Gorilla Technology Group Inc.v3 3.0/10 · 2026-11-13Gorilla Technology Group Inc. provides solutions in security, network, business intelligence, and Internet of Things (IoT) technology in Taiwan and the United Kingdom. It operates through three segments: Video IoT, Security Convergence, and Other segments. The company offers smart building and office solutions, such as occupancy management, integrated security, real-time AI monitoring, smart energy usage, predictive maintenance, smart elevator system, biometric access control, and personalized safety alerts; policing solutions, including GIS and geospatial mapping, temporal and spatial pattern correlation, data integration and pattern recognition, anomaly detection and trend identification, fast video search, people, vehicle, and license plate detection, synced mobile and camera analytics, and intelligence analysis platform services; and smart railway solutions comprising fire detection, facial recognition, people detection and direction, baggage detection, people counting, crowd management, and zone intrusion detection. It also provides smart road solutions, such as faster responses to traffic infractions, optimized traffic flow, reduce red light violations, integrated traffic management, enhanced intersection monitoring, high-precision license plate detection, actionable traffic insights, and integrates with existing video management software; and smart port solutions, including business monitoring and traffic prediction command center, intelligent video analytics, vehicle and people access control, container identification system, IoT gauge integration, automated container damage detection, and comprehensive network security. Gorilla Technology Group Inc. is headquartered in London, the United Kingdom.
2-Year Price History
Valuation v3 Opus worker · 2026-11-13
Gorilla is trying to turn a small Taiwan-rooted video-analytics and security integrator ($101M of revenue in 2025) into a GPU lessor and sovereign-AI data-center operator. Management guides 2026 revenue of at least $200M and $450-500M for 2027, based on 5-year take-or-pay contracts with Yotta (India) and NeutraDC (Indonesia). The stock closed at $7.41 on 2026-11-13, down 66% from its 1-year high. There are 27.5M shares, a market cap of about $204M and an EV of roughly $385M once H2 2026 GPU spending is counted. Testing the pitch made the bear case stronger. - Margins. Q2 2026 gross profit was negative: -$2.1M on $50.1M of revenue. Gross margin went 35% → 33% → 21% → -4% over the four quarters shown. Adjusted EBITDA was negative in both Q1 and Q2. - Cash flow. H1 operating cash flow of -$4.3M was achieved only because payables rose $45.7M. - Funding. The Yotta program alone covers more than 25,000 GPUs, about $1.1-1.4B of capex. Project debt is still not closed, and the $232M of converts appears spent. The company took a VWAP-priced note in October (90% of the lowest VWAPs, $3.86 floor) and is asking to raise authorized shares to 200M. - Track record. The $1.4B Freyr contract, which anchored the original 2026 guide, never visibly went live. - Concentration. About 70% of the 2027 guide depends on Yotta, which is itself raising money to repay debt ahead of a 2027 IPO. The unlevered contract economics do hold up: about 2x capex per dollar of revenue at roughly 75% cash margin. So the enterprise is worth something, about $230M by my DCF. But net debt of about $180M leaves the equity at roughly $2 a share. Fair value is $3, with a range of $0 to $12. Rating 3.0: clearly overvalued, and the funding path runs through equity. As a trade, though, it is only a mediocre short. About 25% of the float is already short, borrow is expensive and implied volatility is 100-150%. A $48-50M Q3 print (Nov 16-18) with Yotta billing could squeeze the stock before the dilution lands. So it is a pass, or at most a small short sized for a squeeze.
A deep dive would have to establish: Can Gorilla close project debt for Yotta 2 and NeutraDC, and collect cash from Yotta, before the VWAP-priced and reset-floor converts dilute the current 27.5M shares several times over?
Research (expand)
What it does. Gorilla began as a Taiwan integrator of video analytics, smart-city systems and cybersecurity, selling to governments and telcos in Taiwan, Egypt and Thailand. Since 2025 it has pitched itself as a 'sovereign AI infrastructure' operator.
- It buys Nvidia servers and rents them out on 5-year take-or-pay GPUaaS contracts:
- Yotta 1: 640 B200 servers, about $100M a year.
- Yotta 2 batch 1: about $250M a year.
