i-80 Gold Corp.v3 5.5/10 · 2026-11-03i-80 Gold Corp. specializes in the exploration, development, and production of gold and silver mineral deposits within the United States. The company holds a 100% interest in the Lone Tree property, encompassing approximately 12,000 acres in Northern Nevada's Battle Mountain-Eureka region. Its significant assets in Northern Nevada also include the Ruby Hill property, the 31,000-acre McCoy-Cove project, and the Buffalo Mountain property, all located within the Battle Mountain Trend. Additionally, i-80 Gold Corp. oversees the Granite Creek Project, situated in the Getchell Trend of Northern Nevada. Established in 2020, the company's primary office is in Reno, Nevada.
2-Year Price History
Valuation v3 Opus worker · 2026-11-03
i-80 Gold is a Nevada gold developer partway through a large build. It mines about 45k oz a year from Granite Creek and has its ore toll-milled by a third party at roughly $350 per ton. It is rebuilding its own Lone Tree autoclave ($430M, first gold Q4 2027) so that Granite Creek and Archimedes can grow to a lower-cost 150-200k oz a year from 2028, with Mineral Point (a big heap-leach project with no permit yet and roughly $1.4B+ of capex) planned as the step to 400-600k oz in the 2030s. The Q1 2026 recapitalization (Franco-Nevada royalty, gold prepay, 3.75% converts at $1.93) removed the going-concern doubt. The company has $411M of cash against about $462M of face debt, plus about $350M of further liquidity it expects (in-the-money $0.70 warrants, a prepay accordion, a stockpile facility). Phase 1 looks funded at today's gold price, and the Q3 2026 call was clean: Lone Tree on schedule, 20% of contingency used, oxide upside at both mines. The stock ($1.30, latest close 2026-11-03; 868M shares, about 1,019M with warrants) has fallen 37% from February's $2.08 as gold fell from about $5,000 to about $3,950. Short interest is about 94M shares (roughly 10 days to cover). Today it earns roughly nothing; 2027 burns about $380M; FCF turns positive in 2028. A DCF of only the funded hub-and-spoke business (gold flat at $3,950, 7x terminal multiple because the reserve life is finite) gives about $0.94 a share. Adding a risked value for Mineral Point, Granite Creek open pit and Cove brings fair value to about $1.45, so the stock is about 10-15% cheap rather than 40%. All five sell-side analysts rate it Buy (mean target about US$3.30), but they use higher gold decks. Each $500/oz move in gold moves the Phase-1 value by about $0.48 a share, so this is a leveraged, execution-heavy gold bet, not a cash-flow bargain. The CEO bought $3M of stock in 2026, which is a positive. Rating 5.5: fair to slightly cheap, with upside if gold recovers and Lone Tree starts on time. Research rating 6: the Mineral Point funding path and the realistic 2028 cost per ounce can be worked out, but the result depends on gold.
A deep dive would have to establish: Can the hub-and-spoke reach about 150k+ oz at under about $2,200/oz AISC in 2028, with Lone Tree commissioned on budget, and can Mineral Point's roughly $1.5B capex be financed without heavy equity dilution at sub-$4,000 gold?
Research (expand)
What the company does
i-80 Gold (formerly a 2021 Equinox Gold spin-out, now run by ex-Perpetua/Kinross/Barrick CEO Richard Young since late 2024) owns a portfolio of Nevada gold deposits around a single processing hub: the Lone Tree autoclave/CIL plant near Battle Mountain. The plan is "hub-and-spoke":
- Granite Creek Underground (producing): Sept-2026 feasibility study set maiden reserves of 556koz at 7.87 g/t, an 8.5-year life, 75koz/yr peak 2028-32 at AISC $1,915/oz (excluding Lone Tree allocation). After-tax NPV5 is $193M at $3,000 gold and $598M at $4,500.
- Archimedes Underground (Ruby Hill, Eureka): construction decided Sept 2025, first ore Q4 2026. High-grade oxide goes onto the existing Ruby Hill leach pad (first ounces Q1 2027); sulfide is stockpiled for Lone Tree. PEA NPV5 was $581M at $2,900 gold. Feasibility study H2 2027.
- Lone Tree plant refurbishment: $430M (12% contingency), 44% committed, 74% of procurement awarded, 20% of contingency used, first gold Q4 2027. Processing cost falls from about $254-350/t (toll) to about $105/t.
- Mineral Point open-pit heap leach: the biggest asset (PEA about 282koz/yr gold-equivalent, NPV5 $2.3B at $3,000 gold, capex about $1.4B). PFS H2 2027, formal permitting not started. Now resequenced as Phase 2.
- Granite Creek Open Pit (PFS H2 2028) and Cove (pushed to the late 2030s, dewatering costs higher than the PEA).
2026 output is about 40-50koz (Granite Creek at the low half of its 30-40koz guidance), toll-milled at a third party with limited capacity. About 9koz sits in inventory at the processor.
The investment case
Owning the mill is the whole thesis. Moving from toll milling to owned processing should raise margins by about $1,000-1,500/oz (management's figure), and two high-grade underground mines feeding an owned autoclave should make about 150-200koz/yr from 2028. Phase 1 looks funded:
- $411M of cash at 9/30/26.
- About $106M from 150.8M warrants at $0.70 (deep in the money, expire Nov 2027).
- A $100M prepay accordion, the last $25M of the Franco-Nevada royalty money, and a stockpile working-capital facility.
Management says no equity raise is needed through 2027. Lone Tree payments lag commitments by about 4 months, so cash outflow peaks in Q2-Q3 2027 and some spills into 2028. Upside levers:
- Oxide surprises at both mines (cheap heap-leach ounces).
- Granite Creek, Archimedes (Ruby Deeps, long-hole mining) and Mineral Point (eastern extension) all look larger than their PEAs.
- A Nevada consolidator (Nevada Gold Mines, i.e. Barrick/Newmont) could find the processing hub plus deposits worth buying. Buyout logic exists, but nothing points to it.
