans to refinance into cheaper, lower-cost debt once construction risk passes. In closing remarks, Cummins addressed growing local scrutiny of data centers, including moratoriums and tighter zoning. He argued that already powered, permitted, and community-supported campuses become scarcer and more valuable, supporting renewals and terminal values. He cited community benefits, including roughly $45 million of savings for MDU customers since the Ellendale project began, over $100 million of substation and grid upgrades paid by the company at Harwood, and local tax revenue in Ellendale rising from $400 thousand to $4 million annually. Cummins said the company could grow its operating portfolio to 3.5 to 4 gigawatts by the end of calendar 2030, with the high end implying roughly 1 gigawatt of annual delivery in 2029 and 2030. The constraint is construction capacity more than power, since the company has power in its pipeline. In the Q&A, analysts asked about North Dakota hyperscaler interest, which management said includes multiple tier-1 conversations and an awareness of a roughly 1 gigawatt self-build by another hyperscaler in the state. Other topics included the Finland option structure, the rationale behind design longevity versus faster-to-market competitors, current US demand (2027 largely contracted, with demand building for 2028 and 2029), the meaning of selectivity and premium pricing, ChronoScale's expansion into smaller grid-tied sites, supply chain lock-ins of about four years at key component factories, and whether the Macquarie partnership extends beyond North America (management said it does not currently). Management also described more flexible tenant fit-out designs as tenants increasingly plan for changing inference workloads, and said it is evaluating smaller modular builds of 20 to 50 megawatts, largely through ChronoScale. ChronoScale is targeting $1 billion of ARR in 2027, and management said it could reach multiple hundreds of megawatts of capacity over 2027 and 2028 outside the large Applied Digital campuses.
▸What is the perception of North Dakota as a market and the receptivity from hyperscalers?Mike Grondahl · Northland Securities
▸What current options exist for investment-grade hyperscaler debt funding given the challenging bond market?Mike Grondahl · Northland Securities
▸What options are embedded in the Finland agreement and how is the commercial side progressing?Nick Giles · B. Riley Securities
▸What was the genesis of the emphasis on the longevity of data center campuses, which seems more pronounced than before?Nick Giles · B. Riley Securities
▸How would you characterize market conditions for the 1.3 gigawatts of US capacity being marketed, given regulatory moratoriums?Derrick Whitfield · Texas Capital
▸How might build costs in Finland compare with the US, including labor, building, and equipment supply chains?Derrick Whitfield · Texas Capital
▸How does the Base Electron PPA enable North Dakota expansion, and which years are most affected?Rob Brown · Lake Street Capital Markets
▸How has the company mitigated supply chain constraints?Rob Brown · Lake Street Capital Markets
▸Does the term selective refer to the quality of customers rather than the amount of capacity to be built?George Sutton · Craig-Hallum
▸How is premium pricing defined for the roughly 250 megawatts of expansion leases, and what does it include beyond base rent?George Sutton · Craig-Hallum
▸How much initial power will the Finland site have, what community or governmental risks exist, and was the site selected for a specific customer?Darren Aftahi · Roth Capital Partners
▸What steps are needed to reach 4 gigawatts by year-end 2030, how much depends on Base Electron, and are other European sites needed?John Todaro · Needham and Company
▸Could ChronoScale reach around 400 megawatts over time, similar to CoreWeave's growth path?John Todaro · Needham and Company
▸Would the existing Macquarie relationship extend to Finland?Michael Donovan · Compass Point
▸As inference becomes a larger share of workloads, are GPU, CPU, and storage mix changes contributing to premium lease rates?Michael Donovan · Compass Point
▸Are there circumstances where the company would consider smaller modular build-outs of around 20 to 50 megawatts?Michael Donovan · Compass Point
SEC Filing Findings
SEC Filing — material findings
2026-10-07 · depth 9/10risk 8Related-Party▸Company signed a 15-year, ~1,200 MW Power Purchase Agreement with Base Electron, a related-party power producer owned/managed by CEO Cummins, Zhang and Nottenburg; APLD owns ~10% of Base Electron, holds a $58.5M related-party promissory note receivable, and has an unconditional guarantee of Base Electron obligations; Base Electron may terminate if financial close not reached by March 31, 2027.
