Stocks/EXK

EXK

Endeavour Silver Corp.v3 4.8/10 · 2026-11-03
Basic Materials·Silver
$6.87
$1.8B market cap
v3 Rating
4.8/103.5–6.5
Setup
6.0/104.5–7.5
Fair Value
$6.80$4.00–$11.00-1%
DCF (10%)
$6.10-11%
Base IRR
+8%-10%–+22%
Visibility
wide±51%
Wall Street
$17.00 target(1 analyst last quarter)(11 buy, 2 hold, 1 sell)
Rating
Revenue (TTM)
$782.5M
Owner Earnings
$115M
Next-Yr Owner Earnings
-$10M
Growth
+12.0% × 5y
P / Next-Yr OE
--
Net Debt
$75M

Endeavour Silver Corp., headquartered in Vancouver, Canada, is a mining enterprise specializing in precious metals. The company is involved in the entire lifecycle of mineral properties, from acquisition and exploration to development, extraction, processing, refining, and reclamation, operating in both Mexico and Chile. While its primary focus is silver, Endeavour also actively seeks gold and other valuable metal deposits. Currently, the company manages two productive silver-gold mines in Mexico: the Guanaceví mine situated in Durango and the Bolañitos mine located in Guanajuato. In addition to these operating assets, Endeavour is progressing two significant exploration and development projects within Mexico: the Terronera property in Jalisco and the Parral properties in Chihuahua. Further expanding its portfolio, the company holds interests in three distinct exploration ventures in northern Chile: the Aida silver project, the Paloma gold project, and the Cerro Marquez project, which explores for copper, molybdenum, and gold. Originally incorporated in 1981, the company underwent a name change from Endeavour Gold Corp. to Endeavour Silver Corp. in September 2004, aligning its identity with its core silver mining activities.

2-Year Price History

$7.03+51.2%
$4.0$6.0$8.0$10$12$14Initial target $6.80 · 2026-11-03volNov 24Mar 25Jul 25Oct 25Feb 26Jun 26Oct 26

Valuation v3 Opus worker · 2026-11-03

Rating
4.83.5–6.5
Setup
6.04.5–7.5
Fair value (USD)
6.804.00 – 11.00
Upside vs 6.87
-1%
DCF (10%)
6.103.50 – 10.50-11%
Base IRR
8%-10% – 22%
Visibility
widerange ±51%
Sentiment
3/10
2026-11-03 · claude-opus-5-5 · priced at 7.03

Endeavour Silver (NYSE: EXK, $7.03 at the 3 Nov 2026 close, a new 52-week low, down 50% from February's $14) is a mid-tier Mexico/Peru silver-gold miner: Guanaceví (old, grades falling, about 2 years of reserves, kept alive with purchased ore), Kolpa in Peru (bought in 2025, expanded to 2,500 tpd) and Terronera (new, still ramping, with higher grades arriving now and the La Luz gold zone in 2027). The next big step is Pitarrilla, one of the world's largest undeveloped silver deposits: about $500-600M to build, a construction decision targeted for early 2027 and first production around 2030. Its feasibility study, due at the end of Q3, has still not been published. Silver has fallen from over $90 in February to about $50 (down 19% in a month, with the market pricing a December Fed hike) and gold to about $3,925. The company also had a weak Q3: a 12-day blockade at Terronera, a mill failure at Guanaceví, production at or below the bottom of guidance, $18M of extra Kolpa capex, the VP of Operations leaving, and downgrades from CIBC and Citi. At spot prices the business makes about $250-280M of EBITDA but only about $110-120M of unlevered owner earnings, because Mexican and Peruvian taxes, royalties, mining duties and roughly $90M a year of sustaining capex take most of it. That means EV of about $2.16B is about 8x spot EBITDA and about 18-20x owner earnings, not the 5x trailing that the $70-silver first half implies. A DCF at a flat $50 silver price, paying for Pitarrilla out of cash flow, gives about $6.10 a share, with year-5 FCF of about $290M valued at 10x. Every $10/oz of silver moves that by about ±$3.5-4. The stock is fairly priced for spot silver. It is a geared call on the metal, not a mispriced business. Sentiment is poor (3/10) but this is not capitulation: silver at $50 is still nearly double its 2024 level, and the sell-side's $14-15.50 targets rest on much higher price decks and will probably be cut after the 9 Nov Q3 results and guidance reset. Rating 4.8/10: no margin of safety against the metal price, Mexican permitting and security risk, a long record of share dilution, and no capital return until about 2030. Research 6/10: if silver stabilizes at $55-60 and the Pitarrilla feasibility study comes in strong (or a major bids for Pitarrilla), a 40-50% re-rate is realistic, and the 9 Nov results plus the feasibility study will settle most of the open questions.

A deep dive would have to establish: Whether the delayed Pitarrilla feasibility study shows a buildable, permit-ready (TSF) project at about $550M capex that still earns well above 10% at $45-50 silver without large equity dilution, and what sustainable 2027 AISC looks like after the 9 Nov guidance reset.

Owner earnings, TTM
$115M$50M – $190M
Realistic peak profit
$300M$170M – $520M
Growth rate
12.0%2.0% – 20.0%
Years of growth
52 – 8
Market cap
$2.1B$2.1B – $2.1B
EV
$2.2B$2.1B – $2.2B
Net debt
$75M$20M – $150M
Capital return / cap
0.0%0.0% – 1.0%
P/E
20.0×11.0× – 40.0×
EV/EBITDA
7.8×5.5× – 11.0×
FCF yield
5.5%2.0% – 10.0%
Projected FCF, base case (USD millions)
Y1-$10M-$80M – $70M
Y2-$125M-$230M – -$20M
Y3-$80M-$190M – $30M
Y4$105M-$30M – $230M
Y5$290M$70M – $490M
Competition: A price-taking, high-cost (Q2 AISC $37/oz) silver producer competing for capital with lower-cost peers such as Pan American, Fresnillo, First Majestic and Hecla; its edge is torque to silver and the scarce, large undeveloped Pitarrilla deposit.
Governance: No fraud or control red flags; the concerns are a long history of equity dilution (ATMs, share-funded acquisitions), repeated schedule slips, and a Q3 2026 departure of the VP of Operations.
Research (expand)

What the company does

Endeavour Silver is a Vancouver-based silver-gold miner. It reports in USD and is listed on NYSE (EXK) and TSX (EDR). It now runs three mines after selling Bolañitos in January 2026:

  • Terronera (Jalisco, Mexico): a new 2,000 tpd underground mine that declared commercial production in October 2025. It ran on diesel until the LNG plant was commissioned in June-August 2026, which should roughly halve power cost. Management deliberately mined lower-grade stockwork first. Silver grade rose from 126 g/t in Q2 to 152 g/t in Q3, with recoveries at 91% by September. The high-grade La Luz gold zone (about 4 g/t Au in the feasibility study) has been pushed to 2027. Q2 AISC was $26.42/oz.
  • Guanaceví (Durango, Mexico): the legacy cash cow, now in decline. Reserves cover about 2 years. Silver grades fell 24% year on year in Q3. Purchased third-party ore is about 25% of direct cost, there is a 16% NSR to the Frisco group, and Q2 AISC was $52/oz. Mine life is being stretched by mining lower grades and buying ore.
  • Kolpa (Huancavelica, Peru): a polymetallic mine (Ag-Pb-Zn-Cu) bought in May 2025 and expanded to 2,500 tpd at the end of Q1 2026. Management says it can run 15-25 years, but it needs catch-up capex: dry-stack tailings, substations, water treatment and a camp, which added $18M to 2026 capex, of which $5M was overrun.
  • Pitarrilla (Durango): one of the world's largest undeveloped silver deposits, with about 430Moz Ag indicated plus lead and zinc. The plan is a 3,500-4,000 tpd underground mine costing about $500-600M (management's own estimate). The feasibility study was promised for 'end of Q3 2026' and has not appeared. The gating item is permitting the dry-stack tailings facility (TSF) in Mexico. The goal is '30 by 30' (30Moz AgEq by 2030).

2026 guidance was 14.6-15.6Moz AgEq (8.3-8.9Moz Ag, 46-48koz Au), AISC $27-28 at a $36-38 silver assumption, and $158M capex, since raised to $181M. Year to date (9 months) the company produced about 10.4Moz AgEq. Full-year output will be 'at or slightly below the low end'. Revised guidance and Q3 financials come on 9 November 2026.

The investment case (and the problem)

The bull case is simple. Production capacity has roughly doubled in two years (Kolpa plus Terronera). Terronera's grades are finally rising. Pitarrilla could roughly double the company again around 2030. The balance sheet is fine: about $300M+ of cash after the VAT refund against $350M of 0.25% converts due 2031, convertible at $12.455. At $70 silver (the Q2 average) the company was running at about $360M of annualised adjusted EBITDA, which made the stock look like 5-6x EBITDA.

The problem is that the metal deck has moved. Silver is about $50 (tradingeconomics, 3-4 Nov 2026; down 19% in a month and down from over $90 in February). Gold is about $3,925, down from $5,000+ early in the year. The market is pricing a December rate hike. EXK is a high-cost, high-tax, high-royalty producer: consolidated AISC was $37/oz in Q2. Some of that cost falls with the silver price, because royalties, purchased ore, profit sharing and mining duties are linked to it (about -$13M a quarter of cost for -$20/oz silver, using management's per-tonne sensitivities). Even so, the margin at $50 is thin.

What it earns today (real owner earnings)

Q2 2026 actuals at $70.16 silver and $4,305 gold: revenue $212.1M, cash cost of sales about $112M, G&A $2.9M (helped by a DSU gain), exploration $6.4M, adjusted EBITDA $90.0M. Operating cash flow before working capital was only $44.9M. The rest went to cash taxes ($44.5M of current tax in H1 alone, including Mexico's 8.5% special mining duty) and to settling the legacy gold forward swaps. About 45koz remained at March 31 at $2,311/oz through June 2027, with a liability of $63.4M at June 30. Sustaining capex ran at $18.9M a quarter, against $91M guided for the year.

Re-pricing Q2 to spot ($50 Ag, $3,925 Au, base metals flat): revenue about $166M, direct costs about $99M after price-linked relief, EBITDA about $56M a quarter, or about $225M a year at 2026 volumes and about $270-280M on 2027 volumes. That rises with Terronera grades and La Luz gold, partly offset by Guanaceví's decline. Unlevered owner earnings for 2027 at spot:

  • EBITDA about $275M
  • less cash taxes about $65-70M (30% income tax plus 8.5% special mining duty plus 1% extraordinary duty in Mexico; Peruvian income tax and royalty)
  • less sustaining capex and mine-life exploration about $90M
  • equals about $115-120M. SBC is small, about $3-5M, and already inside G&A.

Only about 40-45% of EBITDA reaches owners. The gold-hedge drag (about $45M left, ending June 2027) is treated as debt, not as a running cost.

Balance sheet and EV

Shares are about 296.1M (stockanalysis; Q2 weighted basic 296.1M), giving a market cap of about $2.085B at $7.03. Cash at June 30 was $236.6M, plus about $70M of VAT refund due in Q3, plus Q3 cash flow, less Pitarrilla, capex and hedge settlements. I estimate year-end cash at about $290-315M. Against that:

  • $350M of 0.25% converts due 2031, convertible at $12.455. That would be 28M shares if converted, but they are well out of the money at $7.
  • about $10M of equipment loans
  • about $45M of remaining gold-swap liability

Net debt is about $75M (range $20-150M). EV is about $2.16B: about 7.8x 2027 spot EBITDA, about 18-19x unlevered owner earnings, and an owner-earnings yield on market cap of about 5.5% (interest is negligible at a 0.25% coupon). On trailing H1 2026 numbers (about $397M annualised adjusted EBITDA at $77 silver) it looks like 5.4x. That is the optical cheapness that is now gone.

Five-year free cash flow (base deck: $50 Ag, $3,900 Au flat; unlevered, after tax, SBC, sustaining and growth capex including Pitarrilla)

| Year | Core mines owner earnings | Growth capex (Pitarrilla, Kolpa) | FCF |

|---|---|---|---|

| 2027 | ~$120M | ~$130M | ~-$10M |

| 2028 | ~$125M | ~$250M | ~-$125M |

| 2029 | ~$120M | ~$200M | ~-$80M |

| 2030 | ~$115M + ~$40M Pitarrilla start-up | ~$50M | ~+$105M |

| 2031 | ~$110M + ~$180M Pitarrilla | - | ~+$290M |

Assumptions behind this table:

  • Pitarrilla at steady state: about 12Moz AgEq a year, about $510M of revenue at $50, about $280M of EBITDA and about $175-180M of after-tax FCF.
  • Core mines: Guanaceví keeps going on purchased ore and exploration success, but is a fading contributor.
  • Funding: the 2027-29 build pushes peak net debt to about $250-300M. That is fundable with a project loan or stream, but equity dilution is a real risk given history: the share count went from about 190M to 296M in four years through ATMs and the Kolpa deal.

What the company looks like in 5 years

If Pitarrilla gets permitted and built, by 2031 this is a roughly 25-30Moz AgEq senior silver producer. It would have one long-life cornerstone asset (Pitarrilla, 15+ years), Kolpa (15-25 years claimed) and Terronera, with Guanaceví probably closed or marginal. That is a growing income stream with a real company downstream, not a corpse. Mining FCF is still a depleting, price-taker stream, so I value year-5 FCF at 10x (range 8-12x).