What it earns today (real owner earnings)
About breakeven:
- 9M-2026 gross profit was $29.7M (Q3 only $5.0M with fewer ounces sold). That points to about $35-40M for the year, plus about $10M of D&A.
- Less about $28M of G&A, about $13M of SBC (9M: $10.0M) and about $5M of sustaining capex.
That gives unlevered owner earnings of roughly $0 (range -$25M to +$20M). Pre-development/exploration ($88M in 9M, expensed under US GAAP until reserves are declared) and growth capex are treated as growth investment. 9M operating cash flow was -$127M and capex $57M. EBITDA is negative, so EV/EBITDA and P/E on current numbers mean nothing.
Five-year free cash flow (unlevered, after SBC, Phase 1 only, gold flat $3,950)
- Q4 2026: about -$70M (pushes year-end cash to about $340M before warrants and facilities).
- 2027: -$380M. About 55koz at toll and heap-leach margins (+$65M). Against that: about $280M of Lone Tree cash, $80M of mine development, $90M of drilling, studies and predevelopment (including Mineral Point PFS work), about $40M of stockpile build and about $35M of G&A.
- 2028: +$40M. About 130koz at about $1,650/oz margin = $215M. Less $60M of Lone Tree catch-up payments, $50M of growth capex, $50M of Mineral Point permitting/predevelopment and the royalty.
- 2029: +$175M. About 165koz at about $1,800/oz margin (AISC about $2,150, above the FS figure for labor inflation and corporate G&A). Less royalty (1.5% NSR), about $30M of cash tax, exploration and growth capex.
- 2030: +$200M.
- 2031: +$205M. About 175koz; Franco-Nevada steps to a 3% NSR.
The gold prepay (39,978oz delivered over 30 months from Jan 2028, about $155M carrying) is treated as debt, not a cash-flow deduction. In 2029 about 60% of EBITDA (about $290M) reaches owners.
The projection deliberately excludes Mineral Point's roughly $1.4-1.6B construction (plausibly 2029-2031). Including it would drive 2029-31 FCF to about -$200M to -$400M a year in exchange for 400-500koz of output in the early 2030s.
What it looks like in five years
There are three cases.
- Phase 1 alone: a 170koz Nevada producer with about 8 years of Granite Creek reserve plus Archimedes resource. That is a finite-life miner, valued at 6-8x FCF unless exploration keeps replacing ounces.
- Full plan: in 2031 it is building or ramping Mineral Point toward 400-500koz. That is a genuine mid-tier with a 15-20 year life, worth 8-12x FCF.
- Bad case: labor shortages (already hurting Granite Creek and drilling), Lone Tree start-up problems (autoclaves are notoriously hard to commission) and a lower gold price lead to another dilutive raise.
The company's record before Young was repeated guidance misses and serial dilution. 2026 has been better, but production is still at the low end of guidance. I am moderately confident in Phase 1 by 2028-29 and not confident in Mineral Point timing or funding.
Fair value and the multiples we pay
- Share count: 868.2M shares (10-Q cover) × $1.30 = $1,129M market cap. Counting the $0.70 warrants it is 1,019M fully diluted, with $106M of cash coming in.
- Debt: $287.5M 3.75% converts due 2031 (conversion $1.93, out of the money), $155M gold prepay and about $20M of equipment debt, against $411M of cash. Net debt is about $51M at face, so EV is about $1.18B.
- DCF, Phase 1 only: the FCF above (incl. Q4-26), plus 7x 2031 FCF ($1.44B), discounted at 10%, gives about $904M. Less net debt, plus warrant cash, that is about $959M, or $0.94 a share.
- Gold sensitivity: each ±$500/oz of gold moves this by about ±$0.48 a share ($3,450 gives about $0.46; $4,500 gives about $1.42).
- Full-plan DCF: with Mineral Point built (8-10x a roughly $560M steady-state FCF) it is about $2.0 a share, but at low confidence.
- Fair value about $1.45: the Phase-1 DCF plus about $0.35 for Mineral Point (PEA NPV5 of about $4B at $3,950 gold, cut for a 10% discount rate, a start after 2029, permitting risk and dilutive funding of the capex) plus about $0.15 for Granite Creek open pit and Cove.
- Multiples: at $1.30 we pay about 4x 2029E EV/EBITDA and about 10x 2029E P/E. FCF yield is negative until 2028 (2027E about -34%). If 2029 comes in, buying now gives a sub-10x multiple within 3 years, but only with gold near $4,000 and Lone Tree on time.
Management, governance, risks, competition
Richard Young (CEO since late 2024) and COO Paul Chawrun are credible builders. They have hit Archimedes and Lone Tree milestones and are honest about delays (Mineral Point and Archimedes studies slid to H2 2027, Cove deferred). The CEO bought about $3M of stock in Mar and Aug 2026, and no insiders have sold. There is no capital return; shareholders face dilution instead (warrants add about 17% to the share count; the converts would add 149M shares above $1.93).
No fraud or Chinese-control issues. There is a history of value-destroying financings before this management team, and the Franco-Nevada royalty steps from 1.5% to 3% across every property in 2031, a permanent cost.
Key risks:
- Gold price (the biggest factor).
- Lone Tree commissioning, plus outstanding air-quality and mercury permits for the new design.
- Nevada underground labor shortages and contractor turnover.
- Eureka housing constraints for Archimedes and Mineral Point.
- Water inflows at Granite Creek (now 1,300-1,400 gpm, with treatment going up to 3,500 gpm).
- Single-customer and single-toll-processor concentration until Lone Tree runs.
- Mineral Point funding at about $1.5B.
Competition is mostly for labor and toll capacity against Nevada Gold Mines, Kinross and SSR. Owning a permitted refractory plant is a real regional moat, because new autoclaves are nearly impossible to permit.
Sentiment (score 4/10)
The tape is cool rather than capitulating:
- The stock is -37% from February's $2.08, at 34% of its 1-year range ($0.89-2.08).
- Short interest is about 94M shares (about 10-11% of shares, 7-16 days to cover) and still rising. Some of that is likely convert-arbitrage hedging.
- Gold has fallen from about $5,000 to about $3,950 (-5% in the past month) amid rate hikes.