- NeutraDC Batam first 300 servers: about $75-80M a year, for an end customer described as investment-grade.
- Under the Yotta deals Gorilla supplies the hardware and Yotta operates it. Economically, Gorilla is a GPU lessor to a leveraged Indian neocloud.
- It also plans its own campuses: Korat 200 MW, Batam, and a proposed 36 MW US site under a non-binding LOI.
What the market believes. At about $204M market cap, against a $450-500M 2027 revenue target, the market thinks shareholders will pay for the growth. I agree. The sequence of financings:
- June 2026: $107M of 7.5% converts at $25.48, resetting down to a $6 floor from March 2027. Interest can be paid in shares at a 10% discount.
- July 2026: $125M of Series B 7.5% converts. They reset down to an $8.00 floor; the pitch said $6, which was wrong. The stock fell 27% that day.
- October 30: up to $100M of zero-coupon notes, with conversion at 90% of the three lowest VWAPs and a $3.86 floor.
- The first tranche was $27.78M of principal for $25M of proceeds.
- Warrants and pre-delivery shares are attached, with a 2% per 30 days penalty if the registration lapses.
- Lind filed a 9.99% stake.
- Pending: a shareholder vote to raise authorized shares from 73.5M to 200M.
Notes already signed could convert into roughly 33M shares at their floors, plus up to 26M more if the Lind facility is fully drawn. That compares with 27.5M shares outstanding today.
What it earns today.
- H1 2026 revenue was $78.4M and gross profit $3.8M.
- By quarter, gross margin was 21% in Q1 and -4% in Q2. In 2025 it was 33-35%.
- Adjusted EBITDA was -$8.3M in Q1 and -$6.3M in Q2. SBC was $25.4M.
- H1 operating cash flow was -$4.3M only because payables rose $45.7M.
- Receivables plus contract assets are $145M.
- Unlevered owner earnings today are about -$50M a year. The legacy integrator business is now loss-making and adds nothing to value.
FCF projection (unlevered, $M). Some Yotta 2 batch 1 and NeutraDC capex lands in Q4 2026, so it sits in net debt rather than in 2027 FCF.
| Year | FCF ($M) |
|---|---|
| 2027 | -380 |
| 2028 | -150 |
| 2029 | +40 |
| 2030 | +80 |
| 2031 | +100 |
- Unit economics: about 2x capex per dollar of annual revenue (Yotta 1 about 2.0-2.3x, NeutraDC about 1.7x). Cash gross margin is about 75%.
- Assets are written off over 5 years with roughly 20% residual value, and the fleet must be replaced roughly every 5 years.
- Each contract has a modestly positive NPV at 10% if the customer pays.
- At year 5 I value it at about 9x FCF, as a 'neither' business.
DCF result:
- Enterprise value is about $235M.
- Net debt at end-2026 is about $180M, versus net cash of about $59M at June 30, after $200-350M of H2 GPU spending.
- Equity value is therefore about $2 a share.
- The bull case is about $12-14. It requires all contracts to bill on time at a 40% blended gross margin, with growth financed by debt.
Multiples. Trailing earnings are negative. On management's 2027 numbers the stock trades at about 3x EV/EBITDA, but consensus has EBITDA near zero through 2027.
Management, risks, competition.
- CEO. Jay Chandan is highly promotional: '$7B pipeline', '$5B signed backlog', '$500M by 2027', 'barking from the sidelines'.
- Short reports. Bear Cave and Culper attacked the company in 2025; Culper called its $1.8B Thailand PEA contract likely fabricated. Gorilla sued Culper, and the suit settled with no money changing hands.
- Freyr. The $1.4B Freyr contract (Phase 1 of $300M slated for Q4 2025) has not visibly produced revenue, and it is not in the 2027 bridge.
- Counterparty. Yotta is pre-IPO and raising money to repay debt.
- Competition. CoreWeave, Nebius, the hyperscalers and local telcos all have cheaper capital.
- Positives. Fitch rates it B- with a positive outlook. Revenue guidance has been met, though partly with hardware revenue earned at zero margin. The contracts are take-or-pay.
Sentiment: 3/10. The stock is down 66% from its high. Short interest is about 6M shares, roughly 25% of the float, and implied volatility is put-skewed. A loyal retail base still buys dips.