I have low confidence in the projection because of three things:

  • the silver price (every $10/oz is about ±$65M of core FCF and about ±$80M of Pitarrilla FCF a year)
  • Mexican TSF permitting and timing
  • capex overruns (Terronera itself ran far over its original budget)

Fair value

  • DCF at 10%: PV of 2027-31 FCF about $80M, plus PV of 2031 terminal value (290 × 10 = $2.9B, discounted to about $1.80B), gives EV of about $1.88B. Less about $75M of net debt, that is equity of about $1.81B, or about $6.10/share.
  • Sensitivity: about $10/share at $60 silver and $4,200 gold; about $3.50-4 at $40 silver, where Pitarrilla probably gets deferred; about $12-13 at the Q2 deck of $70.
  • Base IRR: year-5 equity of about $3.0B (about $10/share, with net cash by then) against $7.03 today is about 7-8% a year. That is below the 10% hurdle.
  • Fair value about $6.80. I give a little credit above the DCF for the take-out optionality: Pitarrilla is a scarce, large silver asset that the majors (Pan American, First Majestic, Fresnillo, Hecla) would look at. There is also cheap 0.25% convert funding.

This is not a <7x-EV/EBITDA buyout case on owner economics, and it is not a covered-call floor setup. ATM IV is about 65%, but earnings are not predictable and the stock is not at a valuation floor. It moves with the metal.

Management, governance, competition

CEO Dan Dickson (former CFO) and CFO Elizabeth Senez are straightforward on calls and candid about overruns. There is no fraud or governance red flag. The weaknesses are a long record of funding growth with equity (ATM programs and the Kolpa share deal), repeated schedule slips (Terronera, the LNG permit, the Pitarrilla feasibility study now late), and the departure of the VP of Operations in Q3. Management says plainly that there will be no dividends or buybacks until Pitarrilla is built (about 2030): all cash is 'earmarked for Pitarrilla'.

Competition is irrelevant in the usual sense, because the company is a price-taker. What matters is position on the cost curve, and EXK is high-cost (AISC $37 against peers such as Pan American, Fresnillo and First Majestic in the $20s-30s). That makes it among the most levered to silver in both directions.

Risks:

  • Mexican security and community blockades (Terronera in Feb and Aug 2026)
  • slow Mexican permitting
  • a stronger peso inflating costs
  • Guanaceví's 2-year reserve life
  • Peruvian informal mining pulling away labour
  • the gold hedge through June 2027
  • equity dilution to fund Pitarrilla

Sentiment: 3/10 (disliked and falling, not yet capitulation)

  • Price action: the stock is at a fresh 52-week low ($7.03, the bottom of a $7.03-14.12 one-year range), down 50% from February and down 18% over the past month.
  • Ratings and the macro: CIBC cut to Hold (22 Sep) and Citi to Market Perform (9 Oct). Silver is breaking down on rate-hike fears.
  • Short interest: about 22M shares (about 7% of shares), 2.6 days to cover.
  • Targets: the sell-side has not capitulated. The MarketBeat consensus is Moderate Buy with a $14 target (range $11-17); HCW is at $17 and B. Riley at $14. Stockanalysis shows 7 analysts averaging $15.50. Those targets sit on $60-80 silver decks and will probably be cut after the 9 Nov guidance reset. That second leg of capitulation (target cuts, a guidance miss, a possible weak or late Pitarrilla feasibility study) may still be ahead.
  • The metal: silver at $50 is still historically rich (about $30 in 2024), so this is not 'blood on the ground' for the metal.

A better entry probably comes after the guidance reset, or if the Pitarrilla feasibility study disappoints, when the stock trades closer to $5-5.50 with silver holding $45-50.

Financials — Adjusted

Adjusted · TTM 2026-Q3 · USD

TTM & Fiscal-Year P&LTTM2025202420232022
Revenue783+137%462+112%218+6%205-2%210
Gross profit274+790%62.2+48%42.1+15%36.6-29%51.5
Operating expenses27.3-25%32.3-4%33.7+21%27.9-1%28.1
▸Adj EBITDA345+607%105+165%39.5+5%37.5-24%49.6
▸Adj OCF112+329%25.8+19%21.7-25%29.1-36%45.7
CapEx-133-170-195-118-110
Adj FCF-20.5-144-174-88.7-64.1
Interest expense28.514.00.891.260.94
▸Adj net income1731.74-2.47-4.69-224%3.77
▸Owner's earnings25.0--------

claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2022→FY2025 +2026YTD

Where the Cash WentTotal2026YTD2025202420232022
▸Claimed: EBITDA378100%284100%-16.210.0100%47.9100%52.0100%
FCF (OCF−capex)-398-105%44.416%-107-175-106-221%-54.9-105%
Net income18.05%15655%-119-31.5-314%6.1213%6.2012%
▸Capital returned-560-148%23.58%-254-237-54.8-114%-37.9-73%
Buybacks-301-1.40-71.0-122-61.7-44.1
Dividends0.000.000.000.000.000.00
Interest paid33.816.814.00.891.260.94
Debt paid down-2948.13-197-1165.635.27
▸Reinvestment970257%71.625%475195118246%110211%
Capex (PP&E)68693.6170195118110
Intangibles & M&A40.9-31.172.0-0.020.000.00
Leases signed (net Δ)2439.13234---0.060.07
Retained / other12132%52.118%75.062.3622%-51.2-107%-17.0-33%

negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.

Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.

Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).

SBC over the Total window: 15 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.

Balance SheetTTM2025202420232022
▸Assets (total)12891233719475399
▸Liabilities (total)54965523588.583.5
Net debt (incl. leases)-43.427.412.7-30.9-76.5
Net debt / Adj EBITDA-0.130.260.32-0.82-1.54
Net debt / Adj FCF----------
Adj EBITDA / interest12.17.4744.429.852.5
Shares outstanding296262262262262
Dilution (YoY)+0.0%+0.0%+21.3%+9.4%+11.5%
Employees15392.002.002.002.00
MarginsTTM2025202420232022
Gross margin35.0%+25.713.4%-5.919.3%+1.517.8%-6.724.5%
Adj EBITDA margin44.1%+29.322.6%+4.518.1%-0.118.3%-5.423.6%
Adj OCF margin14.4%+6.45.6%-4.410.0%-4.214.2%-7.621.8%
Adj FCF margin-2.6%+42.9-31.1%+48.6-79.7%-36.5-43.2%-12.7-30.5%
Net income margin16.9%+45.3-25.8%-11.3-14.5%-17.43.0%+0.03.0%
Adj NI margin22.1%+28.40.4%+1.5-1.1%+1.1-2.3%-4.11.8%
ROIC (adj, after-tax)18.5%2.9%1.1%1.4%4.6%
Cost of debt11.6%8.9%1.3%----