The sell side remains uniformly bullish: 5 analysts, all Buy (RBC, National Bank, SCP and others), mean target about US$3.31 (C$4.62), range US$2.85-3.97. That is far above my value and reflects higher gold decks and P/NAV on full-plan NAVs. Retail is split between "cheapest Nevada developer" and "serial diluter". This is not euphoria and not blood on the ground. Implied volatility is high, but there is no earnings floor, so it is not a covered-call setup.
- /Users/gregwo/stocks2/data/analysisv3/context/IAUX.md (Q3 2026 call transcript, prior call summaries, short interest, price history)
- /Users/gregwo/stocks2/data/edgar_filings/IAUX/10-Q_2026-11-02_0001628280-26-068954.html (shares outstanding 868,227,720; cash $411.4M; debt; warrants 150.8M at $0.70)
- https://www.sec.gov/Archives/edgar/data/0001853962/000162828026068966/i-80goldcorppressreleaseq3.htm
- https://www.sec.gov/Archives/edgar/data/0001853962/000162828026068954/iaux-20260930.htm
- https://finviz.com/news/394022/i-80-gold-announces-positive-feasibility-study-and-initial-mineral-reserves-for-granite-creek-underground-after-tax-npv5-of-118-million-at-2750oz-au-increasing-to-598-million-at-4500oz-au
- https://rallies.ai/news/i-80-gold-secures-2875m-375-convertible-notes-to-fund-nevada-gold-projects
- https://www.i80gold.com/i-80-gold-closes-250-million-royalty-financing-with-franco-nevada-and-completes-retirement-of-certain-legacy-debt-obligations/
- https://www.newswire.ca/news-releases/i-80-gold-announces-positive-preliminary-economic-assessment-on-the-archimedes-underground-project-nevada-after-tax-npv-5-of-127-million-with-an-after-tax-irr-of-23-at-us-2-175-oz-au-858579546.html
- https://www.nsenergybusiness.com/news/i-80-gold-estimates-total-capex-of-1-4bn-for-mineral-point-gold-project
- https://www.miningstockeducation.com/2026/10/i-80-gold-provides-a-development-update-archimedes-underground-and-lone-tree-plant-refurbishment-remain-on-track-and-mineral-point-open-pit-prioritized-in-updated-development-plan/
- https://www.cruxinvestor.com/posts/i-80-gold-corp-the-nevada-processing-moat-institutional-buy-side-analysis-of-second-quarter-2026-execution-capital-structure
- https://ca.marketscreener.com/quote/stock/I-80-GOLD-CORP-138206708/consensus/
- https://stockanalysis.com/quote/tsx/IAU/forecast/
- https://tradingeconomics.com/commodity/gold
- https://www.insiderscreener.com/en/insider/i/129803
Financials — Adjusted
Adjusted · TTM 2026-Q3 · USD
| TTM & Fiscal-Year P&L | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| Revenue | 131+35% | 95.2+89% | 50.3-8% | 54.9+49% | 37.0 |
| Gross profit | 8.30+50% | 11.5 | -18.4 | -11.0-327% | 4.85 |
| Operating expenses | 143+68% | 110+67% | 65.6-27% | 89.9+52% | 59.2 |
| ▸Adj EBITDA | -131 | -94.9 | -79.7 | -89.5 | -47.0 |
| ▸Adj OCF | -149 | -66.1 | -81.7 | -58.2 | -54.4 |
| CapEx | -61.7 | -8.28 | -7.85 | -46.2 | -50.2 |
| Adj FCF | -211 | -74.4 | -89.5 | -104 | -105 |
| Interest expense | 30.8 | 30.3 | 32.2 | 27.9 | 17.5 |
| ▸Adj net income | -158 | -121 | -116 | -126 | -60.0 |
| ▸Owner's earnings | -100 | -- | -- | -- | -- |
claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2022→FY2025 +2026YTD
| Where the Cash Went | Total | 2026YTD | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|---|
| ▸Claimed: EBITDA | -506 | -148 | -170 | -80.5 | -53.5 | -54.5 |
| FCF (OCF−capex) | -568 | -209 | -77.3 | -90.0 | -95.1 | -96.8 |
| Net income | -664 | -179 | -199 | -116 | -89.7 | -79.2 |
| ▸Capital returned | -739 | -510 | -70.7 | -54.5 | -60.2 | -43.9 |
| Buybacks | -504 | -11.0 | -342 | -119 | -29.5 | -2.65 |
| Dividends | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest paid | 133 | 24.6 | 30.3 | 32.2 | 27.9 | 17.5 |
| Debt paid down | -367 | -523 | 241 | 32.2 | -58.6 | -58.7 |
| ▸Reinvestment | 159 | 56.8 | 8.73 | 7.50 | 36.2 | 50.2 |
| Capex (PP&E) | 169 | 56.8 | 8.28 | 7.85 | 46.2 | 50.2 |
| Intangibles & M&A | -10.4 | 0.00 | 0.00 | -0.42 | -10.0 | 0.00 |
| Leases signed (net Δ) | 0.56 | -- | 0.44 | 0.07 | 0.04 | -- |
| Retained / other | 314 | 326 | 23.7 | -2.89 | 3.06 | -35.5 |
negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.
Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.
Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).
