Stocks/CENX

CENX

Century Aluminum Companyv3 5.0/10 · 2026-11-13
Basic Materials·Aluminum
$31.32
$3.0B market cap
v3 Rating
5.0/103.5–6.5
Setup
4.0/103.0–5.5
Fair Value
$36.00$17.00–$62.00+15%
DCF (10%)
$37.00+18%
Base IRR
+4%-45%–+70%
Visibility
wide±63%
Wall Street
$58.00 target(3 analysts last quarter)(9 buy, 12 hold, 2 sell)
Rating
Revenue (TTM)
$3.0B
Owner Earnings
$850M
Next-Yr Owner Earnings
$580M
Growth
-10.0% × 5y
P / Next-Yr OE
5.7x
Net Debt
-$227M

Century Aluminum Company, along with its associated entities, manufactures both standard and specialized primary aluminum products across the United States and Iceland. The firm also possesses and manages a facility dedicated to carbon anode production, situated in the Netherlands. Founded in 1981, the company's corporate headquarters are located in Chicago, Illinois.

2-Year Price History

$35.98+59.1%
$20$30$40$50$60Initial target $36.00 · 2026-11-13volNov 24Mar 25Jul 25Nov 25Mar 26Jul 26Oct 26

Valuation v3 Opus worker · 2026-11-13

Rating
5.03.5–6.5
Setup
4.03.0–5.5
Fair value (USD)
36.0017.00 – 62.00
Upside vs 31.32
+15%
DCF (10%)
37.0017.00 – 65.00+18%
Base IRR
4%-45% – 70%
Visibility
widerange ±63%
Sentiment
4/10
Reputation
5/10
2026-11-13 · claude-opus-5-5 · priced at 35.98

Century Aluminum is the largest US primary aluminum producer, with a large Icelandic smelter and 55% of a Jamaican alumina refinery. All of its plants are at full capacity for the first time in a decade, behind a 50% Section 232 tariff. Run-rate EBITDA is about $1.15B and the balance sheet holds about $227M of net cash. Yet the stock, at $35.98 (12-Nov close; the pack's $33.77 is stale), trades at only about 3x EV/EBITDA, 45% below its May high. That looks like a screaming bargain, but testing showed the market is mostly right. These earnings are tariff- and shortage-driven rent. EBITDA was $244M in 2024 and $425M in 2025. The Midwest premium of about $2,425/t sits above 50%-tariff import parity of about $1,700/t, and consensus expects a 2027 surplus. The $1.5B federal NOL is largely used up in 2026, so cash taxes will roughly double from 2028. The Oklahoma smelter, which management uses to justify keeping all the cash, faces an attorney-general lawsuit with a pending injunction, a reportedly suspended air-permit review and a federal suit against the DOE grant. That delays both the import-arbitrage option and any buyback. Re-running the DCF with premium-parity, tax and 2027 corrections (and adding the Q4 2026 cash the pitch omitted) gives about $37 a share against a $36 price: fairly priced, with a fat but policy-dependent right tail (about $65) and a tariff-cut left tail (about $17). Rating 5.0 (fair value, no margin of safety, no dated catalyst, Glencore overhang). Interest 4.0: cheap on the headline multiple, but the mispricing is not there once peak rent is normalized. With option IV of 62-72%, covered calls are the only angle worth considering for an existing holder; the earnings are too commodity-driven to call it a true valuation floor.

A deep dive would have to establish: Does the 50% Section 232 tariff (and a Midwest premium of at least about $0.75/lb) survive through 2028, and will Oklahoma's legal fight end in either an FID or a return of the trapped cash?

Owner earnings, TTM
$850M$650M – $980M
Realistic peak profit
$1.1B$850M – $1.4B
Growth rate
-10.0%-22.0% – 3.0%
Years of growth
53 – 5
Market cap
$3.8B$3.6B – $3.9B
EV
$3.6B$3.4B – $3.8B
Net debt
-$227M-$330M – -$150M
Capital return / cap
0.0%0.0% – 4.0%
P/E
4.5×3.5× – 9.0×
EV/EBITDA
3.1×2.8× – 5.5×
FCF yield
17.0%10.0% – 24.0%
Projected FCF, base case (USD millions)
Y1$580M$420M – $800M
Y2$470M$220M – $750M
Y3$440M$150M – $750M
Y4$410M$120M – $720M
Y5$380M$80M – $700M
Competition: A price-taker in a global commodity whose US edge is the tariff wall, competing for the same premium with Alcoa, Canadian imports (Rio Tinto, Alouette) and the restarted New Madrid smelter.
Governance: Glencore is a 30% holder that keeps selling, the customer for 51% of sales, the alumina supplier and a lender; disclosure controls are not effective because a material weakness from the Jamalco restatement is unremediated; and management understated the Oklahoma litigation on the Q3 call.
Research (expand)

What it does. Century smelts primary aluminum. It has about 450kt/yr in the US (Sebree KY; Mt. Holly SC, restarted to 230kt in June 2026) and about 320kt at Grundartangi in Iceland. It also owns 55% of the Jamalco alumina refinery and a carbon-anode plant in the Netherlands. Glencore owns 30% of the shares, takes 51% of sales, and supplies alumina. Century is a price-taker in a commodity whose only US edge is the tariff wall.

What the market believes. This is peak-cycle rent. LME is down about 20% from June and consensus sees a 2027 surplus. The Midwest premium (about $1.10/lb, or $2,425/t) is above tariff parity. Policy is binary: a flat 25% tariff for Canadian aluminum was agreed in principle before talks collapsed on 21 August. The cash is earmarked for Oklahoma, so there are no shareholder returns before FID.

What the pitch hoped the market misses.

  • A 25%-tariff import allowance (about 300kt/yr).
  • A $300M TeraWulf put on the Hawesville data-center stake.
  • Full Grundartangi amperage in Q1 2027.
  • Lower unit costs from full plants.

The TeraWulf put and the volume gains are real. The import option depends on an Oklahoma project now in court.