Earnings Calls

11 calls

Earnings Call · 2026 Q2

2026-07-30

Endeavour Silver delivered a materially stronger second quarter, benefiting from higher production, record metal sales, improved operating leverage and a stronger balance sheet. The company produced nearly 2 million ounces of silver and more than 10,000 ounces of gold, equivalent to 3 million silver-equivalent ounces, a 36% increase from the prior-year quarter. Revenue climbed 150% to $212 million, mine operating earnings rose to $74 million from $7 million, and mine operating cash flow before taxes increased 300% to $100 million. Adjusted net earnings were $45 million, or $0.15 per share. Cash stood at $236 million and working capital at $214 million at quarter-end. A further approximately $70 million VAT refund from Mexico is expected in Q3, which management considers on track and effectively raises near-term liquidity toward $300 million. Terronera’s ramp-up continued, with quarterly throughput remaining consistent while the plant focused on improving recoveries and grinding efficiency. Silver grades were in line with plan and are expected to increase incrementally through Q3 and the remainder of the year as mining reaches higher-grade portions of the Terronera shoot. Management does not expect an immediate step change, as some lower-grade and outside-resource material will continue to be processed. The higher-grade La Luz area, which contains the approximately 4 g/t gold material cited in the feasibility study, has been deferred primarily to 2027; 2026 gold grades are expected to remain near 2 g/t. The LNG plant was commissioned in June without significant technical problems, although permitting took longer because of additional emergency-response and storage requirements. The mine was expected to connect to LNG generation by mid-August, replacing diesel gensets. Exploration drilling has restarted at Terronera for the first time since 2020, and a new resource is expected by year-end. Management does not currently plan a new technical study or mine plan. Kolpa’s crusher and ball-mill expansion increased plant capacity to 2,500 tonnes per day, and throughput has occasionally exceeded that level. The 2026 capital budget was increased by $18 million. Roughly $5 million represents overruns or additional requirements, while about $13 million accelerates investments initially planned for 2027. Projects include power substations, water treatment, tailings expansion and filtration, conversion toward dry-stack tailings, and a new camp. Management characterized most of the spending as one-time capital needed to secure Kolpa’s long-term viability, retain skilled labor and support a potentially much longer mine life. An updated resource and mine plan is expected by year-end. Kolpa grades should remain broadly stable over the next six months. At Guanacevi, AISC was pressured by lower grades, more expensive purchased ore, royalties, special mining duty and profit sharing. Purchased ore represented roughly one-fifth of quarterly throughput, remains profitable at a 30%-33% margin, and helps satisfy local operating arrangements while extending mine life. Company-wide AISC guidance remains unchanged, though actual costs are currently above guidance due to higher silver prices, which increase royalties, duties and other profit-linked costs. Budget assumptions included roughly 3% general inflation and approximately 5% labor inflation, while diesel and supply-chain costs added pressure in Q2. Peso hedging continues selectively for operating expenses, but no additional metal hedging is planned after silver collars expired and gold hedges continue through June 2027. Pitarrilla’s feasibility study remains scheduled for late Q3. Some planned spending will shift into 2027 because equipment purchases and long-lead deposits depend on study completion. The main permitting hurdle is approval of the dry-stack tailings facility; other key project permits are already in place. Management currently estimates construction capital at $500-$600 million and mill throughput at 3,500-4,000 tonnes per day. Current and future cash generation is expected to fund Pitarrilla, while dividends or buybacks are more likely after the project is built and the company reaches greater scale, potentially around 2030.