Thesis test
1. Negative Q2 gross profit and payables-funded cash flow. The challenge is right. The company's own H1 figures show Q2 gross profit of -$2.1M and payables up $45.7M. The legacy business is worth zero, the 'guidance met' record counts for less, and I cut the bull case from $15-18 to $12-14.
2. Funding gap and dilution. The challenge is right on the facts: the Yotta program exceeds 25,000 GPUs, project debt is still not closed, and the Series B floor is $8, not $6. It goes too far in implying dilution further cuts fair value. Equity issued at $4-8, above our roughly $2 DCF, is accretive per share, so the real risk is a funding failure, which supports the $0 low case.
3. Yotta concentration. Mostly right. Yotta is pre-IPO and raising money to repay debt, and it supplies about 70% of the 2027 guide. NeutraDC's investment-grade end customer and Yotta's recent raise at about $4.4B soften this. The low case stays at $0.
4. Contracts that do not convert (Freyr). Partly right. The evidence is that nothing has been reported, not a proven failure. Even so, Q1 2026 revenue fell, and Freyr is missing from the 2027 bridge. I give almost no value to the unnamed $75-125M of 2027 revenue.
5. Net debt understated. Right in direction, though the size rests on my capex estimates. I raise net debt to about [60, 180, 400]. To avoid double counting, I move about $70M of capex out of 2027 FCF and into net debt. The base DCF goes from $2.5 to $2.0.
The objections do not overturn the pitch; they push it further toward the bear side. Enterprise value is positive because the leases have positive NPV, but almost none of it reaches today's equity once debt-funded GPU spending is counted. Fair value is about $3 (range $0-12) against $7.41. This is a pass, or at most a small short, because the crowding and the risk of a squeeze around the Q3 print limit the trade.
- /Users/gregwo/stocks2/data/analysisv3/context/GRRR.md (2026Q2 call transcript, price history, short interest)
- /Users/gregwo/stocks2/data/analysisv3/GRRR/2026-11-13.challenge.md
- https://www.sec.gov/Archives/edgar/data/0001903145/000143774926028827/ex_974012.htm
- https://www.sec.gov/Archives/edgar/data/0001903145/000121390026065533/ea0293741-424b5_gorilla.htm
- https://www.panabee.com/news/gorilla-technology-inks-100-million-financing-deal-with-complex-dilution-terms
- https://www.barchart.com/story/news/3297355/gorilla-technology-group-inc-announces-pricing-of-125-million-senior-unsecured-convertible-bond-offering-to-commence-neutradc-batam-project-in-indonesia
- https://investwithcolby.substack.com/p/gorilla-technology-group-grrr-q2
- https://www.webull.com/news/15542765614064640
- https://www.newsfilecorp.com/release/305933/
- https://www.dealstreetasia.com/stories/data-centre-operator-yotta-india-ipo-493935
- https://www.datacenterdynamics.com/en/news/it-company-gorilla-pushes-into-southeast-asia-signs-14bn-contract-with-singaporean-cloud-provider-freyr/
- https://datacenterdynamics.com/en/news/gorilla-technology-secures-25bn-gpuaas-contract-in-indonesia
- https://stockanalysis.com/stocks/grrr/
- https://www.stocktitan.net/overview/GRRR/
- https://scr.zacks.com/news/news-details/2026/GRRR-The-Good-Raised-Guidance-The-Bad-Short-term-Margin-Pressure-and-The-Ugly-Retail-Traders-Are-Not-Investors-article/default.aspx
| date | price | rating | research | fair value | DCF | base IRR | sentiment |
|---|---|---|---|---|---|---|---|
| 2026-11-03 | 7.97 | 2.5 | 3.5 | 5.00 | 1.50 | -20% | 4 |
| 2026-11-13 | 7.41 | 3.0 | 5.0 | 3.00 | 2.00 | -45% | 3 |
Financials — Adjusted
Adjusted · TTM 2026-Q3 · USD
| TTM & Fiscal-Year P&L | TTM | 2025 | 2024 | 2023 | 2021 |
|---|---|---|---|---|---|
| Revenue | 160+71% | 101+36% | 74.7+15% | 64.7+53% | 42.2 |
| Gross profit | 35.3+7% | 33.9-9% | 37.3-17% | 44.7+183% | 15.8 |
| Operating expenses | 62.3-44% | 41.7-60% | 104+322% | 24.7+4% | 23.8 |
| ▸Adj EBITDA | -25.5 | -6.52 | -65.5-409% | 21.2 | -1.71 |
| ▸Adj OCF | -20.2-169% | 10.2-67% | 30.9 | -9.67-648% | 1.76 |