Company signed a 15-year, ~1,200 MW Power Purchase Agreement with Base Electron, a related-party power producer owned/managed by CEO Cummins, Zhang and Nottenburg; APLD owns ~10% of Base Electron, holds a $58.5M related-party promissory note receivable, and has an unconditional guarantee of Base Electron obligations; Base Electron may terminate if financial close not reached by March 31, 2027.
risk 6Related-Party▸Related-party promissory note to Base Electron (up to $100M payable on demand) carried at gross value with no credit loss allowance, and the Company's maximum exposure to Base Electron is disclosed as the note plus equity investment.
Related-party promissory note to Base Electron (up to $100M payable on demand) carried at gross value with no credit loss allowance, and the Company's maximum exposure to Base Electron is disclosed as the note plus equity investment.
risk 7Hidden Liability▸Company is committed to a 15-year PPA and provides credit support to Base Electron; Base Electron's $2.4B B&W boiler contract is unconditionally guaranteed by APLD, with guarantee terminating only upon Base Electron public listing or raising $50M.
Company is committed to a 15-year PPA and provides credit support to Base Electron; Base Electron's $2.4B B&W boiler contract is unconditionally guaranteed by APLD, with guarantee terminating only upon Base Electron public listing or raising $50M.
risk 6Liquidity/Covenants▸Texas Capital loan requires market capitalization to stay above $2.0 billion at the close of every trading day, plus a liquidity maintenance covenant; a sustained share price decline could trigger default.
Texas Capital loan requires market capitalization to stay above $2.0 billion at the close of every trading day, plus a liquidity maintenance covenant; a sustained share price decline could trigger default.
risk 6Litigation▸Securities class action (McConnell) and derivative suit remain pending; company states loss cannot be estimated and an adverse outcome could be material.
Securities class action (McConnell) and derivative suit remain pending; company states loss cannot be estimated and an adverse outcome could be material.
risk 7Customer Concentration▸Two customers account for 77% of quarterly revenue (Customer A 56%, Customer B 21%).
Two customers account for 77% of quarterly revenue (Customer A 56%, Customer B 21%).
risk 6Toxic Financing▸Series G convertible preferred continues to be issued and converted into common stock, with a PEPA commitment increased to $2.0B; subsequent conversion of 128,750 shares into 5.2M common shares adds dilution.
Series G convertible preferred continues to be issued and converted into common stock, with a PEPA commitment increased to $2.0B; subsequent conversion of 128,750 shares into 5.2M common shares adds dilution.
risk 6Hidden Liability▸Company provides completion guarantees on project notes and a ChronoScale-linked credit exposure; the 2031 7.000% notes carry a $1.59B principal with mandatory redemption on certain lease termination fees, and fixed-rate notes amortize from FY2027 onward.
Company provides completion guarantees on project notes and a ChronoScale-linked credit exposure; the 2031 7.000% notes carry a $1.59B principal with mandatory redemption on certain lease termination fees, and fixed-rate notes amortize from FY2027 onward.