SBC over the Total window: 10 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.
| Balance Sheet | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| ▸Assets (total) | 1156 | 703 | 656 | 654 | 642 |
| ▸Liabilities (total) | 931 | 357 | 315 | 309 | 309 |
| Net debt (incl. leases) | 41.7 | 111 | 173 | 178 | 67.6 |
| Net debt / Adj EBITDA | -- | -- | -- | -- | -- |
| Net debt / Adj FCF | -- | -- | -- | -- | -- |
| Adj EBITDA / interest | -4.25 | -3.13 | -2.48 | -3.21 | -2.68 |
| Shares outstanding | 866 | 827 | 410 | 410 | 410 |
| Dilution (YoY) | +6.1% | +101.9% | +49.1% | +23.7% | +0.5% |
| Employees | 109 | 133 | 109 | 2.00 | 2.00 |
| Margins | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| Gross margin | 6.3%+0.7 | 12.1%+48.7 | -36.6%-16.5 | -20.1%-33.2 | 13.1% |
| Adj EBITDA margin | -100.0%-22.3 | -99.7%+58.7 | -158.4%+4.5 | -162.9%-35.8 | -127.2% |
| Adj OCF margin | -114.2%-58.5 | -69.5%+92.8 | -162.3%-56.2 | -106.0%+41.3 | -147.3% |
| Adj FCF margin | -161.3%-101.7 | -78.2%+99.7 | -177.9%+12.3 | -190.2%+93.0 | -283.2% |
| Net income margin | -202.7%-67.8 | -208.9%+22.6 | -231.4%-68.2 | -163.3%+51.0 | -214.3% |
| Adj NI margin | -120.7%-9.0 | -127.3%+103.3 | -230.5%-1.7 | -228.8%-66.5 | -162.3% |
| ROIC (adj, after-tax) | -15.8% | -14.9% | -12.5% | -14.8% | -9.6% |
| Cost of debt | 8.2% | 17.9% | 16.9% | 16.4% | 18.1% |
Earnings Calls
Earnings Call · 2026 Q3
i-80 Gold's third quarter 2026 call reviewed steady progress toward its goal of becoming a multi-asset, mid-tier gold producer in Nevada. Management highlighted the September feasibility study for Granite Creek Underground, which established the company's first mineral reserves and outlined a higher production rate and a longer mine life than the March 2025 preliminary economic assessment (PEA). The study points to an eight-and-a-half-year mine life after depletion since the PEA. Ongoing drilling at Granite Creek is aimed at converting resources, expanding the resource base, and extending mine life across five focus areas, with a multi-year program starting in 2027. At Archimedes Underground, development remains on track for first gold mining in the fourth quarter of 2026. Development of roughly 2,300 meters for the nine-month period was well ahead of plan, and underground operating costs are in line with the PEA, though capital costs are expected to be slightly higher. Metallurgical tests confirmed strong heap leach recoveries for higher-than-expected oxide material from the upper 426 Zone. Management decided to place this oxide on the existing Ruby Hill heap leach pad by year-end rather than sell it under the ore purchase agreement, which is expected to significantly reduce processing costs. Production from material placed on the pad in Q4 will be recorded in Q1 2027. Archimedes refractory material will be stockpiled in 2027 for processing at the wholly owned Lone Tree plant rather than at a third-party facility. The Lone Tree plant refurbishment is on schedule and largely on budget, with first gold pour targeted for Q4 2027. Bulk demolition is complete, and the general contractor is expected to be awarded in December, with mobilization in early 2027. The overall capital estimate is $430 million. By the end of September, 74% of procurement packages by value had been awarded and 44% of total project capital was committed. Labor costs are running 5% to 10% above original estimates but remain within contingency, and about 20% of contingency had been used at quarter end. Management noted that payment lags of roughly four months, rather than the 30 days assumed in budgeting, will push some cash outflows into 2028. At Granite Creek Underground, mining was lower than planned in Q3 due to high contractor turnover caused by competition for skilled labor. Management has since introduced a retention incentive program, and staffing has returned to steady state. Q3 gold production was about 9,100 ounces, and the project is expected to land in the lower half of its 30,000 to 40,000 ounce full-year guidance. Water management is under control, with a second water treatment plant in commissioning and two new dewatering wells expected to raise treatment capacity to about 3,500 gallons per minute. Mineral Point, the next major development project, received about 26,000 meters of drilling in the quarter, with nine rigs now active. Early results suggest the deposit extends beyond the 2025 PEA pit shell, particularly to the east. The pre-feasibility study is expected in the second half of 2027, and formal permitting has not begun. Granite Creek Open Pit pre-feasibility work has started, with technical and environmental baseline work expected in Q1 2027. Cove Underground's feasibility study is expected in Q4 2026, but the project has been moved later in the pipeline to the 2030s, as a future source of refractory feed. Financially, the company ended the quarter with about $411 million in cash, down from about $465 million at the end of Q2. Management expects up to about $350 million in additional liquidity over the next 18 months from the gold prepay accordion, warrant exercises, the Franco-Nevada NSR, and stockpile financing, though most of these depend on lender approval or warrant exercise. A corporate credit facility is also being discussed to fund Mineral Point without further equity dilution. Q3 gold production was about 11,700 ounces and sales were about 7,750 ounces, compared with 12,430 and 9,370 ounces a year earlier. Nine-month production was about 33,650 ounces. Net loss increased, driven by pre-development expenses and financing and non-cash items. Beginning in Q4 2026, qualifying costs at Granite Creek will be capitalized because reserves have been declared. For 2026 guidance, production is expected in the lower half of the range, and operating costs are expected at or below the low end. Exploration spending is expected below guidance due to late rig deliveries and personnel shortages. Management described 2027 as a transition year, with ramp-up at both underground mines and completion of the plant refurbishment. The company targets growth from 40,000 to 50,000 ounces per year to 150,000 to 200,000 ounces per year beginning in 2028, a medium-term target of 400,000 to 500,000 gold equivalent ounces by the early 2030s, and 500,000 to 600,000 ounces per year by the mid-2030s. Full 2027 guidance will be provided with year-end reporting in February.
▸How will Archimedes ore be sourced in Q4 and 2027, including the stoping ramp-up and the split between oxide and sulfide feed?Justin Chan · SCP Resource Finance
▸What is a good entry-level mining rate for 2027?Justin Chan · SCP Resource Finance
▸When will cash capex outflows converge with accrued capex, given the payment delays?Justin Chan · SCP Resource Finance
▸Does the pushed-back Granite Creek ventilation raise affect production flexibility, and is contractor turnover fully addressed?Don DeMarco · National Bank
▸What will the 2027 guidance include, such as cost metrics and ounces mined or processed?Don DeMarco · National Bank
▸Should the Mineral Point pre-feasibility study be a de-risked version of the 2025 PEA, or will it include material changes?Don DeMarco · National Bank
▸What is the status of Archimedes drilling, oxide, ground conditions, and how will the 2027 feasibility study compare to the prior technical report?Harrison Reynolds · RBC
▸How much material should be stockpiled before Lone Tree commissioning, and what are the trade-offs?Harrison Reynolds · RBC
▸Why were oxide grades so strong at Granite Creek and Archimedes, and will they continue?John Tumazos · John Tumazos Very Independent Research
▸When will the large capital outlays and cash draws occur?John Tumazos · John Tumazos Very Independent Research
▸Is the Lone Tree general contractor tender close to completion, when will it be signed in Q4, and when will construction start?