Analyst Q&A (19)
▸
Were there unexpected bottlenecks or costs during Terronera’s LNG commissioning, and when would the mine and related facilities be fully connected to the LNG system?
Heiko Ihle · H.C. Wainwright
The LNG plant commissioning itself went smoothly, but permitting took longer because of new Mexican emergency-response and storage requirements following a late-2025 LNG incident. The LNG system was connected to the lower platform in early June and the upper platform by quarter-end; the mine was expected to switch from diesel generation by August 15.
▸
Given the approximately $250 million cash balance, what minimum cash level is needed, and when might shareholders see a special dividend or other capital return?
Heiko Ihle · H.C. Wainwright
Management expects eventually to return capital through dividends or buybacks, but near-term cash will support substantial growth plans, including Pitarrilla. The long-term convertible debt is about $350 million, and Pitarrilla construction is currently estimated at $500-$600 million. Once Pitarrilla is built, potentially by 2030, the company should have the scale to consider shareholder returns.
▸
Should Terronera move immediately into higher grades in Q3, and should the first-year feasibility-study grades of more than 200 g/t silver and nearly 4 g/t gold be modeled in the second half of 2026?
Wayne Lam · TD Securities
Terronera’s higher silver grades should emerge incrementally from July through September, with Q3 expected to be higher than Q2 rather than showing an immediate step change. The roughly 4 g/t gold material from La Luz is now planned mainly for 2027, not 2026, while gold should remain near 2 g/t in the near term. The higher-grade Terronera shoot is being accessed earlier, although some lower-grade and outside-resource material will still affect results.
▸
After first-half AISC performance and higher silver prices, is the existing AISC guidance still realistic, considering expected efficiency gains and lower sustaining capital in the second half?
Wayne Lam · TD Securities
The company has not changed its AISC guidance, although current costs are well above guidance because higher metal prices increase royalties, duties and other costs. Increased Kolpa sustaining capital is partly offset by lead, zinc and silver by-product credits and operating efficiencies. Guidance was based on approximately $36-$38 silver, so outcomes vary significantly with analysts’ price assumptions.
▸
What is the forward Mexican peso hedging strategy, and might Endeavour extend silver hedging to protect Guanacevi margins as costs rise?
Wayne Lam · TD Securities
All previous foreign-exchange hedges have been unwound, but the company continues to hedge a modest portion of peso-denominated operating costs at Guanacevi and Terronera. The silver collars expired in June and were paid out July 2; gold hedges remain through June 2027. Management currently has no plans for additional metal hedging.
▸
What inflation assumptions were included in AISC guidance, and has realized inflation been higher than expected?
Cosmos Chiu · CIBC
The budget assumed roughly 3% general inflation and about a 5% labor increase, with labor ending slightly above that. Diesel and supply-chain inflation increased in Q2, partly reflecting geopolitical impacts, although Mexican fuel pricing is influenced by PEMEX. Management expects those pressures to continue but did not characterize their duration.
▸
How much does third-party purchased ore contribute to Guanacevi’s more than $50/oz AISC, and how should the company’s strategy and profitability of this material be viewed?
Cosmos Chiu · CIBC
Guanacevi’s higher AISC reflects lower grades, more expensive purchased ore, royalties, special mining duty and profit sharing. Purchased ore represented about 21% or more of quarterly throughput, with approximately 11,000-12,000 tonnes purchased. Direct costs were about $400 per tonne, including roughly $130 of purchased ore; the company earns a 30%-33% margin on that material. Purchasing ore also satisfies local obligations, supports relationships and extends mine life.
▸
Is the increase in annual capital expenditure from $157 million to $181 million, including $18 million at Kolpa, unexpected spending, or investment that will generate future throughput and cost benefits?
Cosmos Chiu · CIBC
Of the additional $18 million, about $5 million represents overruns and authority-driven requirements, while approximately $13 million accelerates projects originally planned for 2027. The spending includes power substations, water treatment, tailings improvements, dry-stack preparation and a $3 million camp expansion. Some work could move into 2027, but the investments are intended to support a much longer operating life and higher throughput at Kolpa.
▸
How should investors view Kolpa’s additional 2026 spending over the longer term: catch-up capital, or evidence of permanently higher sustaining costs?
Alexander Terentiew · National Bank
Kolpa’s additional spending is primarily one-time investment associated with expanding from 2,000 to 2,500 tonnes per day and addressing shortcomings identified after the acquisition. It includes tailings filtration and dry stacking, accommodations, power substations and water treatment. Management does not expect the spending to represent a permanently higher sustaining-cost base.
▸
When will an updated resource estimate and mine plan for Kolpa be released?
Alexander Terentiew · National Bank
An updated Kolpa resource and mine plan is expected by year-end.
▸
Will the higher silver grades expected at Terronera in the second half also bring higher gold grades?
Alexander Terentiew · National Bank
Gold grades at Terronera should generally remain around 2 g/t, although some higher-grade pockets exist. The principal expected improvement in the second half is in silver grades.
▸
Given higher silver prices and exploration success, does management plan to publish an updated Terronera mine plan?
Alexander Terentiew · National Bank
Endeavour does not plan to issue a new technical study or mine plan for Terronera at this time. It expects to publish a new resource by year-end, while 2027 guidance will provide anticipated tonnes, grades and production. Drilling continues to define the resource and determine the cutoff for year-end results.
▸
Were slightly lower Kolpa grades a result of sequencing during the ramp-up to 2,500 tonnes per day, and how should grades and unit costs trend from here?
Soundarya Iyer · B. Riley Securities
Kolpa’s quarter-over-quarter silver grade was broadly flat, down only about 2%-5%. Grades are expected to remain relatively stable for the next six months, with occasional lower-grade feed from the Yen open pit used to maintain tonnes. Management expects unit-cost trends to reflect this generally steady grade profile.
▸
With $48 million budgeted for Pitarrilla but only about $5 million spent, what remains to be funded, and will the shortfall be catch-up spending or roll into 2027?
Soundarya Iyer · B. Riley Securities
Some Pitarrilla expenditures will shift into 2027 because the feasibility study is expected late in Q3, delaying equipment purchases and long-lead deposits. Spending is behind plan. The key gating item is permitting the dry-stack tailings facility; the project’s environmental approval and underground and plant permits are already in place.
▸
Should the expected $70 million VAT refund be viewed as roughly $70 million of additional cash on top of the reported balance?
John Tumazos · John Tumazos Independent Research
Management expects to collect approximately $70 million of VAT refunds in Q3 and believes it is on track, based on a strong history of recovering Mexican VAT. The refund accumulated largely during Terronera’s construction and can reasonably be viewed as additional cash, taking effective liquidity toward $300 million.
▸
How much of the current cash is committed to completing Kolpa and Terronera, and how much is expected to be needed for Pitarrilla?
John Tumazos · John Tumazos Independent Research
The current cash balance is not earmarked for Terronera sustaining capital or Kolpa expansion because those operations are generating cash to fund those needs. Future cash generation is primarily intended to support Pitarrilla construction, while the balance sheet should continue to grow.
▸
What is the approximate capital requirement for Pitarrilla?
John Tumazos · John Tumazos Independent Research
The feasibility study has not yet established the figure, but management’s current public estimate is approximately $500-$600 million of Pitarrilla capital.
▸
What will be the expected daily mining and milling throughput at Pitarrilla?
John Tumazos · John Tumazos Independent Research
The planned Pitarrilla mill is expected to process approximately 3,500-4,000 tonnes per day, subject to confirmation in the feasibility study.
▸
Would management want to repurchase Endeavour shares or its convertible bonds while the stock is depressed and the bonds may trade below value ahead of conversion?
John Tumazos · John Tumazos Independent Research
Management declined to provide investment advice. Dan Dickson said he has strong confidence in Endeavour and would personally want to own the company’s stock, particularly given its valuation relative to net asset value, but noted that personal investment decisions depend on individual circumstances.

Options

Chain Snapshot (daily)

Call IV (ATM)118%
Put IV (ATM)28%
ATM Spread2.1%
Call $OI (near money)$4.8M
Put $OI (near money)$1.8M
ATM ExpiryDecember 18, 2026 (44D)
ATM Strike$7.5
Major Expirations4
Near-money chain · December 18, 2026
StrikeCall Bid/AskCall OIPut Bid/AskPut OI
$2.50$5.10/$5.7050--/$0.050
$4.00$3.60/$4.100--/$0.100
$5.00$2.75/$3.1098--/$0.100
$6.00$1.80/$2.10200$0.05/$0.2010
$7.50$0.90/$1.05115$0.50/$0.60128
$9.00$0.35/$0.4046$1.35/$1.65586
$10.00$0.15/$0.251,022$2.25/$2.3513
$11.00$0.05/$0.2026$3.10/$3.400
Snapshot: 2026-11-04

Short Interest

Short % of Float7.6%
Short Shares22.5M
Days to Cover4.1
Change (vs Prior)+2.6%
Short % Float History
7.60%+0.70pp
5.0%5.5%6.0%6.5%7.0%7.5%8.0%10-1512-3103-1305-2908-1410-30

Web Traffic

edrsilver.com
Web rank#852,937
Est. visits/mo621K

Institutional Ownership

Fund$ valueCost basisΔ QoQΔ YoYα lifeFund AUM
VAN ECK ASSOCIATES CORP$166M$5.88−$29.2M+$9.9M—$164.08B
Tidal Investments LLC$149M$4.21−$271K+$32.9M—$41.21B
MIRAE ASSET GLOBAL ETFS HOLDINGS Ltd.$97.9M$5.39+$76K+$32.5M—$83.85B
JUPITER ASSET MANAGEMENT LTD$83.0M$3.84−$13.6M−$4.5M—$20.15B
VANGUARD CAPITAL MANAGEMENT LLCPassive$71.5M$9.30+$976K+$71.5M—$4.68T
TWO SIGMA INVESTMENTS, LP$62.2M$7.48−$5.4M+$62.2M—$128.44B
ALPS ADVISORS INC$38.6M$6.85−$3.3M+$21.3M—$21.31B
Condire Management, LP$37.3M$7.71+$0+$29.0M—$942M
SPROTT INC.$36.9M$6.25+$14.7M+$12.9M—$3.02B
CITADEL ADVISORS LLC$28.0M$5.09+$4.5M−$19.9M—$171.38B
Cost basis is a volume-weighted estimate from accumulation periods within our 13F history; holders who built their position before our window started will show a stale basis. % above the cost basis is the unrealized gain at the current price.