Options
Chain Snapshot (daily)
| Strike | Call Bid/Ask | Call OI | Put Bid/Ask | Put OI |
|---|---|---|---|---|
| $14.00 | $3.40/$4.20 | 81 | $0.87/$1.13 | 783 |
| $15.00 | $2.80/$3.65 | 81 | $1.37/$1.51 | 559 |
| $16.00 | $2.52/$3.10 | 297 | $1.81/$2.14 | 1,125 |
| $17.00 | $2.07/$2.26 | 669 | $2.41/$2.65 | 860 |
| $18.00 | $1.66/$1.89 | 868 | $3.00/$3.40 | 1,870 |
| $19.00 | $1.37/$1.49 | 1,542 | $3.65/$3.90 | 2,471 |
| $20.00 | $1.12/$1.20 | 4,098 | $4.35/$4.80 | 841 |
| $21.00 | $0.88/$1.01 | 481 | $5.10/$5.60 | 511 |
Short Interest
Web Traffic
Executive Compensation (2023.0-2025.0)
Cash Runway
Institutional Ownership
| Fund | $ value | Cost basis | Δ QoQ | Δ YoY | α life | Fund AUM |
|---|---|---|---|---|---|---|
| Hood River Capital Management LLC | $548M | $7.33 | +$24.6M | +$42.9M | +1.7% | $9.97B |
| BlackRock, Inc.Passive | $496M | $12.21 | +$1.3M | +$113M | — | $5.69T |
| VANGUARD PORTFOLIO MANAGEMENT LLCPassive | $352M | $23.74 | +$352M | +$352M | — | $1.91T |
| Situational Awareness Partners LP | $320M | $23.74 | +$320M | +$320M | — | $3.86B |
| Situational Awareness LP | $320M | $16.32 | +$50.8M | +$224M | — | $3.86B |
| VANGUARD CAPITAL MANAGEMENT LLCPassive | $256M | $23.74 | +$256M | +$256M | — | $4.04T |
| GOLDMAN SACHS GROUP INC | $190M | $17.40 | +$156M | +$136M | -0.2% | $760.93B |
| Value Aligned Research Advisors, LLC | $158M | $24.40 | +$24.3M | +$158M | +10.7% | $8.44B |
| GEODE CAPITAL MANAGEMENT, LLCPassive | $152M | $9.70 | +$3.0M | +$25.5M | -0.1% | $1.61T |
| DBA TRADING, LLC | $132M | $23.74 | +$132M | +$132M | — | $200M |
Ownership Over Time
5-year share-count history (top 10 holders by peak, incl. exited) + price
Related Stocks
Investors who own this also own
Stocks held by the same active managers as this one, ranked by score — how much more often these appear together than random chance (1× = baseline). Excludes index ETFs and market makers; minimum 3 shared holders.
| Ticker | Name | Co-holders | Score |
|---|---|---|---|
| BW | Babcock & Wilcox Enterprises, Inc. | 3 | 160.22× |
| BTDR | Bitdeer Technologies Group | 3 | 116.53× |
| IREN | IREN Limited | 4 | 74.31× |
| RIOT | Riot Platforms, Inc. | 3 | 67.46× |
| CORZ | Core Scientific, Inc. | 4 | 50.27× |
| CRWV | CoreWeave, Inc. Class A Common Stock | 3 | 38.84× |
| BE | Bloom Energy Corporation | 4 | 25.51× |
| SATS | EchoStar Corporation | 3 | 17.09× |
| LITE | Lumentum Holdings Inc. | 3 | 11.34× |
Analyst Coverage
| Quarter | Revenue | EBITDA | Net Inc | EPS | EPS Range | # Analysts |
|---|---|---|---|---|---|---|
| 2022 Q1 | 1M | -26M | -26M | $-0.09 | $-0.11 – $-0.08 | 3 |
| 2022 Q2 | 7M | -17M | -18M | $-0.06 | $-0.07 – $-0.05 | 2 |
| 2022 Q3 | 6M | -10M | -12M | $-0.04 | $-0.05 – $-0.04 | 2 |
| 2022 Q4 | 12M | -15M | -17M | $-0.06 | $-0.07 – $-0.05 | 2 |
| 2023 Q1 | 17M | -12M | -15M | $-0.05 | $-0.06 – $-0.05 | 2 |
| 2023 Q2 | 22M | -10M | -13M | $-0.05 | $-0.05 – $-0.04 | 1 |
| 2023 Q3 | 34M | -0M | -10M | $-0.04 | $-0.04 – $-0.03 | 1 |
| 2023 Q4 | 56M | 41M | 20M | $0.07 | $-0.51 – $0.73 | 5 |
| 2024 Q1 | 50M | 11M | -20M | $-0.07 | $-0.14 – $-0.01 | 5 |
| 2024 Q2 | 38M | 16M | -60M | $-0.22 | $-0.27 – $-0.19 | 5 |
| 2024 Q3 | 55M | -36M | -78M | $-0.27 | $-0.40 – $-0.12 | 7 |
| 2024 Q4 | 62M | -7M | -41M | $-0.14 | $-0.20 – $-0.10 | 5 |
| 2025 Q1 | 65M | -2M | -30M | $-0.10 | $-0.14 – $-0.04 | 3 |
| 2025 Q2 | 38M | -18M | -45M | $-0.15 | $-0.21 – $-0.06 | 3 |
| 2025 Q3 | 50M | -29M | -38M | $-0.13 | $-0.22 – $-0.07 | 4 |