What it earns today. The Q4 guide of $275-300M annualizes to about $1.15B EBITDA. Adjusted EBITDA excludes the entire forward/derivative line, so realized hedge losses of about $90M a year are deducted. Less about $110M sustaining capex, about $60M cash tax and $15M SBC, that leaves unlevered owner earnings of about $850M on a roughly $3.56B EV.

Five-year FCF (unlevered; Oklahoma treated as NPV-neutral and excluded). 2027 $580M, 2028 $470M, 2029 $440M, 2030 $410M, 2031 $380M. The assumptions are:

  • LME about $2,900.
  • The premium falls to about $1,750/t parity from 2028.
  • Hedges roll off.
  • US cash taxes resume once the NOL ($1.545B at end-2025) runs out.

By year 5 this is a normal, tariff-protected cyclical smelter, worth about 6x FCF.

DCF at 10%. PV of the cash flows is $1.76B and PV of the terminal value is $1.42B. Adding net cash ($227M), Q4-2026 FCF (about $220M), the TeraWulf put (about $250M PV) and the 45X/insurance receivables (about $100M) gives about $3.98B, or about $37 per diluted share (105.2M). In the bull case (LME above $3,100, the premium holds and the import arbitrage goes live) it is about $65. In the bear case (a broad tariff cut to 25% takes the premium to about $900/t) it is about $17.

Multiples. About 3.1x EV/run-rate EBITDA, about 4.5x run-rate P/E, about 8x normalized P/E. The FCF yield is 23% on run-rate and about 12% normalized.

Management and risks. CEO Gary delivered the restarts on time but is promotional. On the Q3 call he glossed over the Oklahoma litigation and plans to lever the project fully. Other risks:

  • Glencore: concentration, related-party ties and an ongoing selldown (43% → 30%).
  • The material weakness from the Jamalco restatement is still unremediated.
  • Jamalco bauxite quality, Iceland transformers, and EPA high-priority-violator status.
  • New Madrid's restart adds about 10% to US supply.

Sentiment: 4/10. The stock has halved from its peak, short interest is about 13% of the non-Glencore float, and option IV is 62-72%.

Thesis test

1. Tariff/premium normalization: challenge right. 50% x ~$3,000 LME plus freight puts parity at about $1,700-1,750/t, so the pitch's $1,900 forever was generous. This costs about $4/share. The Canada-cut tail is real, but Alcoa's argument that a Canada-only cut barely moves the premium keeps it a tail, not the base case.

2. Oklahoma: challenge right on the facts. The AG suit, the pending injunction, the reportedly suspended DEQ review and the federal DOE suit are all sourced, and management omitted them. The base DCF never included the import arbitrage, so DCF value is unchanged. Fair value loses the option and the near-term catalyst, though a dead project could eventually free the cash.

3. 2027 FCF: challenge right. With the lower Q4 guide and LME already below $3,000, $580M is better supported than $700M. That costs about $1/share.

4. Cash taxes: challenge right. The 10-K's $1.545B NOL is largely consumed by the 2026 Hawesville gain plus US profits, so US cash taxes resume around 2028. That costs about $3/share.

5. Glencore overhang: facts right, but no effect on value. It is a timing and sentiment cap, not a cash-flow problem.

The pitch also missed about $2/share of Q4-2026 cash, which partly offsets the cuts.

Conclusion. The core business is intact and the balance sheet is genuinely strong. But the cheap headline multiple is on tariff-and-shortage rent, and on normalized numbers the stock is about fairly valued. There is no margin of safety, no dated catalyst, and a binary policy tail. Pass.

Sources

Financials — Adjusted

Adjusted · TTM 2026-Q3 · USD

TTM & Fiscal-Year P&LTTM2025202420232022
Revenue2996+19%2528+14%2220+2%2185-21%2777
Gross profit740+208%264+43%185+101%91.9+97%46.7
Operating expenses109+65%98.3+55%63.6+6%60.1-69%197
▸Adj EBITDA722+185%258+27%203+91%107-76.8
▸Adj OCF723+281%230+53%150+88%80.1+23%64.9
CapEx-206-98.8-82.3-95.0-86.3
Adj FCF517+363%131+93%68.0-14.9-21.4
▸Interest expense42.147.743.135.529.3
▸Adj net income612+306%157+68%93.3+322%22.1-226
▸Owner's earnings240--------

claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2022→FY2025 +2026YTD

Where the Cash WentTotal2026YTD2025202420232022
▸Claimed: EBITDA1770100%990100%152100%449100%43.4100%136100%
FCF (OCF−capex)38722%45946%84.856%-107-24%10.624%-60.4-44%
Net income121168%88990%41.827%33775%-43.1-99%-14.1-10%
▸Capital returned98.66%98.310%12.68%-14.2-3%48.5112%-46.6-34%
Buybacks0.000.000.000.000.000.00
Dividends0.000.000.000.000.000.00
Interest paid18529.447.743.135.529.3
Debt paid down-86.468.9-35.1-57.313.0-75.9
▸Reinvestment53130%17217%98.865%71.916%104239%84.362%
Capex (PP&E)53517298.882.395.086.3
Intangibles & M&A-2.500.000.00-10.47.900.00
Leases signed (net Δ)-1.10------0.90-2.00
Retained / other47627%39039%12079%-39.2-9%-10.3-24%15.511%

negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.

Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.

Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).

SBC over the Total window: 7.3 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.