| CapEx | -216 | -0.67 | -0.54 | -0.22 | -7.50 |
| Adj FCF | -237-921% | 9.57-68% | 30.3 | -9.88 | -5.73 |
| Interest expense | 9.43 | 0.54 | 0.73 | 0.44 | 0.67 |
| ▸Adj net income | -27.8 | -5.44 | -64.8-494% | 16.4 | -9.18 |
claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2021→FY2025 +2026YTD
| Where the Cash Went | Total | 2026YTD | 2025 | 2024 | 2023 | 2021 |
|---|---|---|---|---|---|---|
| ▸Claimed: EBITDA | -99.9 | -45.4 | -9.08 | -64.0 | 21.1100% | -2.50 |
| FCF (OCF−capex) | -318 | -239 | -29.3 | -32.1 | -11.5-55% | -5.87 |
| Net income | -125 | -53.6 | -11.3 | -64.8 | 13.564% | -8.55 |
| ▸Capital returned | -216 | -105 | -121 | 8.17 | 0.442% | 0.67 |
| Buybacks | -128 | -1.36 | -130 | 3.63 | 0.00 | 0.00 |
| Dividends | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest paid | 11.6 | 9.18 | 0.54 | 0.73 | 0.44 | 0.67 |
| Debt paid down | -100 | -113 | 8.80 | 3.81 | 0.00 | 0.00 |
| ▸Reinvestment | 221 | 217 | 1.20 | 0.54 | 0.221% | 2.34 |
| Capex (PP&E) | 225 | 216 | 0.67 | 0.54 | 0.22 | 7.50 |
| Intangibles & M&A | -5.17 | -0.01 | 0.00 | 0.00 | 0.00 | -5.16 |
| Leases signed (net Δ) | 1.32 | 0.79 | 0.53 | -- | -- | -- |
| Retained / other | -85.3 | -125 | 91.8 | -39.5 | -11.5-55% | -0.71 |
negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.
Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.
Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).
SBC over the Total window: 28 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.
| Balance Sheet | TTM | 2025 | 2024 | 2023 | 2021 |
|---|---|---|---|---|---|
| ▸Assets (total) | 556 | 272 | 154 | 115 | 94.9 |
| ▸Liabilities (total) | 399 | 75.8 | 80.7 | 61.3 | 49.0 |
| Net debt (incl. leases) | 89.3 | -85.7 | -15.3 | -1.22 | 17.0 |
| Net debt / Adj EBITDA | -- | -- | -- | -0.06 | -- |
| Net debt / Adj FCF | -- | -8.96 | -0.50 | -- | -- |
| Adj EBITDA / interest | -2.70 | -12.0 | -89.5 | 48.0 | -2.57 |
| Shares outstanding | 13.5 | 26.2 | 18.1 | 7.57 | 6.85 |
| Dilution (YoY) | +45.0% | +45.0% | +138.7% | +10.4% | +309.6% |
| Employees | 307 | 200 | 143 | 142 | -- |
| Margins | TTM | 2025 | 2024 | 2023 | 2021 |
|---|---|---|---|---|---|
| Gross margin | 22.1%-13.4 | 33.4%-16.5 | 50.0%-19.2 | 69.1%+31.8 | 37.3% |
| Adj EBITDA margin | -15.9%+66.0 | -6.4%+81.3 | -87.8%-120.6 | 32.8%+36.8 | -4.1% |
| Adj OCF margin | -12.6%-44.1 | 10.1%-31.2 | 41.3%+56.3 | -14.9%-19.1 | 4.2% |
| Adj FCF margin | -148.1%-178.9 | 9.4%-31.2 | 40.6%+55.9 | -15.3%-1.7 | -13.6% |
| Net income margin | -35.3%+45.0 | -11.1%+75.6 | -86.8%-107.6 | 20.9%+41.1 | -20.2% |
| Adj NI margin | -17.4%+62.8 | -5.4%+81.4 | -86.8%-112.2 | 25.4%+47.1 | -21.7% |
| ROIC (adj, after-tax) | -7.1% | -2.9% | -55.5% | 18.2% | -7.8% |
| Cost of debt | 19.6% | 3.2% | 2.5% | 1.5% | 2.0% |
Earnings Calls
Earnings Call · 2026 Q2
Gorilla Technology Group management, led by Chairman and CEO Jayesh Chandan and CFO Bruce Bower, reported first-half 2026 results marked by sharp revenue growth, a much smaller operating loss, and an aggressive push into GPU-as-a-service infrastructure. First-half revenue rose about 99% year over year to $78.4 million. Q2 revenue was about $50.1 million, up roughly 78% sequentially and 138% year over year, beating the company's internal expectation, which had been raised from about $33 million to $44 million. Management attributed the beat to deliverables and milestones completed earlier than planned. The reported operating loss narrowed from $41.1 million in Q1 to about $2.2 million in Q2, a reduction of about 95%. Management said most of the first-half share-based compensation was recognized in Q1, so Q2 gives a clearer view of underlying operations. Operating cash consumption fell about 65%, from $12.5 million in H1 2025 to $4.3 million in H1 2026, and dropped from 31.8% of revenue to 5.5%. Cash ended June at about $179.4 million, roughly 82% above the Q1 closing balance. Bruce Bower described the balance sheet as including about $13 million of conventional bank debt and about $107 million of