Vistra Corp.v3 5.8/10 · 2026-10-16Vistra Corp., along with its various holdings, functions as a unified entity primarily engaged in retail electricity supply and power generation. The company organizes its operations across six distinct segments: Retail, Texas, East, West, Sunset, and Asset Closure. It directly provides electricity and natural gas to residential, commercial, and industrial clients throughout 20 U.S. states and the District of Columbia. Beyond its retail endeavors, Vistra also participates in generating electricity, facilitating wholesale energy transactions, managing commodity-related risks, producing fuel, and overseeing fuel logistics. With approximately 4.3 million customers, Vistra commands an impressive generation capacity of about 38,700 megawatts. This capacity is sustained by a diverse portfolio of facilities, including those powered by natural gas, nuclear energy, coal, solar, and advanced battery energy storage systems. The enterprise, initially known as Vistra Energy Corp., adopted its current name, Vistra Corp., in July 2020. Tracing its origins back to 1882, Vistra Corp. maintains its corporate headquarters in Irving, Texas.
2-Year Price History
Valuation v3 Opus worker · 2026-10-16
Vistra is the largest US competitive power generator plus Texas' biggest retailer (TXU): ~41 GW of gas, nuclear and coal, 5.5 GW more coming with Cogentrix, nuclear PPAs signed with Amazon (1.2 GW Comanche Peak) and Meta (2.6 GW PJM), and a 30% share-count reduction since 2021. The business is printing records (Q2 adj. EBITDA +31% to $1.77B; 2026 guide $6.8-7.6B EBITDA / $3.9-4.7B FCF-before-growth, tracking at/above midpoint), but the stock (~$154 on Oct 15, the latest close I could confirm; ~30% below its $220 high) has de-rated because ERCOT wholesale prices have collapsed to ~$30/MWh as batteries flatten the evening scarcity hours, the Texas data-center queue is under audit, and the 2027 $7.4-7.8B EBITDA range now trends to the low end before ~$0.7B of Cogentrix + Meta adds. At ~10x EV/EBITDA and ~8% FCF-before-growth yield to common (after ~$190M preferred dividends), my base DCF (10% rate) is ~$171, a ~10-11% base IRR: decent, under the 14% hurdle, with a wide merchant-price range. Rating 5.8: a quality, well-hedged, shareholder-friendly franchise at a fair-to-modestly-cheap price, not a mispricing. Research rating 6.0: the bull case (management's $22-25 FCF/share by 2030, Street targets ~$210-218) needs ERCOT tightening and premium data-center contracts. Both are uncertain, but the Nov 6 Q3 call and its 2027 guide update will show a lot of it.
A deep dive would have to establish: Whether ERCOT forward prices recover once battery build-out slows and data-center load arrives in 2027-28, and at what premium Vistra can contract existing gas and nuclear to hyperscalers, which together decide if 2029-30 FCF/share reaches management's $22-25 or stalls near $15.
Research (expand)
What the company does
Vistra (NYSE: VST, Irving TX) is an integrated power company. Generation: ~41 GW after the Lotus deal (Oct 2025, 2.6 GW gas), made up of ~6.4 GW of nuclear (Comanche Peak in ERCOT, plus Beaver Valley, Perry and Davis-Besse in PJM from Energy Harbor), a large CCGT/peaker gas fleet across ERCOT, PJM, ISO-NE, NYISO and CAISO, residual coal (Martin Lake etc., in the Sunset segment), plus solar and batteries. Retail: ~4.3-5M customers through TXU Energy and other brands, about $2.4B of steady EBITDA a year. That retail book is a natural hedge for Texas generation. Pending: Cogentrix (10 modern gas plants, ~5.5 GW in PJM, ISO-NE and ERCOT) for ~$2.3B cash + ~$1.5B assumed debt + 5M shares at $185. FERC approved it in Aug 2026 and it should close late 2026 (~$730/kW net of tax benefits).
The investment case
1. Load growth meets scarce dispatchable supply. ERCOT and PJM both set record peaks in July 2026 (91 GW / 168 GW). Management sees 4-6%/yr ERCOT and 2-3%/yr PJM load growth through 2030, of which data centers are only ~2 points in ERCOT. New-build costs about $90/MWh against ~$30/MWh ERCOT forwards, so the existing fleet's replacement value sits far above its trading value.