Balance SheetTTM2025202420232022
▸Assets (total)31722280193918471472
▸Liabilities (total)13261340127715021073
Net debt (incl. leases)-233413486385494
Net debt / Adj EBITDA-0.321.602.393.61--
Net debt / Adj FCF-0.453.147.15----
Adj EBITDA / interest17.15.404.713.00-2.62
Shares outstanding99.099.093.392.792.3
Dilution (YoY)+6.1%+6.1%+0.7%+0.4%+1.2%
Employees29712906297129391956
MarginsTTM2025202420232022
Gross margin24.7%+15.210.4%+2.18.3%+4.14.2%+2.51.7%
Adj EBITDA margin24.1%+14.110.2%+1.09.2%+4.34.9%+7.6-2.8%
Adj OCF margin24.1%+16.69.1%+2.36.8%+3.13.7%+1.32.3%
Adj FCF margin17.3%+12.85.2%+2.13.1%+3.7-0.7%+0.1-0.8%
Net income margin29.7%+26.41.6%-13.515.2%+17.1-2.0%-1.5-0.5%
Adj NI margin20.4%+14.46.2%+2.04.2%+3.21.0%+9.2-8.2%
ROIC (adj, after-tax)28.3%12.1%9.9%3.0%-10.3%
Cost of debt8.2%9.5%8.6%7.0%6.0%

Revenue Breakdown

Revenue Segments

By Product (2026-Q1)
Aluminum$587.9M+10%
Alumina$61.3M-38%
By Geography (2026-Q1)
UNITED STATES$561.9M+36%
ICELAND$87.3M-60%

Earnings Calls

12 calls

Earnings Call · 2026 Q3

2026-11-05

Century Aluminum reported a strong third quarter 2026, driven by its first return to full capacity across all assets in over a decade and robust US and European pricing. Shipments were about 174 thousand tons, up 33% sequentially, and net sales rose $209 million to nearly $1 billion. Net income was $303 million ($2.89 per share); adjusted net income was $272 million ($2.58 per share). Adjusted EBITDA was $332 million, up $5 million sequentially, with realized LME at about $3.4 thousand per ton, a US Midwest premium of $1.11 per pound and a European premium of $520 per ton. Seasonal energy costs at Sebree (MISO Indiana Hub around $60/MWh) and initial instability at Mt. Holly were headwinds. The company converted $332 million of EBITDA into $365 million of cash flow and ended with $755 million in cash against $486 million of debt, no revolver borrowings and over $1 billion of liquidity. Cash items included $94 million of fiscal 2025 45X credits, $19 million of Iceland insurance proceeds, and a $40 million working capital release; CapEx was $38 million. Operationally, Mt. Holly instability was resolved and the plant should return to full volume and normal mix in Q4. Grundartangi ran a strong quarter after returning to full pots in July; three of four replacement transformers have arrived, with amperage returning to full nameplate over Q1. Jamalco continues to work through the bauxite quality issue, with the revised mine plan taking a few quarters, while the new TG4 turbine came online in August. Sebree again performed excellently. For Q4, the company guides to lagged LME of $3.15 thousand per ton, a Midwest premium of $1.10 per pound and a European premium of $550 per ton, reducing EBITDA by $35-45 million. Energy is expected to improve by up to $5 million, raw materials to be a $5-10 million headwind, opex up $5 million, and volume/mix up $5-10 million. Q4 adjusted EBITDA is guided at $275-300 million, with hedge settlements of $20-25 million and tax expense of $10-15 million. On Oklahoma, financing material terms are largely agreed, power contract documentation is progressing, and engineering with Bechtel and EGA continues. A new environmental plan cuts permitted fluoride emissions by 37%, and an economic impact study shows nearly $1.5 billion annual GDP benefit. Management expects to access the import-incentive program (25% tariff rate) quickly, possibly coincident with FID. Major restart CapEx (~$125 million) is complete, and cash will first fund Oklahoma before shareholder returns or other projects are considered after FID. Century also retains a 6.8% interest in the TeraWulf Hawesville data center with a $300 million put right. Management said cost improvements reflect full-production efficiencies and should persist into 2027, and 2027 value-added premium guidance will come in February.

Analyst Q&A (11)
▸
Given Oklahoma CapEx may fall more in 2028, could excess cash build on the balance sheet, and would Century consider shareholder returns earlier given the stock is under pressure?
Nick Giles · B. Riley Securities
Management agrees the stock looks underpriced but believes it prudent to wait on shareholder returns until FID, once financing, import incentives and the size and timing of equity needs are clear. They will steward cash responsibly, move quickly to FID, and update investors if an opportunity arises as cash builds.
▸
What is the power strategy in Oklahoma (will it be hedged) and what are the key gating items for the power agreement?
Nick Giles · B. Riley Securities
Century will buy power directly from the utility, similar to the South Carolina structure rather than market-based (Sebree) or LME-linked (Iceland), with specific structuring to be disclosed at FID. Good progress continues and the parties are moving into final documentation.
▸
Was community opposition in Oklahoma mainly about fluoride emissions, were there other concerns, and is there risk of permitting delays?
Matthew Key · Texas Capital
Various concerns exist among regulators and community members; Century is addressing them via voluntary fluoride cuts, town halls and one-on-one engagement. State and federal support remains strong, communication with regulators is good, and the project is making good progress and staying on track.
▸
After FID, how soon could Century use the import-arb program and how does the application process work?
Matthew Key · Texas Capital
Century is actively working with the Department of Commerce on mechanics, with good alignment. Management expects to use the program very quickly, if not coincident with FID.
▸
What is the status of Oklahoma financing options, and did the midterm elections change the opportunity set?
Katja Jancic · BMO Capital Markets
Nearly all material financing terms are agreed and it should be ready at FID, with an attractive package expected. On the midterms, reindustrialization is bipartisan and the project has had support from both parties and the administration, so broad support is expected to continue.
▸
Does the Q4 EBITDA guide reflect volume improvement after Q3 Mt. Holly instability, and is Grundartangi line 2 assumed at 100% in Q4?
Richard Garchitorena · Barclays
The instability was resolved in Q3 and is in those results; Q4 outlook includes units ramping back up through the quarter, and Iceland needs no further adjustments. Additional Grundartangi amperage increases and full Mt. Holly benefit come in Q1.
▸
Is anything likely to delay or slow the Oklahoma financing and power contract work, separate from community discussions?
Richard Garchitorena · Barclays
Century aims to line up all work streams at once so everything is ready at FID, while continuing to address community and permitting issues. Engineering and allowed preconstruction activities proceed on all fronts.
▸
Cost per pound improved about $0.33 over two quarters; should those costs come back in the December and March quarters?
John Tumazos · Very Independent Research
No. The improvement reflects returning smelters to full production (fixed cost absorption, power and labor efficiency), and this cost structure, with perhaps a bit more improvement, should continue into 2027 and beyond.
▸
With strong cash flow, why pay fees and borrow the full financing for Oklahoma when you may not need it all?
John Tumazos · Very Independent Research
Century wants the most efficient capital structure and views the financing's rates and structure as very attractive; the decision will be made at FID, but management expects to fully utilize the financing.
▸
Are there more material uses of cash than modest projects like Jamalco, and could growing net cash force a decision on other uses in the next couple of quarters?
Timna Tanners · Wells Fargo
It is a good problem to have; few projects resemble the Mt. Holly restart, though Jamalco cost projects exist and teams keep generating ideas. If conditions persist, Century can fund its Oklahoma share and either additional projects or shareholder returns.
▸
Given talk of a potential Canada carve-out on aluminum tariffs, what insight is there on the administration's thinking about aluminum tariffs?
Timna Tanners · Wells Fargo
Management cannot speak to the negotiations, but the government sees Section 232 working as designed, citing the Mt. Holly restart, the imminent New Madrid restart, and progress toward Oklahoma. Despite chatter, there have been no changes, exemptions or exceptions, and management is confident of continued support.