long-term debt from a five-year convertible placed in June, with a further convertible completed in July. Management characterized the cash as deliberately deployed into equipment, site preparation, deposits, and working capital rather than idle. Capital expenditure was about $14.1 million in the first half, and Chandan cited a current figure of $29.4 million, with management expecting spending in the second half to be many multiples of the first-half amount. Gross margin declined in the first half because of a revenue mix weighted toward hardware, initial deployments, and project mobilization. Management expects margins to expand as GPU-as-a-service projects go live, which it said generate gross margins of about 75% or more. Project status updates included Yotta Phase 1, where testing was complete, equipment deliveries were underway, and deployment had begun; Yotta Phase 2, where equipment was being manufactured with completion expected in 25 to 30 days; and NeutraDC in Batam, Indonesia, where the company is targeting roughly 200 megawatts with initial ready-for-service in mid-2027 and broader deployment in the second half of 2027. At Korat in Thailand, land has been cleared and financing, GPU procurement, and infrastructure work are advancing, with the company engaging prospective offtakers. Guidance was updated. Q3 revenue is planned at $48 to $50 million, up from the earlier $36 to $40 million range. Q4 revenue is planned at over $60 to $70 million. Full-year 2026 revenue is now expected to be at least $200 million, up from the prior $137 to $200 million range, with the upper end requiring further deliveries and customer workload activation. For 2027, management is targeting $450 to $500 million in revenue, implying roughly $112 to $125 million per quarter. Bower emphasized that guidance includes only contracted revenue with defined amounts and dates. Yotta 1 and the first batch of Yotta 2 are included, as is the first 300-server phase of NeutraDC, expected around September. Additional NeutraDC servers and the second Yotta 2 batch are excluded until delivery schedules firm up. Management expects over $20 million in large customer collections in September and October, and it expects operating cash flow to reach breakeven or better for the full year. SG&A was about $2.7 million per month, expected to rise to a $38 to $40 million annualized run rate by the end of 2027, which management framed as a worthwhile trade-off given the offshore cost base. Headcount was about 300 full-time employees plus about 300 to 350 contractors, with a target of roughly 2,000 people by mid-2027. Bower also said that the company is pursuing a credit rating and expects future CapEx to rely more on project finance and debt. Management said that all significant hardware, power, water, and connectivity pricing is on fixed-price terms, so the company is not passing spot-price volatility to customers or retaining it, and that GPU contracts are take-or-pay, with fixed billing for five-year terms. In the Q&A, management addressed GPU residual value, which it said is about 20 to 25 percent at year five for current B300 and GB300 hardware, with options to keep operating, redeploy, or sell. It also explained that maintenance CapEx is expensed because much of it is labor and vendor-covered warranty work. Project financing for Indonesia was described as covering about 70 percent of the project, with the balance funded by the balance sheet and customer prepayments. Management identified its main risks as hardware timing, site and power readiness, and customer acceptance and workload migration, and said contingency plans exist for each. The company said Egypt, Taiwan, and Thailand security and network intelligence operations remain important sources of collections and technical credibility, and that it is bidding on large projects in those markets. Chandan closed by asking investors to judge the company by contracts signed, equipment delivered, revenue recognized, and cash collected.