Ownership Over Time

5-year share-count history (top 10 holders by peak, incl. exited) + price

022.4M44.8M67.1M89.5M$1.97$3.83$5.69$7.54$9.402021-092022-092023-092024-092025-092026-06
hover the chart for per-quarter detailprice (right axis)
VAN ECK ASSOCIATES CORP20.0MTidal Investments LLC17.9MMIRAE ASSET GLOBAL ETFS HOLDINGS Ltd.11.8MJUPITER ASSET MANAGEMENT LTD10.0MTWO SIGMA INVESTMENTS, LP7.5MALPS ADVISORS INC4.7MCondire Management, LP4.5MMILLENNIUM MANAGEMENT LLC1.9MSPROTT INC.4.5MWaratah Capital Advisors Ltd.—

Analyst Coverage

Analyst Coverage
Price Targets
Last Quarter (1 analysts)$17.00+177.3%
Last Year (3 analysts)$14.17+131.2%
Current Price$6.13
Analyst Ratings
11
2
Buy: 11Hold: 2Sell: 1Consensus: Buy
Consensus Estimates
QuarterRevenueEBITDANet IncEPSEPS Range# Analysts
2007 Q129M-3M-5M$0.08$0.06 – $0.1017
2008 Q33M-6M-13M$-0.07$-0.09 – $-0.0619
2009 Q142M1M-3M$-0.32$-0.39 – $-0.2613
2009 Q212M-0M-2M$-0.08$-0.10 – $-0.0618
2009 Q310M3M-1M$-0.03$-0.04 – $-0.0213
2010 Q137M8M2M$0.08$0.06 – $0.1016
2010 Q2118M3M-1M$0.12$0.09 – $0.1412
2010 Q335M4M0M$0.09$0.07 – $0.1117
2011 Q127M5M0M$0.10$0.08 – $0.1212
2011 Q245M38M20M$0.18$0.14 – $0.2212
2011 Q347M18M4M$0.14$0.11 – $0.1719
2012 Q136M29M12M$0.10$0.08 – $0.1213
2012 Q2162M24M12M$0.38$0.30 – $0.4520
2012 Q384M7M0M$0.18$0.14 – $0.2217
2013 Q170M36M14M$0.13$0.10 – $0.1617
2013 Q271M13M-0M$-0.04$-0.05 – $-0.037
2013 Q315M—30M$0.07$0.06 – $0.097
2014 Q144M20M3M$0.02$0.02 – $0.0312
2014 Q292M15M-0M$-0.04$-0.04 – $-0.039
2014 Q326M9M-5M$-0.04$-0.04 – $-0.0310
2015 Q2286M8M-2M$-0.10$-0.12 – $-0.0814
2015 Q340M-3M-13M$-0.03$-0.04 – $-0.038
2016 Q1104M10M3M$0.07$0.06 – $0.0916
2016 Q2312M9M3M$0.12$0.09 – $0.1413
2016 Q342M12M6M$0.04$0.03 – $0.0510
2017 Q115M10M3M$0.01$0.01 – $0.0111
2017 Q259M4M-0M$0.04$0.03 – $0.0412
2017 Q3119M7M1M$0.05$0.04 – $0.0517
2017 Q442M9M3M$0.02$0.02 – $0.0216
2018 Q160M15M3M$0.04$0.03 – $0.0519
2018 Q219M-12M-20M$0.07$0.06 – $0.0913
2018 Q39M3M-10M$-0.01$-0.02 – $-0.0110
2018 Q456M3M-5M$-0.06$-0.08 – $-0.0511
2019 Q129M-10M-18M$-0.03$-0.03 – $-0.036
2019 Q228M3M-4M$-0.04$-0.04 – $-0.048
2019 Q329M2M-5M$-0.04$-0.04 – $-0.035
2019 Q430M-12M-22M$-0.04$-0.04 – $-0.045
2020 Q123M-17M-24M$-0.03$-0.03 – $-0.036
2020 Q220M0M-4M$-0.04$-0.04 – $-0.038
2020 Q340M10M1M$0.04$0.04 – $0.044
2020 Q452M40M18M$0.06$0.05 – $0.064
2021 Q138M24M10M$0.02$0.02 – $0.027
2021 Q249M23M10M$0.03$0.03 – $0.031
2021 Q341M-9M-14M$0.02$0.02 – $0.021
2021 Q454M26M12M$0.04$0.04 – $0.041
2022 Q153M19M8M$0.05$0.04 – $0.052
2022 Q239M25M13M$0.01$0.01 – $0.012
2022 Q342M-9M-16M$0.01$0.01 – $0.012
2022 Q458M-12M-21M$0.04$0.04 – $0.042
2023 Q152M19M7M$0.03$0.02 – $0.031
2023 Q253M30M14M$0.01$0.01 – $0.011
2023 Q344M-8M-17M$0.01$-0.03 – $0.064
2023 Q450M-13M-20M$0.02$-0.02 – $0.052
2024 Q155M20M7M$0.02$-0.02 – $0.134
2024 Q262M18M5M$0.02$0.00 – $0.023
2024 Q352M9M1M$0.00$0.00 – $0.001
2024 Q447M1M-4M$-0.01$-0.01 – $-0.012
2025 Q161M13M2M$0.01$-0.02 – $0.043
2025 Q282M21M3M$0.01$0.00 – $0.013
2025 Q3131M42M10M$0.03$0.02 – $0.042
2025 Q4171M70M20M$0.06$0.03 – $0.093
2026 Q1200M94M41M$0.13$0.09 – $0.162
2026 Q2211M111M49M$0.15$0.14 – $0.162
2026 Q3197M85M33M$0.10$0.10 – $0.102
2026 Q4197M113M47M$0.14$0.14 – $0.141
2027 Q1228M129M54M$0.17$0.17 – $0.171
2027 Q2231M149M64M$0.20$0.20 – $0.201
2027 Q3239M160M68M$0.21$0.21 – $0.211
2027 Q4238M166M69M$0.21$0.21 – $0.211
2028 Q1248M162M64M$0.20$0.20 – $0.201
2028 Q2246M166M64M$0.20$0.20 – $0.201
2028 Q3244M167M62M$0.19$0.19 – $0.191
2028 Q4243M171M62M$0.19$0.19 – $0.191
2029 Q1175M183M69M$0.21$0.21 – $0.211
2029 Q2175M185M69M$0.21$0.21 – $0.211
2029 Q3175M185M68M$0.21$0.21 – $0.211
2029 Q4159M175M62M$0.19$0.19 – $0.191
2030 Q1193M232M95M$0.29$0.29 – $0.291
2030 Q2193M231M94M$0.29$0.29 – $0.291
2030 Q3193M235M95M$0.29$0.29 – $0.291
v2 analysis (legacy, 2026-07-30) — for comparison onlyclick to expand