| 2025 Q4 | 85M | -15M | -36M | $-0.12 | $-0.20 – $-0.03 | 3 |
| 2026 Q1 | 76M | -23M | -44M | $-0.15 | $-0.33 – $-0.08 | 2 |
| 2026 Q2 | 97M | 11M | -33M | $-0.11 | $-0.22 – $-0.03 | 2 |
| 2026 Q3 | 116M | 33M | -86M | $-0.30 | $-0.42 – $-0.07 | 4 |
| 2026 Q4 | 159M | -13M | -90M | $-0.31 | $-0.38 – $-0.18 | 3 |
| 2027 Q1 | 205M | -16M | -100M | $-0.34 | $-0.44 – $-0.18 | 4 |
| 2027 Q2 | 268M | 3M | -93M | $-0.32 | $-0.38 – $-0.22 | 1 |
| 2027 Q3 | 337M | 32M | -77M | $-0.26 | $-0.32 – $-0.18 | 1 |
| 2027 Q4 | 413M | 60M | -65M | $-0.22 | $-0.27 – $-0.15 | 1 |
| 2028 Q1 | 491M | 83M | -62M | $-0.21 | $-0.26 – $-0.15 | 2 |
| 2028 Q2 | 569M | 120M | -48M | $-0.16 | $-0.20 – $-0.11 | 2 |
| 2028 Q3 | 697M | 377M | 143M | $0.49 | $0.34 – $0.59 | 2 |
| 2028 Q4 | 753M | 417M | 152M | $0.52 | $0.36 – $0.62 | 2 |
| 2029 Q1 | 787M | 445M | 150M | $0.52 | $0.36 – $0.62 | 2 |
| 2029 Q2 | 759M | 466M | 146M | $0.50 | $0.35 – $0.60 | 1 |
Corporate
Insider Trading (last 12mo)
| Date | Side | Insider | Title | Shares | Price | Dollars | Owned $ |
|---|---|---|---|---|---|---|---|
| 2026-10-16 | BUY | Cummins Wes | director, officer: CEO; Chairman | 55,803 | $18.04 | $1.01M | $105.98M |
| 2026-10-16 | BUY | Zhang Jason Gechen | officer: President | 300,000 | $18.86 | $5.66M | $53.55M |
| 2026-10-13 | SELL | Nottenburg Richard N | director | 31,250 | $21.84 | $683K | $2.23M |
| 2026-08-04 | SELL | Nottenburg Richard N | director | 75,000 | $31.15 | $2.34M | $4.15M |
| 2026-04-30 | SELL | Nottenburg Richard N | director | 12,500 | $34.59 | $432K | $7.21M |
| 2026-04-28 | SELL | Nottenburg Richard N | director | 12,500 | $32.00 | $400K | $7.07M |
| 2026-04-27 | SELL | MILLER DOUGLAS S | director | 10,000 | $34.98 | $350K | $6.47M |
| 2026-01-29 | SELL | HASTINGS CHUCK | director | 45,987 | $38.57 | $1.77M | $14.98M |
| 2026-01-16 | SELL | Cummins Wes | director, officer: CEO; Chairman | 165,000 | $36.42 | $6.01M | $152.10M |
| 2026-01-15 | SELL | Nottenburg Richard N | director | 12,000 | $35.45 | $425K | $8.27M |
| 2026-01-14 | SELL | Nottenburg Richard N | director | 11,606 | $35.28 | $409K | $8.66M |
| 2026-01-12 | SELL | MILLER DOUGLAS S | director | 10,000 | $38.54 | $385K | $7.74M |
| 2025-11-28 | SELL | MILLER DOUGLAS S | director | 8,000 | $26.98 | $216K | $5.69M |
| 2025-11-24 | SELL | Benson Ella G. | director | 8,581 | $23.22 | $199K | $1.59M |
v2 analysis (legacy, 2026-07-30) — for comparison onlyclick to expand
Thesis
Applied Digital is rapidly transitioning from a weak crypto/cloud infrastructure history into a hyperscale AI-data-center developer and operator. The signed lease backlog is genuinely transformational: approximately 1.41 GW and $36.2B of 15-year contracted revenue, with a rising share of investment-grade counterparties. Recent execution at Polaris Forge 1 and the latest 810 MW hyperscaler leases materially strengthen the business case. However, this is still a financing and construction platform rather than a proven compounder. Capital expenditure is enormous, consolidated owner earnings are currently negative, stock-based compensation and dilution are substantial, and net debt has risen sharply. A single customer represents approximately 59% of continuing-operations revenue, leases contain construction milestone termination rights, and the Base Electron guarantee creates an unusual related-party contingent liability. The likely trajectory is strongly upward operationally, but the range of outcomes remains exceptionally wide.