▸What is on the delivery schedule for 2027, which Yotta phases and NeutraDC phases are active, and what is assumed versus not assumed in guidance?Brian Kinstlinger · Alliance Global Partners
▸Does Yotta require any construction?Brian Kinstlinger · Alliance Global Partners
▸What has been the biggest obstacle in securing project financing, given previous comments about offers?Brian Kinstlinger · Alliance Global Partners
▸What is the terminal value of GPUs after five years, and could they be operated for a sixth year?Alex Latimore · Northland Capital Markets
▸Does the India and Indonesia CapEx forecast include maintenance CapEx, and how is it sequenced?Alex Latimore · Northland Capital Markets
▸Could you describe the Indonesia debt financing, including interest rate, customer financing share, and completion percentage?Alex Latimore · Northland Capital Markets
▸What is the biggest risk next year, whether people, power, facilities, or equipment acquisition?John Marc Roy · Water Tower Research
▸What is current headcount and the monthly OpEx run rate exiting Q2, given hiring plans across Thailand, India, and Taiwan?Bharath Nagaraj · Cantor Fitzgerald
▸Are GPU contracts take-or-pay at fixed prices, or indexed to spot prices, and does Gorilla bear margin risk if supply improves?Bharath Nagaraj · Cantor Fitzgerald
▸What utilization assumptions underpin 2026 and 2027 guidance?Bharath Nagaraj · Cantor Fitzgerald
▸What contribution have Egypt, Taiwan, and Thailand made in the first half?Bharath Nagaraj · Cantor Fitzgerald
Options
Chain Snapshot (daily)
| Strike | Call Bid/Ask | Call OI | Put Bid/Ask | Put OI |
|---|---|---|---|---|
| $2.50 | $4.80/$6.20 | 0 | --/$0.55 | 79 |
| $5.00 | $1.90/$3.90 | 0 | --/$1.00 | 103 |
| $7.50 | $0.95/$1.80 | 46 | $1.20/$1.50 | 171 |
| $10.00 | $0.35/$0.65 | 479 | $2.20/$3.90 | 197 |
| $12.50 | $0.05/$0.95 | 113 | $4.00/$7.10 | 1 |
| $15.00 | --/$0.35 | 55 | $6.00/$9.60 | 22 |
| $17.50 | --/$0.15 | 1 | $9.40/$10.70 | 1 |
| $20.00 | --/$0.60 | 7 | $11.00/$14.50 | 0 |
Short Interest
Cash Runway
Institutional Ownership
| Fund | $ value | Cost basis | Δ QoQ | Δ YoY | α life | Fund AUM |
|---|---|---|---|---|---|---|
| UBS Group AG | $7.0M | $16.94 | +$663K | +$4.4M | +0.0% | $562.11B |
| NATIONAL BANK OF CANADA /FI/ | $4.0M | $15.61 | −$179K | +$2.6M | -0.1% | $97.70B |
| STATE STREET CORPPassive | $3.3M | $18.41 | +$135K | +$3.3M | -0.2% | $2.89T |
| ROYAL BANK OF CANADA | $2.9M | $14.07 | +$1.1M | +$2.9M | -0.4% | $526.36B |
| BlackRock, Inc.Passive | $2.6M | $10.92 | −$16K | +$2.6M | — | $5.69T |
| ADVISOR GROUP HOLDINGS, INC. | $1.9M | $16.82 | +$286K | +$1.6M | — | $67.63B |
| SBI Securities Co., Ltd. | $1.9M | $21.00 | −$106K | +$632K | — | $3.62B |
| Legal & General Group Plc | $1.5M | $15.52 | +$122K | +$1.5M | -0.1% | $432.24B |
| JANE STREET GROUP, LLCMM | $1.3M | $17.09 | −$330K | +$1.0M | +1.5% | $92.10B |
| MORGAN STANLEY | $1.1M | $20.50 | +$549K | −$725K | -0.3% | $1.65T |
Ownership Over Time