Thesis

Endeavour is transitioning from a small, inconsistent Mexican silver producer into a substantially larger multi-mine operator. Terronera and Kolpa have dramatically lifted revenue and adjusted EBITDA, and the latest quarter confirms strong operating leverage. The important distinction is that this is not yet a high-quality cash compounder: cumulative adjusted FCF from 2022 through the latest period is approximately negative $460M, while capex, acquisitions and lease commitments have consumed far more than reported EBITDA. Pitarrilla creates substantial long-term upside but also represents a $500M-$600M funding requirement before the company is likely to return capital. The base case assumes the current operational improvement is real but gives limited credit for exploration upside or a permanent precious-metals boom. Terronera's LNG conversion and higher silver grades should help, but management explicitly pushed the highest-grade La Luz gold material into 2027 and acknowledged that current AISC is above guidance. Kolpa's extra capital appears largely catch-up and life-extension spending, but it reinforces the reinvestment treadmill risk. The business is therefore improving rapidly, but the range of outcomes is wide. It has meaningful commodity, country, permitting, security, execution and financing exposure. At the same time, the company has ample near-term liquidity, expected VAT proceeds and operations that are increasingly capable of funding development. The central investment question is whether strong current metal prices are converted into durable free cash flow or simply recycled into the next major project.

Trade Signal

Trade rating
-3.9/10
No trade
Horizon
~3mo
gpt-5.6-luna2026-07-30 · saw $7.77-11.6% since

Lean short/no-trade: EXK's strong operating trajectory and silver exposure are real, but the shares appear materially above fair value and already discount successful execution while Pitarrilla creates substantial future funding risk.

Temporary mispricing+2.5

The stock rallied sharply through late 2025 and January 2026, broadly alongside silver strength, the Terronera/Kolpa production step-up and renewed growth expectations. It then fell from $13.90 in late February to the $8-$10 range in March and drifted toward $7.56 in July, reflecting a combination of commodity/sector reversal, profit-taking and concern about operating and funding risks. The July decline was more drift and repricing than a clearly identifiable company-specific shock. Q2 earnings were materially strong, yet the stock was unchanged the day before versus the day after the release, suggesting the good news was largely discounted rather than missed. The pullback may be somewhat overshot, but it is not a clear panic dislocation; the valuation gap looks more durable than temporary.

Market view+2.0

The stock is broadly liked by analysts, with 11 Buys versus 2 Holds and 1 Sell and an average one-year target of $11.56. The bullish narrative is record silver prices, Terronera/Kolpa growth, falling costs and Pitarrilla's large resource. Bears focus on high valuation, volatile mine economics, Mexican security and cost inflation, and the need to fund Pitarrilla. Price has nevertheless fallen 45% from its 52-week high and short interest has risen from roughly 5% to 6.9%, indicating a more cautious positioning backdrop. The market is constructive rather than euphoric, but analyst optimism may be stale relative to funding risk.

Inflectionwindow ~2mo+3.5

The next operating inflection is positive: Terronera should benefit from LNG power, higher grades and continued ramp-up, while Kolpa is operating at expanded capacity. Q3 results and the Pitarrilla feasibility study could make the growth story more credible. Much of the operating improvement is already visible in record Q1/Q2 results, and the consensus Buy stance and $11.56 average target suggest the market already expects a favorable trajectory. The less-appreciated risk is that Pitarrilla's capital burden converts operational success into future dilution or leverage.

Catalysts
  • ▲August-September 2026 · Terronera LNG power transition and approximately $70M Mexico VAT refund — The LNG plant should reduce operating costs, while the VAT refund could lift liquidity toward $300M; execution and timing are key.
  • ▲Q3 2026 · Pitarrilla feasibility study — A credible study could validate a major long-term growth asset, though higher-than-expected capex or weak returns would be negative.
  • ▲October-November 2026 · Q3 2026 earnings — Watch Terronera grades, LNG savings, Kolpa throughput, AISC and cash generation; confirmation of margin improvement could support the shares.
  • •Late 2026 · Terronera exploration/resource update — High-grade drilling and a year-end resource could extend mine life, but the economic value is not yet established.
  • •Late 2026 · Kolpa updated resource and mine plan — Could improve mine-life visibility, but the additional capital program and tailings spending remain execution risks.
Flow-1.0

TTM dilution was approximately zero and there is no stated near-term buyback or dividend. Current cash generation should help fund growth, but Pitarrilla's projected $500-$600M build likely creates future debt and/or equity issuance risk. Short interest is moderate at 6.9% of float, with limited squeeze fuel at 4.2 days to cover; insider and institutional flow data do not show a strong directional signal.

Floor / Ceiling+1.0

Cash of roughly $236M, expected VAT proceeds and profitable operating assets provide some support, but this is not a hard asset floor: reported FCF yield is negative, AISC is elevated, and Pitarrilla may require $500-$600M of construction capital. There is also no active buyback or committed acquisition floor. The principal ceiling is funding risk if the stock rises and management uses equity or expensive debt to finance Pitarrilla, but it is not an immediate hard cap.

Buyability

Real buyers can own the strong production growth, record silver prices, Terronera/Kolpa ramp and potential Pitarrilla expansion. However, the stock is already followed and broadly rated Buy, while future Pitarrilla funding may require meaningful debt or dilution; it is buyable, but not an undiscovered bargain.

Fear vs Greedfear 7/10 (-1.0)greed 8/10 (+2.0)

Fear is modestly stronger than greed at $7.56: the operating business has genuinely improved, but the market price discounts a favorable silver environment and substantial execution success while the analyst's own fair value is about 37% lower. I would prefer a small, catalyst-aware short or no position rather than an aggressive short because silver strength and Pitarrilla optionality can produce sharp upside.