SEC Filing Findings

SEC Filing — material findings

2026-11-05 · depth 9/10
risk 6Internal Controls / Restatement
▸

Disclosure controls concluded NOT effective as of Sept 30, 2026; material weakness from Dec 2025 (Jamalco consolidation) remains unremediated; prior-period figures restated for Jamalco full consolidation.

“concluded that our disclosure controls and procedures were not effective as of September 30, 2026”
risk 7Related-Party / Customer Concentration
▸

Glencore owns 30% of common stock and is the largest customer, taking ~51% of Q3 2026 net sales; also alumina supplier, lender (Vlissingen facility up to $90M) and counterparty on contingent obligation.

“For the three months ended September 30, 2026 and 2025, we derived approximatel y 51.1 % and 50.6 %, respectively, of our consolidated net sales from Glencore.”

Options

Chain Snapshot (daily)

Call IV (ATM)62%
Put IV (ATM)72%
ATM Spread1.5%
Call $OI (near money)$3.7M
Put $OI (near money)$5.1M
ATM ExpiryDecember 18, 2026 (44D)
ATM Strike$32.5
Major Expirations3
Near-money chain · December 18, 2026
StrikeCall Bid/AskCall OIPut Bid/AskPut OI
$25.00$8.10/$9.102$0.40/$0.7564
$27.50$6.10/$6.805$0.80/$1.0013
$30.00$4.40/$5.0086$1.40/$2.00301
$32.50$3.10/$3.60413$2.45/$3.1032
$35.00$1.95/$2.45199$4.20/$4.501,164
$37.50$1.40/$1.705,830$5.60/$6.50243
$40.00$0.90/$1.20449$7.60/$8.40796
$42.50$0.35/$0.9062$9.50/$10.800
Snapshot: 2026-11-04

Short Interest

Short % of Float15.6%
Short Shares9.2M
Days to Cover4.0
Change (vs Prior)-2.4%
Short % Float History
15.60%+1.90pp
13.0%14.0%15.0%16.0%17.0%10-1512-3103-1305-2908-1410-30

Web Traffic

centuryaluminum.com
Web rank#995,190
Est. visits/mo581K
Traffic YoY▼ 38.4%
Traffic QoQ (12w)▼ 2.7%
Web Rank History
#995,190+180,425
rankest. visits/mo
400k600k800k1.0m470K799K1.1M1.5M1.8M05-1909-1512-0803-0206-0108-3111-16

Executive Compensation (2023.0-2025.0)

Direct Pay$61.3M
Incentive & Other$24.7M
Total Compensation$86.1M
% of Revenue1.1%

Institutional Ownership

Fund$ valueCost basisΔ QoQΔ YoYα lifeFund AUM
Glencore plc$1.37B$18.22+$0−$477M—$4.87B
BlackRock, Inc.Passive$474M$19.40+$59.6M+$6.7M—$6.70T
STATE STREET CORPPassive$255M$15.86+$40.3M+$86.4M—$3.38T
VANGUARD PORTFOLIO MANAGEMENT LLCPassive$220M$57.28+$24.5M+$220M—$2.22T
VANGUARD CAPITAL MANAGEMENT LLCPassive$137M$57.04+$17.8M+$137M—$4.68T
Invesco Ltd.$111M$26.20+$15.7M+$86.5M—$1.26T
Sourcerock Group LLC$104M$26.27−$19.4M+$38.7M—$1.92B
DIMENSIONAL FUND ADVISORS LPPassive$102M$12.48+$947K−$39.6M—$551.30B
FMR LLC$90.2M$47.98−$32.2M+$89.9M—$2.30T
GEODE CAPITAL MANAGEMENT, LLCPassive$85.0M$35.27+$14.1M+$25.1M—$1.87T
Cost basis is a volume-weighted estimate from accumulation periods within our 13F history; holders who built their position before our window started will show a stale basis. % above the cost basis is the unrealized gain at the current price.

Ownership Over Time

5-year share-count history (top 10 holders by peak, incl. exited) + price

012.1M24.2M36.3M48.4M$5.28$19$32$45$592021-092022-092023-092024-092025-092026-06
hover the chart for per-quarter detailprice (right axis)
Glencore plc29.7MSourcerock Group LLC2.3MFMR LLC2.0MInvesco Ltd.2.4MMILLENNIUM MANAGEMENT LLC1.1MAssenagon Asset Management S.A.1.5MMORGAN STANLEY1.5MEncompass Capital Advisors LLC900KD. E. Shaw & Co., Inc.796KCITADEL ADVISORS LLC290K

Related Stocks

Investors who own this also own

Stocks held by the same active managers as this one, ranked by score — how much more often these appear together than random chance (1× = baseline). Excludes index ETFs and market makers; minimum 3 shared holders.