5-year share-count history (top 10 holders by peak, incl. exited) + price
Analyst Coverage
| Quarter | Revenue | EBITDA | Net Inc | EPS | EPS Range | # Analysts |
|---|---|---|---|---|---|---|
| 2022 Q3 | 6M | — | 33M | $1.27 | $1.19 – $1.36 | 1 |
| 2022 Q4 | 5M | — | 51M | $1.95 | $1.83 – $2.08 | 1 |
| 2023 Q1 | 12M | -52M | -52M | $-2.00 | $-2.13 – $-1.87 | 1 |
| 2023 Q2 | 12M | -52M | -52M | $-2.00 | $-2.13 – $-1.87 | 1 |
| 2023 Q3 | 6M | -18M | -18M | $-0.70 | $-0.75 – $-0.65 | 1 |
| 2023 Q4 | 12M | -52M | -52M | $-2.00 | $-2.13 – $-1.87 | 1 |
| 2024 Q1 | 6M | -18M | -18M | $-0.70 | $-0.75 – $-0.65 | 2 |
| 2024 Q2 | 19M | -5M | -5M | $-0.20 | $-0.21 – $-0.19 | 1 |
| 2024 Q3 | 27M | 9M | 8M | $0.30 | $0.27 – $0.34 | 1 |
| 2024 Q4 | 20M | 3M | 3M | $0.09 | $0.06 – $0.11 | 1 |
| 2025 Q1 | 20M | 1M | 0M | $0.01 | $0.01 – $0.01 | 1 |
| 2025 Q2 | 22M | 5M | 5M | $0.17 | $0.12 – $0.21 | 1 |
| 2025 Q3 | 27M | 4M | 3M | $0.11 | $0.08 – $0.14 | 1 |
| 2025 Q4 | 34M | 7M | 7M | $0.24 | $0.17 – $0.30 | 1 |
| 2026 Q1 | 26M | 14M | 13M | $0.45 | $0.32 – $0.57 | 1 |
| 2026 Q2 | 39M | 4M | 1M | $0.03 | $0.02 – $0.04 | 2 |
| 2026 Q3 | 51M | -14M | -16M | $-0.58 | $-0.72 – $-0.26 | 2 |
| 2026 Q4 | 77M | -17M | -19M | $-0.68 | $-5.21 – $4.87 | 2 |
| 2027 Q1 | 132M | -11M | -13M | $-0.48 | $-0.60 – $-0.34 | 1 |
| 2027 Q2 | 150M | -9M | -12M | $-0.43 | $-0.54 – $-0.31 | 1 |
| 2027 Q3 | 177M | -4M | -7M | $-0.26 | $-0.33 – $-0.18 | 1 |
| 2027 Q4 | 226M | -1M | -6M | $-0.21 | $-0.26 – $-0.15 | 1 |
| 2028 Q1 | 364M | -26M | -32M | $-1.15 | $-1.45 – $-0.82 | 1 |
| 2028 Q2 | 432M | -12M | -20M | $-0.71 | $-0.89 – $-0.51 | 1 |
| 2028 Q3 | 501M | 17M | 7M | $0.26 | $0.19 – $0.33 | 1 |
| 2028 Q4 | 513M | 26M | 14M | $0.51 | $0.37 – $0.64 | 1 |
Corporate
Insider Trading (last 12mo)
| Date | Side | Insider | Title | Shares | Price | Dollars | Owned $ |
|---|---|---|---|---|---|---|---|
| 2026-04-15 | SELL | Medeiros Evan S | director | 12,604 | $12.16 | $153K | $255K |
| 2026-04-14 | SELL | Medeiros Evan S | director | 5,186 | $12.00 | $62K | $403K |
v2 analysis (legacy) — for comparison onlyclick to expand
Recent Research & News
Recent Research & News
2026-06-21Company news
- Q1 2026 Financial Performance & Guidance Upgrade: On May 27, 2026, Gorilla announced its financial results for the first quarter ended March 31, 2026. Revenue increased 55% year-over-year to $28.2 million, driven by strong project execution. The company achieved a major milestone as operating cash flow swung positive to $6.6 million (a $17.3 million year-over-year improvement). Cash and cash equivalents reached $98.4 million, up 373% year-over-year, while total debt remained low at $13.2 million. Gorilla reported an IFRS operating loss of $41.1 million, but management emphasized that this was distorted by non-cash charges, including $20.9 million in stock-based compensation and $18.9 million in foreign currency exchange losses. Based on strong momentum, the company raised its full-year 2026 revenue guidance to a range of $160 million to $200 million.