Trade Signal
Short, with substantial risk management around squeezes: the stock's AI-infrastructure backlog is real, but at roughly $8.0 billion of equity value versus an analyst fair value near $2.4 billion, leverage, preferred claims, dilution, and negative owner earnings leave common shareholders paying for an optimistic outcome.
The stock rose from roughly $10 in mid-2025 to $47.28 in May 2026 as the market capitalized the AI-data-center pivot, hyperscaler leases, capacity announcements, and financing milestones. It then declined from the mid-$40s to $23.22 through July as investors reassessed valuation, dilution, execution, and financing risk; the latest leg included a roughly 15% drop around the July 27 earnings release despite 407% revenue growth and $20.2 billion of new contracted leases. The post-earnings reaction was directionally justified because the print also showed a $110.6 million common-stockholder loss, $116.8 million of SBC, continued heavy capex, and no demonstrated owner earnings. The selloff may have overshot near term given the lease news, but the broader repricing from $47 is largely durable rather than a temporary panic. A modest residual oversold component exists, amplified by 81% volatility and crowded short positioning.
The stock is widely liked by sell-side analysts and AI-infrastructure investors, with 26 analysts and 94% Buy indications, but it is not a complacent consensus winner: the shares have fallen 53% from the 52-week high, declined 38% in one month and 42% in six months, and short interest remains very high at 26.9% of float. Bulls focus on the $36 billion contracted backlog, investment-grade hyperscaler exposure, and rapid revenue growth. Bears focus on CoreWeave concentration and credit risk, negative owner earnings, leverage, dilution, preferred claims, Base Electron allegations, and power bottlenecks. The market appears to have begun discounting these risks after earnings, but the valuation still reflects too much of the bull case.
The operational inflection is real: revenue grew 407%, adjusted EBITDA was positive, and contracted lease value expanded sharply with long-duration hyperscaler commitments. But the market already recognizes and heavily rewards that story: the consensus is unanimously Buy, the average target is far above the current price, and the stock has previously traded at extreme AI-infrastructure multiples. More importantly, the analyst's forecast path conflicts with the bullish narrative: published estimates still show negative EBITDA through 2029, while the company must spend heavily before those leases translate into distributable common-equity cash flow. The next evidence is more likely to expose financing and conversion risk than produce an unanticipated step-up.
- ▼late 2026 · Q1 FY2027 earnings and construction/lease update — Likely first test of whether the $1 billion NOI run-rate trajectory is credible, whether capex and financing needs are escalating, and whether new campuses remain on schedule.
- ▼H2 2026-H1 2027 · Further project-debt or equity/preferred financing — Approximately $600 million of near-term quarterly capex and the capital-intensive buildout could expose additional dilution, interest burden, or unfavorable financing terms.
- •H2 2026-2027 · Polaris Forge and Delta Forge construction milestones — On-time delivery and energization would support the bull case; delays, cost overruns, or power constraints would validate the bear case.
- ▼H2 2026-2027 · Base Electron/Babcock & Wilcox litigation and project developments — Adverse legal findings, delays, or evidence that the power arrangement is unnecessary could increase the governance discount and potential liability.
- •Next 6-12 months · Additional hyperscaler lease announcements — New take-or-pay contracts could support the premium valuation, but only if economics, counterparty quality, financing needs, and common-equity value are demonstrably attractive.
Flow is materially negative for common shareholders: TTM dilution is approximately 27%, SBC was $116.8 million in the latest quarter and the study identifies a further large CEO-award overhang. There have been no insider purchases and approximately $31.9 million of insider sales over the last year. Project financing may reduce immediate parent-level issuance, but it adds leverage and does not eliminate preferred or equity dilution. Short interest at 26.9% of float creates squeeze fuel, while passive ownership provides some mechanical demand.