2. Contracted, lower-volatility earnings. 20-yr PPAs with AWS (1.2 GW from Comanche Peak, starting Q4'27 and ramping to 2032) and Meta (2.6 GW of PJM nuclear + 433 MW of uprates, with partial delivery from late 2026 and full by YE27). Management targets ~half of EBITDA from low-volatility sources. The DOE has conditionally committed up to $4.2B in loans for the PJM nuclear uprates and life extensions (Oct 2026), which lowers the capital burden.
3. Downside floors. The 45U nuclear PTC (through 2032) sets a floor under nuclear revenue. PJM capacity cleared at the cap again: $325/MW-day for 2028/29, against an uncapped ~$555. Hedges cover ~100% of 2026, ~94% of 2027 and ~72% of 2028 volumes.
4. Capital return. The share count is down ~30% since Nov 2021 (171M shares retired at ~$38 average), with ~336M shares out as of Aug 3, 2026. About $3B goes to shareholders over 2026-27, $1.2B of authorization remains, and the board is willing to extend it. Investment-grade ratings came from S&P (BBB-) and Fitch. The CEO bought ~$1.2M of stock at ~$135 in August.
5. Optionality. Helix Digital Infrastructure (with KKR, NVIDIA and KIA) gives Vistra a preferred-power-partner channel, with up to $1B committed (above $0.5B only on milestones). There are also Permian peakers (860 MW), co-location in PJM after FERC's June order, and Batch Zero projects in ERCOT.
What it earns today and at maturity
- 2026: Ongoing Ops adj. EBITDA ~$7.3B (guide midpoint $7.2B, H1 $3.26B). Adj. FCF before growth ~$4.4B, or ~$4.2B after preferred dividends (~$12.5/share). GAAP earnings are noisy because of hedge marks (Q2 GAAP NI $305M after a $472M unrealized loss; H1 NI $1.33B).
- 2027: midpoint-opportunity range $7.4-7.8B, now trending to the low end because ERCOT forwards fell, plus ~$0.7B from Cogentrix and the Meta premium, giving ~$8.1B pro forma. Management's pre-ERCOT-slump "≈$16 FCFbG/share" 2027 framework is probably ~$15 now.
- Maturity (2029-30): management says $22-25 FCFbG/share if all cash goes to buybacks. In dollars I see ~$6.0B FCF before growth (range $4.5-7.5B), which needs AWS/Meta full delivery, uprates and some ERCOT recovery. Watch-outs: cash taxes rise as tax attributes are used up, and hedges roll off at lower ERCOT prices.
Fair value and multiples
- Price $154.17 (Oct 15 close, confirmed against Oct 8 close $156.14 and the ~$153-156 trading range). Shares ~335.6M (10-Q cover, Aug 3), or ~340M after the Cogentrix stock. Market cap ~$51.7B.
- Net debt at 6/30/26: long-term debt $19.6B + AR financing $0.3B + forward repurchase obligation $0.6B − cash $0.4B ≈ $20.1B. Add the $1.5B junior subordinated notes issued Sept 2026 (partly prefunding Cogentrix), $2.5B of preferred stock (8.0%/7.0%/8.875%), and Cogentrix's ~$3.8B at close. I carry ~$24B of debt-like claims (range $21.5-27B), so EV ≈ $75.7B.
- EV/EBITDA ~10.3x 2026 and ~9.6x 2027 pro forma. P/FCFbG ~12x, an ~8% FCF-before-growth yield to common. P/E is ~15x Street 2027 EPS (~$10.35, cut from $11.30). Peers: CEG trades richer on its pure nuclear and contract mix, NRG and TLN in a similar ballpark.
- DCF (10%, equity cash flows after interest, preferred dividends and ~$0.6-1.0B/yr of growth capex): FCF of $3.8B, $4.1B, $4.5B, $4.9B and $5.2B over 2027-31, with 2% terminal growth. PV of the explicit years is ~$16.8B and PV of the terminal value ~$41.2B, so equity ≈ $58B ÷ ~339M shares ≈ $171/share. The base-case IRR from $154 is ~10.5-11%. The range is wide ($105-245) because the terminal value depends on long-run ERCOT and PJM pricing.
- Fair value ~$175 ($120-240). Street targets are ~$210-218 mean and $248 median, with 16 of 21 analysts at Buy.
Risks and competition
- ERCOT price structure: batteries (31 GWh) now cover the evening ramp, so scarcity hours are vanishing (on Jul 22 the market cleared at $57 against a prior $400-500 pattern). Forwards near $30/MWh mean open 2028+ Texas gas output earns much less than the 2024-25 bull case assumed. Some offset: battery returns have fallen, which should slow new builds.