TickerNameCo-holdersScore
AAAlcoa Corporation3197.79×
PUMPProPetro Holding Corp.393.69×
CCJCameco Corporation330.17×

Analyst Coverage

Analyst Coverage
Price Targets
Last Quarter (3 analysts)$58.00+89.0%
Last Year (8 analysts)$61.63+100.9%
Current Price$30.68
Analyst Ratings
9
12
2
Buy: 9Hold: 12Sell: 2Consensus: Hold
Consensus Estimates
QuarterRevenueEBITDANet IncEPSEPS Range# Analysts
2003 Q1138M32M14M$-0.10$-0.12 – $-0.0813
2003 Q2180M10M-3M$-0.11$-0.13 – $-0.0914
2003 Q3150M9M-4M$-0.10$-0.12 – $-0.0811
2003 Q4296M4M-9M$-0.07$-0.09 – $-0.0619
2004 Q1172M16M3M$0.20$0.16 – $0.2412
2004 Q2246M37M17M$0.52$0.42 – $0.6216
2004 Q3366M-7M-20M$0.85$0.68 – $1.028
2004 Q4262M40M19M$0.65$0.52 – $0.7820
2005 Q1278M22M6M$0.77$0.62 – $0.9220
2005 Q2305M77M44M$0.90$0.72 – $1.0815
2005 Q3340M-10M-24M$0.77$0.62 – $0.928
2005 Q4381M-169M-183M$0.80$0.64 – $0.9611
2006 Q1320M-115M-130M$1.10$0.88 – $1.3219
2006 Q2387M80M44M$1.74$1.39 – $2.0911
2006 Q3531M337M223M$2.14$1.71 – $2.578
2006 Q4427M-101M-120M$1.66$1.33 – $1.9914
2007 Q1467M115M67M$2.03$1.62 – $2.4412
2007 Q2464M-42M-61M$1.69$1.35 – $2.0318
2007 Q3499M31M8M$1.47$1.18 – $1.7616
2007 Q4576M-120M-140M$1.20$0.96 – $1.447
2008 Q1530M-238M-259M$1.60$1.28 – $1.9215
2008 Q2497M19M-2M$2.07$1.66 – $2.4811
2008 Q3603M78M40M$1.55$1.24 – $1.8611
2008 Q4343M-557M-578M$-0.38$-0.46 – $-0.3014
2009 Q1158M-44M-73M$-0.63$-0.75 – $-0.5014
2009 Q2222M-96M-123M$-0.94$-1.13 – $-0.7510
2009 Q3432M101M53M$-0.23$-0.27 – $-0.189
2009 Q4257M-2M-24M$0.03$0.02 – $0.0413
2010 Q1246M30M5M$0.16$0.13 – $0.1914
2010 Q2379M31M6M$0.31$0.25 – $0.3714
2010 Q3745M-2M-25M$0.12$0.09 – $0.1410
2010 Q4235M84M43M$0.15$0.12 – $0.1820
2011 Q1381M64M29M$0.32$0.26 – $0.3816
2011 Q2366M56M24M$0.26$0.21 – $0.3120
2011 Q31.5B11M-11M$0.21$0.17 – $0.2511
2011 Q4328M-10M-32M$-0.33$-0.40 – $-0.2612
2012 Q1399M16M-5M$-0.26$-0.31 – $-0.2110
2012 Q2485M6M-16M$-0.20$-0.24 – $-0.167
2012 Q3305M10M-12M$-0.27$-0.32 – $-0.2217
2012 Q41.5B10M-11M$-0.23$-0.27 – $-0.1820
2013 Q1321M54M22M$-0.14$-0.16 – $-0.1119
2013 Q2140M5M-14M$-0.07$-0.08 – $-0.058
2013 Q3517M14M-12M$-0.38$-0.46 – $-0.309
2013 Q4441M12M-11M$-0.24$-0.29 – $-0.198
2014 Q1377M5M-18M$-0.12$-0.15 – $-0.1014
2014 Q3520M98M52M$0.56$0.45 – $0.679
2014 Q4653M126M72M$0.74$0.59 – $0.8915
2015 Q1514M114M63M$0.54$0.43 – $0.659
2015 Q2565M-13M-36M$0.29$0.23 – $0.3514
2015 Q3389M-22M-47M$-0.22$-0.26 – $-0.1710
2015 Q4442M-6M-36M$-0.69$-0.83 – $-0.5519
2016 Q1444M6M-21M$-0.41$-0.49 – $-0.337
2016 Q2915M13M-14M$-0.21$-0.25 – $-0.177
2016 Q311M-1.7B-1.7B$0.30$0.24 – $0.3618
2016 Q4453M-183M-211M$-0.20$-0.24 – $-0.1613
2017 Q28.6B45M13M$0.39$0.31 – $0.4616
2017 Q3614M67M28M$0.31$0.25 – $0.3717
2017 Q4401M74M33M$0.22$0.18 – $0.2620
2018 Q2382M49M15M$0.20$0.16 – $0.2415
2018 Q4600M-49M-77M$-0.63$-0.76 – $-0.5014
2019 Q1485M-7M-37M$-0.75$-0.77 – $-0.747
2019 Q2477M-4M-29M$-0.26$-0.26 – $-0.2611
2019 Q3456M12M-14M$-0.33$-0.33 – $-0.327
2019 Q4427M20M-6M$-0.15$-0.16 – $-0.1510
2020 Q1422M22M-5M$-0.08$-0.08 – $-0.089
2020 Q2402M9M-17M$-0.14$-0.14 – $-0.146
2020 Q3374M-24M-55M$-0.63$-0.64 – $-0.626
2020 Q4424M3M-27M$-0.26$-0.26 – $-0.266
2021 Q1458M-33M-63M$-0.45$-0.46 – $-0.446
2021 Q2548M1M-27M$-0.22$-0.22 – $-0.221
2021 Q3587M-39M-66M$-0.14$-0.14 – $-0.131
2021 Q4693M330M211M$-0.08$-0.08 – $-0.081
2022 Q1731M52M17M$0.34$0.34 – $0.351
2022 Q2881M-6M-34M$0.15$0.15 – $0.161
2022 Q3642M-49M-73M$-0.54$-0.55 – $-0.531
2022 Q4540M358M233M$-0.61$-0.62 – $-0.601
2023 Q1510M52M19M$-0.12$-0.12 – $-0.121
2023 Q2512M-13M-38M$0.03$0.03 – $0.031
2023 Q3501M-47M-80M$-0.15$-0.22 – $-0.072
2023 Q4477M395M256M$0.17$0.17 – $0.172
2024 Q1474M59M21M$-0.12$-0.13 – $-0.121
2024 Q2496M33M1M$0.01$0.01 – $0.011
2024 Q3536M79M30M$0.29$0.29 – $0.291
2024 Q4515M113M59M$0.56$0.55 – $0.581
2025 Q1578M108M53M$0.50$0.50 – $0.521
2025 Q2611M83M35M$0.34$0.33 – $0.351
2025 Q3628M156M87M$0.82$0.81 – $0.851
2025 Q4652M236M135M$1.28$1.26 – $1.321
2026 Q1636M270M165M$1.57$1.54 – $1.621
2026 Q2817M378M245M$2.33$2.30 – $2.411
2026 Q3952M433M280M$2.67$2.62 – $2.752
2026 Q4976M368M235M$2.23$2.19 – $2.303
2027 Q11.1B425M274M$2.60$1.93 – $3.503
2027 Q21.1B432M278M$2.64$2.60 – $2.731
2027 Q31.0B413M265M$2.52$2.47 – $2.601
2027 Q41.1B400M255M$2.42$2.38 – $2.501
2028 Q1942M272M165M$1.57$1.54 – $1.622
2028 Q2936M336M209M$1.99$1.96 – $2.052
2028 Q3937M331M205M$1.95$1.92 – $2.012
2028 Q4937M305M187M$1.78$1.75 – $1.842