▸Is $411 million enough to recommission Lone Tree without an equity raise, and how confident is management that Archimedes will begin production mining before 2027?
▸Will Ruby Hill be used to leach ore?Adella Harding · Elko Daily Free Press
▸What changed in the timing of the upcoming technical studies for Archimedes, Mineral Point, and Granite Creek Open Pit?
SEC Filing Findings
SEC Filing — material findings
2026-11-02 · depth 9/10risk 7Liquidity/Covenants▸2026 Gold Prepay is secured by first-ranking security over substantially all assets and contains customary financial covenants and events of default; 39,978 oz gold deliveries from Jan 2028 to Jun 2030 are a fixed future obligation.
2026 Gold Prepay is secured by first-ranking security over substantially all assets and contains customary financial covenants and events of default; 39,978 oz gold deliveries from Jan 2028 to Jun 2030 are a fixed future obligation.
risk 6Dilution▸2026 Convertible Debentures ($287.5M, 3.75%, due 2031) convertible at ~$1.93/share (~149M underlying shares), a large potential dilution overhang versus ~867M shares outstanding; change-of-control put at par.
2026 Convertible Debentures ($287.5M, 3.75%, due 2031) convertible at ~$1.93/share (~149M underlying shares), a large potential dilution overhang versus ~867M shares outstanding; change-of-control put at par.
risk 6Liquidity/Covenants▸Liquidity cushion partly depends on conditional sources: $25M NSR tranche and $100M gold prepay accordion require conditions and lender approval; company is in talks for a corporate revolver 'if needed'. Management tied the $25M to $25M of 2026 Mineral Point spending.
Liquidity cushion partly depends on conditional sources: $25M NSR tranche and $100M gold prepay accordion require conditions and lender approval; company is in talks for a corporate revolver 'if needed'. Management tied the $25M to $25M of 2026 Mineral Point spending.
risk 6Liquidity/Covenants▸Lone Tree refurbishment capital commitments of $137.9M over next 12 months; invoicing lag of 4-5 months rather than 30 days, and labor costs running 5-10% above estimates, with ~20% of contingency drawn and ~44% committed.
Lone Tree refurbishment capital commitments of $137.9M over next 12 months; invoicing lag of 4-5 months rather than 30 days, and labor costs running 5-10% above estimates, with ~20% of contingency drawn and ~44% committed.
Short Interest
Executive Compensation (2023.0-2025.0)
Cash Runway
Institutional Ownership
| Fund | $ value | Cost basis | Δ QoQ | Δ YoY | α life | Fund AUM |
|---|---|---|---|---|---|---|
| Condire Management, LP | $118M | $0.62 | +$0 | +$3.0M | — | $942M |
| SPROTT INC. | $38.5M | $1.21 | −$13.4M | −$22.5M | — | $3.02B |
| VANGUARD CAPITAL MANAGEMENT LLCPassive | $36.5M | $1.52 | +$1.7M | +$36.5M | — | $4.68T |
| VAN ECK ASSOCIATES CORP | $30.8M | $1.12 | −$538K | −$11.3M | — | $164.08B |
| Pale Fire Capital SE | $27.1M | $0.86 | −$2.9M | −$3.5M | — | $1.41B |
| Tidal Investments LLC | $26.9M | $1.24 | +$14.8M | +$20.8M | — | $41.21B |
| Nokomis Capital, L.L.C. | $26.5M | $0.60 | −$5.4M | −$10.9M | — | $280M |
| Trek Financial, LLC | $17.7M | $0.85 | +$826K | +$2.3M | — | $2.01B |
| TWO SIGMA INVESTMENTS, LP | $16.0M | $1.30 | +$8.9M | +$14.3M | — | $128.44B |
| Groupe la Francaise | $8.1M | $1.20 | +$144K | +$8.1M | — | $8.12B |
Ownership Over Time
5-year share-count history (top 10 holders by peak, incl. exited) + price
Related Stocks
Investors who own this also own
Stocks held by the same active managers as this one, ranked by score — how much more often these appear together than random chance (1× = baseline). Excludes index ETFs and market makers; minimum 3 shared holders.