- Policy: the Texas data-center queue audit and SB6 large-load rules may slow contracts. PJM rules are in flux (the capacity collar ends after 2028/29, the Reliability Backstop Procurement, the IRAS proposal with bring-your-own-capacity, co-location tariff compliance). An affordability backlash could cap capacity prices.
- Leverage: ~3x net debt (incl. preferred) to EBITDA after Cogentrix, layered with junior subordinated notes and preferred. Fine at investment grade, but it amplifies merchant swings.
- Operating: nuclear outages, Moss Landing battery-fire liabilities, coal closure costs and Asset Closure AROs. Uri litigation largely cleared in March 2026, and the EPA's proposed CCRMU rescission is a tailwind.
- Competition: Constellation-Calpine (the biggest nuclear and gas fleet), NRG (retail + gas), Talen, and new-build gas, solar and batteries from developers and utilities. Hyperscalers can also self-build or contract with regulated utilities.
How investors feel (5.5/10)
Analysts remain near-unanimous Buys with targets ~40% above the price, but the tape is cooler than that. The stock is down ~15-25% YTD and ~30% from its $220 peak on ERCOT softness. It swings ±6-10% a day on DOE and PJM headlines (+20% from Sep 30 to Oct 7 on the DOE loan, −6% Oct 8). Options price ~51% implied volatility. Short interest is low (~10.5M shares, ~3% of float, 2 days to cover). The CEO buying in August and continued buybacks are supportive. Sentiment has gone from loved AI-power momentum to skeptical-but-owned. The Nov 6 Q3 call, with its 2026/2027 guidance update and possibly Cogentrix closing, is the next decision point.
- Vistra 10-Q for quarter ended 2026-06-30 (filed 2026-08-10): balance sheet, debt, 335,635,195 shares as of Aug 3, Cogentrix terms
- Vistra 8-K 2026-08-07 Ex.99.1 Q2 2026 earnings release (guidance, hedge %, buybacks)
- Vistra 8-K 2026-09-24 ($1.5B 7.000%/7.250% junior subordinated notes due 2057)
- Vistra 8-K 2026-10-02 (commodity-linked facility extended to Sep 2027)
- Vistra Q4 2025 and Q2 2026 earnings call transcripts
- https://www.tikr.com/blog/vistra-stock-fell-6-in-a-day-after-a-20-run-heres-what-its-november-6-report-needs-to-show
- https://www.tikr.com/blog/vistra-stock-is-down-27-this-year-but-analysts-havent-budged-their-targets
- https://www.tikr.com/blog/vistra-stock-fell-6-in-three-months-its-ceo-just-bought-the-dip-heres-what-hes-betting-on
- https://www.barchart.com/story/news/3999453/vistra-corp-stock-is-wall-street-bullish-or-bearish
- https://www.marketbeat.com/instant-alerts/price-vistra-nyse-vst-shares-climb-107-heres-why-2026-10-06/
- https://world-nuclear-news.org/articles/doe-offers-vistra-loan-for-reactor-upgrades-and-uprates
- https://www.utilitydive.com/news/doe-intends-to-loan-vistra-42b-for-nuclear-fleet-improvements/832236/
- https://www.opis.com/resources/energy-market-news-from-opis/pjms-2028-2029-capacity-auction-clears-at-price-cap-for-third-time/
- https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2026-releases/20260714-pjm-capacity-auction-procures-138318-mw-of-generation-resources.pdf
Financials — Adjusted
Adjusted · TTM 2026-Q3 · USD
| TTM & Fiscal-Year P&L | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| Revenue | 17356-20% | 16730-14% | 19377+25% | 15542-13% | 17837 |
| Gross profit | 3721-55% | 2659-65% | 7693+49% | 5169+65% | 3131 |
| Operating expenses | 2683+63% | 1683+15% | 1465+16% | 1260+4% | 1207 |
| ▸Adj EBITDA | 4016-58% | 3992-55% | 8860+53% | 5775+46% | 3957 |