Corporate

Insider Trading (last 12mo)

Open-market only (Form 4 P-Purchase + S-Sale). Excludes grants, option exercises, tax withholding, gifts.
Officers & directors
Buys ($, 12mo)
$0
0 txns · 0 insiders · 0 sh
Sells ($, 12mo)
$26.24M
11 txns · 8 insiders · 502,249 sh
Major holders (≥10% beneficial owners)
Buys ($, 12mo)
$0
0 txns · 0 insiders · 0 sh
Sells ($, 12mo)
$326.81M
1 txn · 1 insider · 6,315,245 sh
Recent transactions
DateSideInsiderTitleSharesPriceDollarsOwned $
2026-03-25SELLTrpkovski Peter Aofficer: EVP, CFO16,739$50.51$845K$3.24M
2026-03-16SELLGary Jesse Edirector, officer: President and CEO150,000$55.47$8.32M$7.91M
2026-03-12SELLCalloway Kenneth Lofficer: SVP, Human Resources18,000$58.00$1.04M$1.44M
2026-03-11SELLHoffman Robert Fofficer: SVP, IT and CAO10,529$56.51$595K$3.20M
2026-03-04SELLGLENCORE INTERNATIONAL AG10 percent owner6,315,245$51.75$326.81M$630.56M
2026-03-04SELLHoffman Robert Fofficer: SVP, IT and CAO10,000$56.33$563K$3.78M
2026-03-03SELLAboud Mattofficer: SVP, Strategy & Business Dev't2,971$52.67$156K$3.42M
2026-03-02SELLAboud Mattofficer: SVP, Strategy & Business Dev't12,126$52.50$637K$3.56M
2026-02-27SELLHafberg Agust Fofficer: SVP & Chief Commercial Officer22,884$51.24$1.17M$2.31M
2026-02-25SELLGudlaugsson Gunnarofficer: EVP - Global Operations43,000$54.10$2.33M$7.38M
2026-02-23SELLDeZee Johnofficer: EVP, GC and Secretary66,000$50.72$3.35M$4.95M
2026-01-23SELLGary Jesse Edirector, officer: President and CEO150,000$48.19$7.23M$14.10M
v2 analysis (legacy, 2026-08-06) — for comparison onlyclick to expand

Thesis

Century has moved from a fragile, underutilized smelter operator to a substantially healthier domestic aluminum producer. The operational trajectory is favorable: Mount Holly is fully restarted, Grundartangi Line 2 is returning earlier than expected, Jamalco has added self-generation capacity, and growth CapEx should decline. The balance sheet is also much stronger, with debt reduction, substantial cash, tax-credit receipts, and insurance recoveries. The main issue is that the current earnings surge is not a clean through-cycle run rate. Aluminum prices and U.S. regional premiums are unusually high, and derivative positions can limit upside or create losses when prices move. The business remains capital intensive and exposed to energy, labor, operating, and geopolitical risks. Oklahoma offers substantial optionality but also carries permitting, financing, power-contract, execution, and political risk and should not be capitalized as an operating asset yet. The base case therefore assumes good execution but meaningful normalization in pricing. That still produces attractive cash generation and a healthier business, while the bear case reflects how quickly value can compress when a commodity margin cycle turns.

Trade Signal

Trade rating
-6.3/10
Short
Horizon
~4mo
gpt-5.6-luna2026-08-06 · saw $45.95-31.8% since

Short, with the core issue that a highly cyclical aluminum producer is priced at roughly twice the analyst's normalized equity value despite peak-like premiums and earnings already reflected in the stock.

Temporary mispricing+2.0

The stock rose from $39.18 at year-end 2025 to $50-$55 in February-March, then briefly reached $66-$69 in April-May as the U.S. aluminum shortage, elevated Midwest premiums, Mount Holly restart, and the broader tariff/reshoring theme were capitalized. It fell to about $46 by late June after the Oklahoma AG lawsuit, concerns about premium normalization and hedging, and the Grundartangi/commodity-risk debate; July was mostly drift between $41 and $47. The Q2 earnings print on August 6 produced essentially no move despite $327 million of adjusted EBITDA, restored capacity, and stronger cash, suggesting the market had already priced the operational recovery. The decline from the peak was a partial correction, not a full repricing: the stock remains far above the analyst's normalized value and current FCF yield is only 3%. This is a durable overvaluation risk more than a temporary panic dislocation, though the already-large decline makes the short timing-sensitive.