| Ticker | Name | Co-holders | Score |
|---|---|---|---|
| BTG | B2Gold Corp. | 3 | 271.96× |
Analyst Coverage
| Quarter | Revenue | EBITDA | Net Inc | EPS | EPS Range | # Analysts |
|---|---|---|---|---|---|---|
| 2023 Q1 | 5M | -11M | -19M | $-0.02 | $-0.02 – $-0.02 | 1 |
| 2023 Q2 | 5M | -14M | -23M | $-0.03 | $-0.03 – $-0.03 | 1 |
| 2023 Q3 | 15M | -28M | -37M | $-0.04 | $-0.04 – $-0.04 | 1 |
| 2024 Q1 | 26M | -25M | -34M | $-0.04 | $-0.04 – $-0.04 | 1 |
| 2024 Q2 | 29M | -27M | -37M | $-0.04 | $-0.04 – $-0.04 | 1 |
| 2024 Q3 | 33M | -4M | -13M | $-0.02 | $-0.02 – $-0.02 | 1 |
| 2024 Q4 | 38M | 0M | -7M | $-0.01 | $-0.01 – $-0.01 | 1 |
| 2026 Q2 | 44M | -29M | -39M | $-0.04 | $-0.04 – $-0.04 | 1 |
| 2026 Q3 | 50M | -22M | -32M | $-0.04 | $-0.04 – $-0.04 | 1 |
| 2026 Q4 | 45M | -34M | -44M | $-0.05 | $-0.05 – $-0.05 | 1 |
| 2027 Q1 | 32M | -38M | -48M | $-0.06 | $-0.06 – $-0.06 | 1 |
| 2027 Q2 | 41M | -36M | -48M | $-0.05 | $-0.05 – $-0.05 | 1 |
| 2027 Q3 | 44M | -33M | -45M | $-0.05 | $-0.05 – $-0.05 | 1 |
| 2027 Q4 | 53M | -27M | -39M | $-0.05 | $-0.05 – $-0.05 | 1 |
| 2028 Q1 | 71M | -27M | -41M | $-0.05 | $-0.05 – $-0.05 | 1 |
| 2028 Q2 | 178M | 47M | 29M | $0.03 | $0.03 – $0.03 | 1 |
| 2028 Q3 | 210M | 72M | 49M | $0.06 | $0.06 – $0.06 | 1 |
| 2028 Q4 | 217M | 81M | 54M | $0.06 | $0.06 – $0.06 | 1 |
| 2029 Q1 | 217M | 79M | 49M | $0.06 | $0.06 – $0.06 | 1 |
| 2029 Q2 | 217M | 76M | 43M | $0.05 | $0.05 – $0.05 | 1 |
| 2029 Q3 | 217M | 79M | 43M | $0.05 | $0.05 – $0.05 | 1 |
| 2029 Q4 | 213M | 79M | 41M | $0.05 | $0.05 – $0.05 | 1 |
| 2030 Q1 | 216M | 84M | 43M | $0.05 | $0.05 – $0.05 | 1 |
| 2030 Q2 | 216M | 87M | 43M | $0.05 | $0.05 – $0.05 | 1 |
| 2030 Q3 | 216M | 91M | 45M | $0.05 | $0.05 – $0.05 | 1 |
| 2030 Q4 | 131M | 30M | -14M | $-0.02 | $-0.02 – $-0.02 | 1 |
Corporate
Insider Trading (last 12mo)
| Date | Side | Insider | Title | Shares | Price | Dollars | Owned $ |
|---|---|---|---|---|---|---|---|
| 2026-09-02 | SELL | Begeman John Arthur | director | 19,231 | $1.74 | $33K | $1.44M |
| 2026-08-18 | BUY | Savarie David Roger | officer: EVP, General Counsel | 4,575 | $1.59 | $7K | $436K |
| 2026-08-18 | BUY | Young Richard Scott | director, officer: President and CEO | 1,000,000 | $1.62 | $1.62M | $9.67M |
| 2026-05-28 | SELL | Begeman John Arthur | director | 24,356 | $1.59 | $39K | $1.32M |
| 2026-05-15 | BUY | Yopps Steven W. | director | 50,000 | $1.47 | $74K | $74K |
| 2026-03-30 | BUY | Seaman John William | director | 32,000 | $1.42 | $45K | $551K |
| 2026-03-25 | BUY | Butler Ronald Jr | director | 17,730 | $1.41 | $25K | $71K |
| 2026-03-25 | BUY | Savarie David Roger | officer: EVP, General Counsel | 6,500 | $1.40 | $9K | $518K |
| 2026-03-25 | BUY | Young Richard Scott | director, officer: President and CEO | 1,000,000 | $1.40 | $1.40M | $6.96M |
| 2025-12-09 | BUY | Seaman John William | director | 20,000 | $1.30 | $26K | $451K |
| 2025-11-25 | BUY | Seaman John William | director | 30,000 | $1.03 | $31K | $337K |
| 2025-11-17 | BUY | Savarie David Roger | officer: SVP, General Counsel | 5,000 | $1.05 | $5K | $276K |
v2 analysis (legacy, 2026-08-11) — for comparison onlyclick to expand
Thesis
i-80 Gold is a Nevada gold developer/producer in the middle of a multi-year transformation from a capital-starved, toll-milling junior into a self-sufficient hub-and-spoke producer anchored by the Lone Tree autoclave refurbishment. The company just completed an ~$787.5M recapitalization (Franco-Nevada NSR royalty, gold prepay facility, convertible notes) that retired high-cost legacy debt, removed going-concern doubt, and left it with ~$465M cash. Realized gold prices near $4,500-4,900/oz are a major tailwind. But the business today produces no real owner earnings: Granite Creek is still ramping through ground-control and ventilation issues, Archimedes and Mineral Point studies keep slipping (feasibility pushed to mid-2027), Lone Tree's critical air-quality/mercury permits are still outstanding, and toll-milling constraints are causing production/sales timing mismatches (Q2: 11,100oz produced vs only 5,335oz sold). Shares outstanding have roughly doubled in a year (410M to 862M), reflecting how much of the funding came via dilution rather than free cash flow. The story is now credibly funded through the construction phase (2026-2028), which materially de-risks insolvency, but execution risk (permitting, contractor/rig availability, dewatering) remains the swing factor between a re-rate toward management's ~$5B NAV narrative and a value-destructive slog with further capital needs.
Trade Signal
Short/avoid: at $1,431M market cap IAUX trades ~50% above the analyst's fair value and even further above the discounted market-should-pay level, with the bullish Lone Tree/Granite Creek transformation story already well-known, dilution running near 94% TTM, and owner earnings still deeply negative - the gold-price/recap euphoria has outrun the still-unresolved permitting and execution risk.
Stock is up 179% over the past year and 19% in the last month, riding the ~$787.5M recapitalization (Franco-Nevada NSR + gold prepay) that removed going-concern doubt, record realized gold prices (~$4,900/oz), and speculative excitement about the Lone Tree autoclave transformation story. The latest Q2 print (8/10-8/11) was mixed - production up but sales/revenue lagged on toll-milling bottlenecks and a wider net loss - yet the stock actually rallied into and through earnings (1.51→1.70→1.67), suggesting the market is trading the gold-price/recap halo more than the fundamentals. This looks like durable repricing of solvency risk (fair) layered with a momentum/gold-beta overshoot on the multiple itself - not a temporary dislocation that will simply mean-revert on new information, but a valuation now pricing in flawless multi-year execution the filings show is still contingent on permits, contractors and dewatering.