- Convertible Bond Offering: On June 3, 2026, Gorilla announced the pricing of a $107 million aggregate principal amount of 7.50% Senior Unsecured Convertible Notes due 2031. The registered offering is led by current institutional stakeholder Highbridge Capital Management.
- Supermicro Strategic Partnership: On June 2, 2026, Gorilla successfully closed a landmark $2 billion AI infrastructure supply agreement with Super Micro Computer, Inc. (Supermicro). The deal secures delivery of 20,736 B300 cards, 5,120 B200 cards, networking equipment, and related infrastructure. Beyond this transaction, the companies established a strategic framework to jointly pursue multi-billion-dollar opportunities across the Asia-Pacific region.
- NeutraDC Capacity Agreement: On May 26, 2026, Gorilla signed a strategic agreement with Indonesian data center platform NeutraDC, securing an initial 5.5 MW of AI-focused data center capacity in Batam. This allocation is scheduled to scale rapidly to 18 MW by November 2026 to support Gorilla's regional expansion.
▸ Thesis-test Findings
Gorilla Technology Korat Thailand data center construction status
On May 5, 2026, Gorilla announced the acquisition of a 40-acre (100 rai) strategic land site in Korat (Nakhon Ratchasima), Thailand, to develop a 200MW AI data center campus designed for a 150MW net IT load across six high-density data halls. As of June 2026, construction has not yet begun; however, site preparation, water, power, and dark fiber connectivity have already been identified. Construction is expected to officially commence in July 2026, subject to final engineering, permitting, and mobilization. The first phase is targeted for completion in Q1 2027, with Gorilla projecting up to $1.5 billion in annualized revenue from the campus by 2028 at full commercial utilization.
Yotta India GPU infrastructure partnership Gorilla Technology 2026
Gorilla's partnership with India's Yotta Data Services has expanded exponentially in 2026. Initially establishing a contract in March 2026 to supply 640 Nvidia HGX B200 servers (over 5,000 GPUs) representing a projected $500 million in revenue over five years, the alliance was dramatically upscaled on April 29, 2026. Gorilla signed a follow-up agreement to deploy an additional 20,736 B300 GPU cards in India, representing a total project value of approximately $2.8 billion. This expanded deployment is scheduled for completion by September 30, 2026. Execution is heavily backed by Gorilla's subsequent $2 billion hardware deal with Supermicro, and offtake is highly derisked, with Nvidia expected to account for roughly half of the capacity through a 4-year commitment tied to a major DGX Cloud cluster.
Gorilla Technology Egypt smart city contract payments cash collections
A core bear case against Gorilla has been its heavy reliance on the $270 million Egypt Smart Government Security Convergence contract signed in 2023, which was denominated in Egyptian Pounds (EGP) and exposed the firm to severe currency devaluation—including a $25.6 million foreign currency exchange loss in FY2025 and an additional $18.9 million loss in Q1 2026. However, findings from the Q1 2026 earnings call indicate a significant positive shift in collections. During Q1 2026, Gorilla completed key milestones, resulting in substantial cash collections from the Egyptian government. Crucially, the bank-issued advance payment letters of guarantee associated with completed stages have been released. This reduced the company’s restricted cash on the balance sheet to nearly zero and successfully converted the project’s book revenue into liquid cash.