Market view+1.0

The market is constructive but no longer euphoric. Consensus is Hold, with a $55 average target, and the bull narrative emphasizes U.S. reshoring, tariffs, a projected aluminum deficit, restored capacity, and the Oklahoma option. Bears focus on peak-cycle Midwest premiums, hedging asymmetry, energy costs, project risk, and the possibility that current earnings are not sustainable. The stock is off its $68.77 high and fell roughly 25% over three months, so some skepticism is already present, but 16.6% short interest and substantial call open interest indicate a crowded, volatile debate rather than an ignored stock. Insider and Glencore selling are not reflected adequately in the bullish target narrative.

Inflectionwindow ~3mo-3.0

The operational inflection has largely already occurred: Mount Holly is restored, Grundartangi is restarting, Jamalco has new self-generation, and CapEx is falling. That is a real improvement, but it is visible in the recent $470 million TTM EBITDA and the stock's 123% one-year gain. The analyst's normalized/base case of roughly $300 million owner earnings is well below current earnings, while consensus data is sparse and inconsistent. The next major strategic event, Oklahoma, is years from operating earnings and faces legal, financing, and power-contract risk. Thus there is no large unpriced positive inflection; the more likely surprise is normalization.

Catalysts
  • ▲2026-10 to 2026-11 · Q3 2026 earnings and first full-quarter Mount Holly contribution — Expected in late October or early November; higher restored volumes and Jamalco self-generation savings could support EBITDA, though hedge settlements and energy costs may offset part of the benefit.
  • ▲2026-Q4 · Grundartangi Line 2 transformer replacement completed — Replacement units are expected in Q4; a clean return to normalized output would remove a key operational overhang and improve cash generation.
  • •2026-12 · Oklahoma smelter FID, financing and power-contract update — Management targets FID and groundbreaking by year-end, but the Oklahoma AG lawsuit and unresolved financing/power arrangements create substantial delay risk; strategic upside is not near-term earnings.
  • ▲2027-02 · 2026 year-end operating and cash-flow update — With growth CapEx largely complete, investors should see whether restored production converts into sustained free cash flow rather than merely peak commodity EBITDA.
  • ▼H2 2026 to 2027 · Normalization of Midwest aluminum premiums or LME prices — A retreat from exceptionally elevated regional premiums would expose how much of current earnings is cyclical and could drive a valuation reset.
Flow-6.0

Clearly negative. Officers and directors recorded no purchases and roughly $27 million of sales over 12 months; Glencore sold approximately $327 million of stock, while major-holder sales totaled roughly $599 million. Trailing dilution is 6%, and there is no disclosed buyback or committed shareholder-return program. Short interest is already 16.6% of float, creating squeeze risk but not favorable underlying flow.

Floor / Ceiling-2.0

The balance sheet provides some support: cash after tax-credit and insurance receipts is above total debt, and the company is solvent even in the analyst bear case. However, there is no hard asset-value floor near $46 because aluminum smelting earnings are highly cyclical, sustaining capital remains necessary, and the current 3% FCF yield does not provide meaningful valuation support. The principal ceiling is more important: insider and Glencore selling, 6% trailing dilution, and investors' willingness to capitalize peak premiums at only a modest multiple.

Buyability

Poor as a long at $45.95: the company is operationally improved and balance-sheet risk is low, but current valuation depends heavily on unusually high aluminum prices and Midwest premiums. A marginal buyer could be attracted by the U.S. supply-shortage and tariff story, but the next buyer is likely paying for peak-cycle earnings rather than durable normalized cash flow.

Fear vs Greedfear 5/10 (-2.0)greed 7/10 (+3.0)

Fear is stronger than greed at this price. The business has genuinely improved, but the market is valuing a cyclical aluminum producer at roughly 10x TTM EBITDA and 32x EV/FCF after an exceptional pricing period. The main risk to the short is that tight U.S. aluminum markets and tariffs keep premiums elevated longer than expected, producing another upside earnings print.

Valuation

Our Target
$2.3B-26%
Market Should Pay
$2.4B-22%
target ×1.05 (greed premium)
Current Market Cap
$3.0BNeutral
What Changed
transcript · 2026-08-06
+12%fair value on this information

The Q2 call confirmed that Mount Holly reached full production on schedule, Grundartangi Line 2 restarted roughly six months earlier than initially expected, and Jamalco's TG4 began reducing grid dependence. It also provided a stronger Q3 EBITDA outlook, confirmed that growth CapEx is largely complete, disclosed additional July tax-credit and insurance receipts, and described the potential 25%-versus-50% tariff benefit and Oklahoma financing work in more detail. These operational and liquidity developments were not fully known before the call.

▸ How the cases moved

The bear equity value rises from approximately $900M to $1,050M as all operating assets return to production and near-term liquidity improves, although commodity downside remains. The base case rises from approximately $2,450M to $2,925M: full Mount Holly and near-full Grundartangi capacity, Jamalco self-generation, lower growth CapEx, and stronger cash conversion increase expected owner earnings. The bull case rises from approximately $4,900M to $5,500M because the tariff-import opportunity and Oklahoma progress add strategic upside, though the project is still not valued as an operating asset. Bear probability falls from 0.30 to 0.25; base rises from 0.50 to 0.55; bull remains 0.20.

2-Year Plausible Outcomes
bear25%
$1.1B
rev -4%/yrOE $120M

Aluminum prices and Midwest premiums normalize sharply, while hedges and higher energy costs compress margins. Mount Holly and Grundartangi operate, but the incremental volumes do not offset weaker pricing; Oklahoma is delayed by permitting, financing, or power-contract issues. The company remains solvent but returns to a much more cyclical, low-return earnings profile.

▸ Valuation

5.0x $250M EBITDA = $1,250M EV − $200M net debt = $1,050M equity

base55%
$2.9B
rev +4%/yrOE $300M

The restored assets deliver substantially higher volumes, Jamalco captures part of the self-generation savings, and growth CapEx falls toward sustaining levels. Aluminum pricing and regional premiums retreat from exceptional 2026 levels but remain supportive of domestic smelting. Oklahoma advances toward FID without contributing material operating earnings within the two-year period; cash generation broadly offsets sustaining investment and leaves the company near net cash.