There is no hard common-equity floor near the current price. Project assets and contracted leases provide enterprise value, but roughly $3.2-$4.5 billion of net debt or debt-like claims, the Macquarie preferred liquidation stack, Series G dilution, continuing cash burn, and execution risk can absorb much of that value before common equity. The large short interest can create temporary trading support or squeezes, but it is not a fundamental floor. A meaningful ceiling is also present because insiders have sold, dilution is substantial, and the stock already capitalizes a very optimistic execution outcome.
The business is strategically attractive to AI-infrastructure investors, and hyperscaler leases can draw real buyers. However, common equity is difficult to own at this valuation because cash burn, roughly 27% TTM dilution, heavy project debt, preferred liquidation claims, CoreWeave concentration, and governance/legal risks mean much of the enterprise value may accrue ahead of common. The likely marginal buyer is a momentum or AI-infrastructure investor, not a traditional cash-flow investor.
Fear is stronger than greed at this price. The operating story is genuinely impressive, but the common stock appears to price in successful multi-campus execution, favorable financing, high utilization, and limited counterparty or governance problems despite negative owner earnings, very high capex, substantial leverage, and structural claims ahead of common.
Valuation
The genuinely new information is the scale and concentration of the three newly signed 15-year leases: approximately 810 MW and $20.2B of additional base-term revenue with one high-investment-grade hyperscaler. The company also reported $258.7M of quarterly revenue, $42.4M of adjusted EBITDA, on-time delivery of additional Polaris Forge capacity, and a target to reach a $1B NOI run rate next year. The quarter also highlighted that restricted-cash details remain incomplete and that CapEx will increase from approximately $600M in the next quarter.
▸ How the cases moved
The new quarter shifts the bull case upward from roughly $8,000M to $9,500M as the 810 MW, approximately $20.2B hyperscaler leases are now disclosed, financing has been arranged and management expects a $1B NOI run-rate next year. The base case rises from approximately $2,700M to $3,200M because contracted revenue visibility and investment-grade customer mix are better than previously established. The bear case remains meaningful, moving only from roughly $450M to $500M because construction termination rights, concentration, leverage and the Base Electron guarantee remain unresolved. Bull probability rises from 0.17 to 0.20, base remains near 0.50, and bear falls from 0.33 to 0.30.
Construction delays, power constraints, or customer stress prevent the full contracted backlog from converting into operating assets. CoreWeave concentration remains a problem, the Base Electron guarantee becomes costly, and financing costs stay elevated. The company reaches only modest positive EBITDA as existing sites mature, with poor cash conversion and little additional growth.
▸ Valuation
2x $2,000M EBITDA = $4,000M EV - $3,500M net debt = $500M equity value
The signed investment-grade hyperscaler leases are substantially delivered, while the existing CoreWeave facilities continue to ramp. Revenue grows rapidly, but construction spending, depreciation, stock compensation, interest and project-level leverage keep owner earnings well below NOI or EBITDA. The company becomes a credible scaled data-center landlord, but customer concentration and execution risk prevent a premium valuation.
▸ Valuation
8x $900M EBITDA = $7,200M EV - $4,000M net debt = $3,200M equity value
Applied delivers the recently signed 810 MW leases on time and on budget, adds the two expansion opportunities at higher pricing, and refinances project debt as construction risk declines. Investment-grade counterparties, campus economies of scale and lower financing costs drive EBITDA and owner earnings sharply higher. The valuation assumes the gap between NOI/EBITDA and owner earnings closes as projects mature and recurring maintenance capital becomes a smaller share of revenue.
▸ Valuation
10x $1,400M EBITDA = $14,000M EV - $4,500M net debt = $9,500M equity value
▸ Target Rationale
The probability-weighted scenario value is $2,920M, but I set the analytical target at $2,800M because the arithmetic does not fully capture execution risk, customer concentration, dilution, related-party power obligations and the uncertain cash conversion of a rapidly expanding project-finance structure. The signed backlog deserves substantial value, but it should not yet be valued like a mature, diversified infrastructure owner.