Consensus is bullish and increasingly crowded: sole sell-side analyst rates Buy with a $2.60 target (~57% above spot), insiders have been net buyers (8 buys vs 1 sell, including a $1.4M buy in March), and retail attention/order flow has been elevated and choppy. But short interest has tripled over the past year (3%→11.6% of float, 9.5 days to cover) as sophisticated investors increasingly bet the recap/gold-price story is more than priced in, and 13F holders are mostly flat-to-trimming. The narrative (gold developer transforming into self-sufficient hub-and-spoke producer) is well-known and already reflected in an 11x P/S and a market cap 50% above even the constructive base-case fair value.
The genuine operational inflection (Lone Tree commissioning, owner-operated recovery lifting margins $1,000-1,500/oz, production scaling from 50koz to 150-200koz by 2028) is real but 18-24+ months out and contingent on unresolved permits (NDEP air/water permits), contractor bottlenecks (already pushing Mineral Point and Cove studies into 2027), and dewatering execution. Consensus estimates already show revenue nearly doubling by mid-2027 and EBITDA turning less negative, so much of the improvement is expected, not a surprise. Near-term (next 2 quarters) estimates still show negative EBITDA and EPS, meaning the next few prints are more likely to disappoint a stock priced for a smooth ramp than to deliver an unexpected positive surprise.
- •Q3 2026 · Granite Creek updated resource/feasibility study — Could show lower cutoff/lower grade offsetting more tonnes - swing factor for NAV credibility
- •late Q3 2026 · Cove Underground feasibility study — New capital/dewatering-heavy project; costly surprises could pressure balance sheet
- ▼2026-11 · Q3 2026 earnings — Consensus still shows negative EBITDA/EPS; sales vs production gap likely persists given toll-milling constraints
- ▲Q4 2026 · Archimedes first gold (upper 426 zone) — Tangible production milestone that could support bull narrative if on time
- •Q4 2026 · NDEP Lone Tree Water Pollution Control Permit — Critical-path permit for autoclave refurb; delay would hit 2027 first-gold target
- ▼Q1-mid 2027 · Mineral Point drilling completion / PFS — Already slipped due to contractor/drilling issues - further delay is a real risk
- ▼H2 2026-2027 · Potential additional financing/dilution if capex overruns — 94% TTM share dilution and $150-175M growth capex guide leave room for further equity issuance
Extreme share count growth (94% TTM dilution) via the recapitalization, convertible settlements, and equity issued to fund a still-cash-burning multi-year buildout (owner earnings -100M). No buyback. Insider buying has been modestly supportive (8 buys, ~$1.6M net, small size) but SBC and further equity raises to fund Lone Tree/Archimedes/Cove capex remain a real overhang. Short interest is rising fast (3%→11.6% in a year), adding two-sided flow risk - a squeeze is plausible on any positive print, but the dilution trend is the dominant multi-year story.
No hard floor: despite ~$465M cash, the company is burning through it on capex (owner earnings -100M) and net debt is roughly EV-implied ~$500M when netted against cash, so the balance sheet is a funding runway, not a valuation floor. FCF yield is deeply negative (-10%), so there's no buyback support. Above the price, no obvious hard ceiling either, but continued dilution capacity if the stock stays elevated (management has consistently issued equity/converts through the cycle) caps upside somewhat, and the current 11x P/S already prices a generous chunk of the growth story, effectively acting as a soft ceiling until production actually inflects.
Real buyers exist here - gold bulls, momentum/retail traders riding the metals cycle, and thematic developer-story investors (Sprott, generalist gold funds) - and insider buying plus a sell-side Buy rating give the story some institutional credibility. But this is a serial-dilutor with negative owner earnings, a going-concern history only recently resolved, and a valuation already at a premium to even the constructive base case; the next incremental buyer needs the gold price to stay elevated AND flawless execution on permits/contractors, a high bar. It's buyable as a levered gold-price/story trade, not as a value name.
Greed dominates the tape (179% 1y rally, retail chasing the recap/gold story) but fear is the more rational response at these levels given the valuation gap, ongoing dilution, and negative owner earnings - this feels like a stock priced for the bull scenario while trading in the base/bear reality.
Valuation
Q2 2026 results largely confirm what was already flagged on the prior call (ventilation/ground-control delays at Granite Creek, processing-timing mismatch building inventory) rather than revealing new negative surprises. The incrementally new items are: (1) gold sales fell YoY (5,335oz vs 8,400oz) even as production rose sharply (11,098oz vs 4,178oz), underscoring a toll-milling bottleneck that is worse than the market may have modeled; and (2) net loss widened more than expected to $52.5M largely because pre-development/exploration spend nearly tripled to $29.3M from $9.0M — a deliberate acceleration of technical work (Mineral Point's 131,000m program, Cove/Archimedes studies) rather than a cost overrun, which is arguably a positive read on optionality but a negative read on near-term cash burn.
▸ How the cases moved
Base case largely unchanged (equity value ~$1,160M, probability 0.5) — the ramp trajectory and Lone Tree timeline are unaffected. Bear case probability nudges up slightly (0.28→0.30) given the sales/inventory bottleneck is a tangible near-term execution miss versus guidance optimism on the prior call. Bull case probability trimmed marginally (0.22→0.20) as the widened loss and elevated near-term burn slightly dent confidence in a smooth, low-friction ramp, though the underlying resource/permitting narrative is intact.
Permitting delays (air quality/mercury at Lone Tree), continued ground-control/dewatering setbacks at Granite Creek, and contractor bottlenecks at Mineral Point/Archimedes push first Lone Tree gold into 2029. Cash burn continues faster than planned, forcing another dilutive raise or asset sale (FAD) despite the recent recap. Production stalls near 60-90koz/yr by 2028, owner earnings remain near breakeven/negative, and the market discounts the NAV story heavily given the dilution history.