▸ Valuation

6.5x $450M EBITDA = $2,925M EV − $0M net debt = $2,925M equity

bull20%
$5.5B
rev +12%/yrOE $450M

A prolonged U.S. aluminum shortage, strong Midwest premiums, tariff protection, and full utilization combine with Mount Holly, Grundartangi, and Jamalco improvements. The Oklahoma project secures its power and financing arrangements and the tariff-related import opportunity becomes credible, improving the strategic value of the platform even before the new smelter operates. High cash conversion, limited sustaining CapEx, and net cash support a premium cyclical multiple.

▸ Valuation

8.0x $650M EBITDA = $5,200M EV − ($300M net cash) = $5,500M equity

▸ Target Rationale

The probability-weighted discounted scenario value is $2,377M. I set the analytical target at $2,250M, below the mechanical model, because the model's EBITDA multiples do not fully capture the company's commodity-cycle exposure, hedging asymmetry, recurring sustaining-capital needs, dilution risk, and the unresolved Oklahoma funding and permitting path. The target still recognizes the materially improved balance sheet, tax-credit and insurance receipts, and near-term operating improvements.

Business Quality & Sentiment

Business Quality (price-independent)
Business quality6/10
Situation now8/10
Trajectory8/10
Risk6/10
Governance6/10
Insolvency prob (2yr)2%
Outcome uncertainty8/10

Recent Research & News

Recent Research & News

2026-06-21

Company news

Q1 2026 Earnings Report (May 7, 2026)

Century Aluminum reported its Q1 2026 financial results, highlighting a transition toward improved profitability. Net sales reached $649.2 million, a sequential increase of 2.4% from Q4 2025, driven primarily by strong realized aluminum prices and high regional premiums. Net income attributable to Century surged to $337.5 million, up from $1.8 million in the prior quarter, which was heavily boosted by a one-time gain of $287.9 million from the sale of the Hawesville, Kentucky smelter site. Adjusted EBITDA stood at $231.4 million.

Despite the profit gains, total shipment volumes declined by 12.4% sequentially to 122,865 tonnes. This drop was caused by the full-quarter operational impact of a transformer equipment failure on Line 2 at the Grundartangi smelter in Iceland. Century has received $83 million in total insurance proceeds to date related to this incident and initiated a progressive restart of the line in April 2026, targeting a full recovery by July 2026. Management also projected a 2026 global aluminum deficit of 1.4 million tons, driven by Middle East geopolitical tensions and the closure of the Strait of Hormuz.

Mt. Holly Smelter Expansion (April 16, 2026)

Century announced the commencement of first hot metal production at its Mt. Holly, South Carolina plant following a major expansion project. The expansion is projected to reach full capacity by the end of June 2026. Once fully operational, this initiative is expected to boost overall U.S. domestic primary aluminum production by approximately 10%, strengthening Century's position as the leading primary aluminum producer in the United States.

---

▸ Thesis-test Findings
U.S. Midwest Aluminum Premium Historical Spot Prices 2026
  • Findings: The U.S. Midwest aluminum premium (the regional cash-settled surcharge paid over the LME benchmark) skyrocketed to historic highs in early 2026. Fueled by increased trade protectionism—specifically the doubling of Section 232 tariffs to 50% in mid-2025—the premium exceeded $2,000 per metric ton ($0.91/lb) for the first time on January 8, 2026, eventually reaching an all-time record of $2,182 per metric ton ($0.99/lb) in late January. As of June 2026, CME futures indicate the premium remains highly elevated at approximately $1.155/lb ($2,546/tonne).
  • Bull/Bear Impact: This is a major bull case tailwind for Century Aluminum. High domestic premiums allow Century to capture significantly higher realized pricing on its domestic output (as demonstrated in their Q1 results), shielding margins from lower global LME benchmarks. However, it poses severe headwind challenges for domestic end-users (such as Molson Coors, which forecasted a minimum $125 million headwind for 2026 due to the premium).
EGA Century Aluminum Oklahoma Smelter Project FID Update
  • Findings: On January 26, 2026, Century joined Emirates Global Aluminium (EGA) in a 40/60 joint venture (Oklahoma Primary Aluminum) to build a new 750,000-tonne/year greenfield smelter in Inola, Oklahoma. In February 2026, Bechtel was awarded the preparatory engineering contract. During the May 2026 earnings call, Century CEO Jesse Gary stated that negotiations for financing and a competitive power deal with the Public Service Company of Oklahoma were progressing, with plans to reach a Final Investment Decision (FID) and break ground by the end of 2026.
  • Bull/Bear Impact: A critical bear case risk emerged on June 2, 2026, when Oklahoma Attorney General Gentner Drummond filed a lawsuit in the Rogers County District Court seeking to block the $4 billion project. The AG's petition raises concerns over environmental public nuisance (emissions/wastewater) and national security risks stemming from EGA’s 60% foreign-sovereign stake (Abu Dhabi). While the JV has defended the project's adherence to state regulatory reviews (via the Oklahoma Department of Environmental Quality), this legal battle introduces major political and timing risks that could delay the final FID and groundbreaking.
Hawesville Data Center Redevelopment Critical IT Load Status
  • Findings: Following the sale of its idle Hawesville, Kentucky smelter site to TeraWulf Inc. on February 2, 2026, for $200 million, the site is undergoing transition into an AI-focused digital infrastructure campus. On March 20, 2026, TeraWulf signed a limited notice to proceed with Fluor Corp. to handle early engineering, master planning, and preconstruction. The critical load status for the planned facility is designed for a massive 480 MW of power capacity on the 790-acre site. The development will utilize the site's robust existing electrical infrastructure, including multiple high-voltage transmission lines and an on-site substation. Groundbreaking is planned for late 2026 with completion targeted in 2027.
  • Bull/Bear Impact: This is highly bullish for Century. Beyond the $287.9 million gain on sale realized in Q1, Century has retained a non-controlling minority equity stake in the project. This structure allows Century to benefit from the high-growth AI data center boom and future upside of the Hawesville site redevelopment while carrying zero operational or capital expenditure requirements.