Business Quality & Sentiment
Recent Research & News
Recent Research & News
2026-06-21Company news
Applied Digital Corporation (APLD) has announced several material operational, financial, and strategic updates over the last six months:
- Major Debt and Capital Raises: In June 2026, APLD announced the pricing of $1.59 billion in Senior Secured Notes through its subsidiary APLD ComputeCo 3 LLC to fund the fourth building at its Polaris Forge 1 campus. This followed a $300 million senior secured bridge facility in May 2026 and a $350 million committed revolving credit facility (with a $200 million accordion option) secured in late May 2026 to support its broader pipeline.
- Hyperscale Leasing Milestones: The company surpassed 1 GW of total contracted capacity in May 2026 after securing a lease with an investment-grade hyperscaler at its Polaris Forge 3 campus. Shortly after, in June 2026, APLD signed a 15-year, 210 MW take-or-pay lease at its fifth campus, Delta Forge 2, which is projected to generate approximately $5.2 billion in base contracted revenue. APLD also signed a tenant agreement for its 430 MW Delta Forge 1 campus in April 2026.
- Tenant Lease Restructuring: On March 30, 2026, APLD restructured its 100 MW and 150 MW leases with CoreWeave at Polaris Forge 1. The leases were migrated to a CoreWeave Special Purpose Vehicle (SPV) that secured an investment-grade credit rating of A3, supported by an unconditional springing guarantee from CoreWeave Parent and a $50 million letter of credit.
- Corporate Separation: In May 2026, APLD completed the spin-off of its Cloud Services Business, establishing ChronoScale as an independent publicly traded entity.
- Financial Performance: For the third fiscal quarter ended February 28, 2026, APLD reported revenues of $126.6 million (a 139% year-over-year increase) and an adjusted EBITDA of $44.1 million, though it experienced a GAAP net loss of $100.9 million driven by depreciation and non-recurring items.
▸ Thesis-test Findings
- CoreWeave liquidity and financial stability reports 2026: CoreWeave (CRWV), APLD's primary tenant at Polaris Forge 1, is experiencing hyper-growth alongside heavy financial strain, supporting both bull and bear cases. In Q1 2026, CoreWeave surpassed $2 billion in revenue (up 112% YoY) and expanded its contracted backlog to nearly $100 billion, bolstered by a $21 billion Meta contract. However, CoreWeave remains deeply unprofitable, posting a $740 million net loss and carrying a debt load of nearly $30 billion as of mid-2026. Despite its B+ speculative-grade rating from S&P, APLD mitigated counterparty risk in March 2026 by shifting the leases to an investment-grade (A3-rated) SPV backed by parent guarantees. Completion and tenant concentration risks still constrain ratings on APLD's senior notes to CoreWeave's credit profile.
- North Dakota grid capacity and industrial power allocations 2026: Expanding data center demand has triggered localized grid bottlenecks, prompting three western North Dakota counties (such as Oliver and Mercer) to implement 180-day to one-year moratoriums on new data center projects in early 2026. Despite these local pushbacks, APLD has de-risked its immediate grid access by funding infrastructure directly. In April 2026, the North Dakota Public Service Commission (PSC) approved a $110 million substation and high-voltage transmission line project (Agassiz). Though owned by Minnkota Power Cooperative, APLD is covering the cost upfront to secure 280 MW of peak power for its eastern North Dakota facility. This strategy shields other ratepayers and de-risks power supply, but underscores APLD's highly capital-intensive development model.
- Base Electron Babcock and Wilcox contract status: In March 2026, Babcock & Wilcox (B&W) received a full notice to proceed on a $2.4 billion, 1.2 GW design-build agreement with independent power producer Base Electron to construct four 300-MW gas-fired boilers to power APLD's AI data centers. APLD has unconditionally guaranteed Base Electron's obligations, with the guarantee terminating if Base Electron secures a public listing or raises $50 million. However, the contract has faced significant controversy. A March 2026 short-seller report from Wolfpack Research and subsequent class-action lawsuits allege the contract is an unviable, conflict-of-interest-ridden deal designed to provide exit liquidity for B. Riley (BRC) (whose co-CEO, Bryant Riley, is a director of Base Electron and shares its corporate address). The allegations highlight that APLD already has grid agreements for its current projects and may not need the B&W-built power. Management notes that the bulk of physical construction is deferred to 2027 and 2028, presenting execution and timing risks.