Valuation

Our Target
$800M-56%
Market Should Pay
$656M-64%
target ×0.82 (fear discount)
Current Market Cap
$1.8BSlightly bullish
What Changed
transcript · 2026-07-30
+8%fair value on this information

The quarter newly demonstrated that the stronger production platform is translating into much higher mine operating earnings and operating cash flow: revenue was approximately $212M, mine operating earnings $74M and pre-tax mine operating cash flow about $100M. It also confirmed that LNG commissioning was largely successful, Kolpa is operating at or above 2,500 tonnes per day, and approximately $70M of VAT refunds is expected in Q3. Conversely, the call clarified that the near-term Terronera grade uplift will be incremental, the approximately 4 g/t gold La Luz material is mainly deferred to 2027, AISC is currently above guidance, and some Pitarrilla spending is moving into 2027.

▸ How the cases moved

Versus the day before the Q2 release, the bear case improves modestly from roughly $130M to $150M as liquidity, operating cash flow and the expected $70M VAT refund reduce near-term stress; its probability falls from 0.28 to 0.25. The base case rises from roughly $900M to $1,020M because the quarter confirms Terronera and Kolpa production leverage, while its probability rises from 0.48 to 0.50. The bull case rises from roughly $1,900M to $2,040M on stronger throughput, LNG commissioning and continued resource potential, but its probability increases only from 0.24 to 0.25 because management deferred the highest-grade Terronera gold material and still faces the large Pitarrilla funding requirement.

2-Year Plausible Outcomes
bear25%
$150M
rev -5%/yrOE $10M

Silver prices retreat, Terronera and Kolpa deliver only modest operating improvement, and Mexican security, inflation and permitting risks keep costs high. Pitarrilla requires substantial funding before it creates value, leaving the company with low free cash flow and a heavier effective capital burden.

▸ Valuation

5x $80M EBITDA = $400M EV - $250M net debt = $150M equity

base50%
$1.0B
rev +12%/yrOE $75M

Terronera reaches stable production, LNG reduces power costs, Kolpa operates near its expanded throughput and silver prices remain supportive but normalize from current elevated levels. Pitarrilla advances but consumes most available cash, so owner earnings improve without meaningful shareholder distributions.

▸ Valuation

6x $220M EBITDA = $1,320M EV - $300M net debt = $1,020M equity

bull25%
$2.0B
rev +25%/yrOE $150M

Silver remains strong, Terronera reaches higher-grade zones, LNG and operational improvements materially reduce unit costs, and Kolpa's expansion works as intended. Pitarrilla receives a credible feasibility study and is funded without severe dilution, creating a larger, higher-margin mid-tier producer platform.

▸ Valuation

7x $320M EBITDA = $2,240M EV - $200M net debt = $2,040M equity

▸ Target Rationale

The probability-weighted scenario math produces an $846M present value. I set my analytical target at $800M because the arithmetic gives substantial credit to a successful Pitarrilla funding path while not fully capturing execution risk, likely future capital intensity, convertible-debt dilution, and the limited evidence that current adjusted EBITDA will convert into durable owner earnings. The target is not reduced for sentiment; the market's fear discount is handled separately.

Business Quality & Sentiment

Business Quality (price-independent)
Business quality6/10
Situation now7/10
Trajectory8/10
Risk7/10
Governance5/10
Insolvency prob (2yr)5%
Outcome uncertainty8/10

Recent Research & News

Recent Research & News

2026-06-21

Company news

  • Record Q1 2026 Financial Results: In May 2026, Endeavour reported record-breaking financial and operating performance for the first quarter of 2026. Fueled by the additions of the newly producing Terronera mine in Mexico and the Kolpa mine in Peru, consolidated production reached 3.3 million silver equivalent ounces (1.88 million ounces of silver and 11,740 ounces of gold), marking a 78% increase year-over-year. Revenue surged 230% to $209.7 million, with mine operating cash flow before taxes growing 419% to $114.6 million, benefiting from robust commodity prices.
  • High-Grade Drill Intercepts at Terronera: On June 18, 2026, the company announced exceptionally high-grade silver and gold drill results from its exploration program at Terronera and the nearby La Luz system. Notable intercepts included 10 meters grading 282 g/t silver and 1.8 g/t gold (TRU-001) and 9 meters of 150 g/t silver and 6.3 g/t gold (TRU-003). Industry analysts noted that these findings strongly support long-term resource growth and the potential for a significant mine-life extension beyond the current plan.
  • Bolañitos Divestment Completed: In mid-January 2026, Endeavour finalized the sale of its non-core Bolañitos mine, sharpening its focus and capital allocation toward its core, high-margin operations.
  • 2026 Annual General Meeting: Shareholders approved all proposed items at the AGM on June 2, 2026, including the re-appointment of KPMG LLP as auditors and the re-election of all eight board directors.
▸ Thesis-test Findings
  • Pitarrilla Feasibility Study Capex Updates 2026: Endeavour has budgeted $65.8 million to advance its world-class Pitarrilla project in Durango, Mexico for the 2026 fiscal year. This program allocates $15.0 million specifically to complete the Feasibility Study—expected to be finalized in mid-to-late 2026 (targeting Q3/August)—alongside $2.8 million for exploration drilling and $48.0 million for early growth capital expenditures (such as mine equipment, underground development, and site infrastructure). While the company has not yet released official capital expenditure projections for the full construction phase under the new study, third-party industry reports estimate the total project build cost will range between $400 million and $500 million. This highlights a massive organic growth catalyst but introduces a significant future capital funding requirement.
  • Terronera Mine LNG Power Plant Commissioning Status: Although Terronera achieved commercial production in late 2025, early operations in Q1 2026 continued to rely on higher-cost temporary diesel-powered generation. On the Q1 2026 earnings call, management confirmed that the company has secured all necessary permits and expects to fully transition the mine's power generation to its on-site liquefied natural gas (LNG) vaporization plant before the end of Q2 2026. Transitioning to the LNG plant is a critical margin driver, expected to reduce direct operating costs by approximately $8 per tonne once fully online.
  • Mexican Silver Mining Security and Cartel Logistics Impacts 2026: Geopolitical and operational security risks in Mexican mining jurisdictions spiked in early 2026 following retaliatory cartel violence in February. High-profile incidents—such as the kidnapping of mining workers in Sinaloa—highlight the parallel taxation and extortion systems targeting the industry. Endeavour was directly impacted at its flagship Jalisco-based Terronera mine, which was temporarily paused for three days in late February 2026 due to regional highway blockades and security concerns. While operations resumed quickly with minimal impact on total quarterly throughput, the situation underscores that security is an increasingly sticky operating cost, with transport corridors remaining the most vulnerable link in the logistics chain.