▸ Valuation
1.5x $300M revenue = $450M EV, plus residual net cash ~$150M after burn = $600M equity, less dilution/financing drag → $600M equity value
Granite Creek and Archimedes ramp roughly on the guided (if slightly delayed) timeline; Lone Tree permits clear with modest slippage and first gold lands late 2027/early 2028, only partially contributing by mid-2028. Production reaches ~100-130koz by 2028 with gold prices moderating from current highs but still elevated (~$3,300-3,600/oz). Owner earnings turn modestly positive as toll-milling costs are partly replaced by owner-operated recovery gains. Market applies a mid-cycle growth-producer multiple reflecting remaining execution risk.
▸ Valuation
7x $180M EBITDA = $1,260M EV, less ~$100M net debt (cash spent on remaining Lone Tree capex) = $1,160M equity
Lone Tree commissions on schedule (late 2027), permitting clears without material delay, Archimedes and Mineral Point studies confirm large, high-grade resources, and gold prices stay near current elevated levels. Owner-operated recovery lifts margins ~$1,000-1,500/oz, production scales toward the 150-200koz 2028 target, and the market begins re-rating toward the long-term >600koz vision, paying up for the NAV optionality.
▸ Valuation
8x $420M EBITDA = $3,360M EV, less ~$160M net debt = $3,200M equity
▸ Target Rationale
I trim slightly below the model figure to reflect governance/dilution overhang (shares up ~2.1x in a year, further dilution plausible if any project slips), customer concentration risk (96% of receivables from one buyer), and the outstanding critical-path environmental permits at Lone Tree that the filings flag as a real (sev 7) unresolved risk not fully captured in a clean scenario multiple. The recap materially de-risked near-term solvency, which is why the target isn't cut further, but the base case's positive owner earnings by 2028 depend on several things (permits, contractor availability, dewatering) still not in hand.
Business Quality & Sentiment
Recent Research & News
Recent Research & News
2026-06-21Company news
- Recapitalization and Debt Restructuring (Q1 2026): In March 2026, i-80 Gold successfully closed a massive $500 million financing package. This package is comprised of a $250 million Net Smelter Return (NSR) royalty with Franco-Nevada and an up-to-$250 million gold prepayment facility backed by National Bank of Canada and Macquarie Bank (with an initial $150 million advanced at closing). The company utilized approximately $165 million of these proceeds to fully retire high-cost legacy liabilities, including the redemption of its 8% 2027 convertible debentures and the settlement of Orion Mine Finance's convertible loan and gold prepayment agreements.
- Strong Liquidity Position (May 2026): As of March 31, 2026, the company reported a robust cash balance of approximately $514 million, which significantly alleviates the historical financing risks associated with executing its Nevada development plans.
- Q1 2026 Operating Performance & Infrastructure Incident: In May 2026, the company reported its Q1 2026 financial results. Granite Creek Underground generated approximately $43.8 million in quarterly revenue. However, underground operations were temporarily disrupted by a main surface electrical substation transformer fire in January 2026. While temporary diesel generators mitigated immediate operational impacts, permanent replacement electrical infrastructure was successfully installed and commissioned in mid-March 2026. Additionally, the company reported encountering higher-than-expected levels of oxide material relative to its original PEA projections at Granite Creek.
- Exploration Drilling Success (April 2026): i-80 Gold announced high-grade assay results from its drilling campaign at the Archimedes Underground project, featuring notable intercepts such as 24.6 g/t Au over 23.6 meters. Construction at Archimedes is progressing on schedule, with initial production set to feed toll-milling operations before transitioning to the refurbished Lone Tree facility.
▸ Thesis-test Findings
i-80 Gold Lone Tree autoclave air quality permit Nevada
The permitting path for the Lone Tree autoclave refurbishment sits on the critical path to achieving the company’s late-2027 first gold pour target. Following the completion of the plant’s engineering designs in late 2025, i-80 Gold projected submitting its formal environmental permit applications (covering air quality, water pollution, mercury abatement, and reclamation management) to the Nevada Division of Environmental Protection (NDEP) in Q1 2026. Refurbishment and operating permit approvals are sequenced to occur between Q2 2026 and Q2 2027, with the NDEP Water Pollution Control Permit specifically targeted for Q4 2026. Successfully securing these air and environmental permits is a vital milestone for the bull case; commissioning the autoclave will transition the company from 55% to 60% gold payability at third-party toll processors to an owner-operated average gold recovery of roughly 92% across all three feeding underground mines.
Granite Creek gold mine water dewatering infrastructure 2026
Dewatering remains a central technical and capital challenge for mining the deeper, higher-grade zones at the Granite Creek underground operation. The company successfully completed the installation of permanent dewatering infrastructure during Q3 2025 to manage water inflows at depth. Throughout Q1 2026, capital expenditures at Granite Creek continued to prioritize water management, specifically funding ongoing operations at the water treatment plant, Rapid Infiltration Basin (RIB) construction, and auxiliary electrical systems needed to power the pumps. Effective water management is essential for the bull case of moving Granite Creek from its current ramp-up phase into steady-state production. Notably, the company is also closely studying Cove's dewatering requirements (where dewatering accounts for 60% of Cove's $157 million capital budget) to identify potential capital cost-reduction synergies across its wider active portfolio.
Franco-Nevada i-80 Gold financing agreement filing terms
According to the official Net Smelter Return (NSR) Royalty Agreement filed on March 16, 2026, Franco-Nevada acquired a life-of-mine royalty on i-80 Gold’s core portfolio—consisting of the Ruby Hill, Granite Creek, Cove, and Lone Tree properties (with the FAD project added after three years if retained). The contract terms dictate an initial royalty rate of 1.5% NSR, which will step up to a permanent 3.0% NSR starting January 1, 2031, aligning with the company's expected ramp-up to peak production. Out of the $250 million total agreement, $225 million was advanced at closing, with the final $25 million milestone payment contingent on i-80 Gold spending $25 million of budgeted capital in 2026 to advance permitting and technical work at the Mineral Point project. While the arrangement represents a massive non-dilutive capital injection that cleared immediate debt maturity pressures, the permanent 3.0% post-2031 NSR rate introduces a structural margin drag that represents a long-term risk for the bear case to monitor.