| ▸Adj OCF | 6879+32% | 5254+8% | 4879+29% | 3787+26% | 2999 |
| CapEx | -4034 | -3430 | -2209 | -1676 | -1301 |
| Adj FCF | 2845+0% | 1824-32% | 2670+26% | 2111+24% | 1698 |
| ▸Interest expense | 1116 | 1131 | 1090 | 749 | 854 |
| ▸Adj net income | -807-115% | -324-107% | 4395+60% | 2739+93% | 1420 |
| ▸Owner's earnings | 2300 | -- | -- | -- | -- |
claimed profit vs where the cash actually went — % = share of claimed EBITDA; Total = FY2022→FY2025 +2026YTD
| Where the Cash Went | Total | 2026YTD | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|---|
| ▸Claimed: EBITDA | 24065100% | 6047100% | 4888100% | 7189100% | 4615100% | 1326100% |
| FCF (OCF−capex) | 776532% | 181030% | 64013% | 235433% | 377782% | -816-62% |
| Net income | 634226% | 247441% | 94419% | 265937% | 149332% | -1228-93% |
| ▸Capital returned | 569624% | 144224% | 143729% | 113116% | 99822% | 68852% |
| Buybacks | 5377 | 917 | 0.00 | 1266 | 1245 | 1949 |
| Dividends | 1608 | 231 | 306 | 305 | 388 | 378 |
| Interest paid | 4669 | 845 | 1131 | 1090 | 749 | 854 |
| Debt paid down | -5958 | -551 | 0.00 | -1530 | -1384 | -2493 |
| ▸Reinvestment | 1423359% | 252042% | 342470% | 530874% | 166836% | 131399% |
| Capex (PP&E) | 11136 | 2520 | 3430 | 2209 | 1676 | 1301 |
| Intangibles & M&A | 3065 | 0.00 | 0.00 | 3065 | 0.00 | 0.00 |
| Leases signed (net Δ) | 32.0 | -- | -6.00 | 34.0 | -8.00 | 12.0 |
| Retained / other | 367315% | 121320% | 3347% | -752-10% | 352876% | -650-49% |
negative buybacks = net dilution (capital raised); negative debt paid down = debt GREW.
Leases signed (net Δ) = non-cash growth in lease obligations — reinvestment committed with no cash out; '--' = no opening balance on file.
Retained / other = operating cash kept on the balance sheet, net of other investing/financing (security trades, FX).
SBC over the Total window: 200 — a real cost the cash-flow statement adds back; its dilution lands in Buybacks.
| Balance Sheet | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| ▸Assets (total) | 45029 | 41550 | 37770 | 32966 | 32787 |
| ▸Liabilities (total) | 38566 | 36440 | 32187 | 27644 | 27869 |
| Net debt (incl. leases) | 18403 | 19579 | 16176 | 11199 | 12881 |
| Net debt / Adj EBITDA | 4.58 | 4.90 | 1.83 | 1.94 | 3.26 |
| Net debt / Adj FCF | 6.47 | 10.7 | 6.06 | 5.31 | 7.59 |
| Adj EBITDA / interest | 3.60 | 3.53 | 8.13 | 7.71 | 4.63 |
| Shares outstanding | 336 | 338 | 340 | 351 | 390 |
| Dilution (YoY) | -0.9% | -0.5% | -3.3% | -9.8% | -16.9% |
| Employees | 6850 | 6390 | 6850 | 4870 | 4910 |
| Margins | TTM | 2025 | 2024 | 2023 | 2022 |
|---|---|---|---|---|---|
| Gross margin | 21.4%-16.2 | 15.9%-23.8 | 39.7%+6.4 | 33.3%+15.7 | 17.6% |
| Adj EBITDA margin | 23.1%-20.8 | 23.9%-21.9 | 45.7%+8.6 | 37.2%+15.0 | 22.2% |
| Adj OCF margin | 39.6%+15.7 | 31.4%+6.2 | 25.2%+0.8 | 24.4%+7.6 | 16.8% |
| Adj FCF margin | 16.4%+3.3 | 10.9%-2.9 | 13.8%+0.2 | 13.6%+4.1 | 9.5% |
| Net income margin | 15.6%+10.3 | 5.6%-8.1 | 13.7%+4.1 | 9.6%+16.5 | -6.9% |
| Adj NI margin | -4.7%-28.6 | -1.9%-24.6 | 22.7%+5.1 | 17.6%+9.7 | 8.0% |
| ROIC (adj, after-tax) | 3.0% | 3.2% | 21.8% | 14.6% | 8.3% |
| Cost of debt | 5.5% | 6.1% | 6.5% | 5.6% | 6.6% |
Revenue Breakdown
Revenue Segments
| Retail Segment | $1.9B | -5% |
| Texas Segment | $1.4B | +57% |
| East Segment | $1.3B | +21% |
| Revenue From Other Wholesale Contracts | $472.0M | +35% |
| East Segment | $2.3B | +64% |
| West Segment | $89.0M | -43% |
Earnings Calls
Earnings Call · 2026 Q2
Vistra delivered a notably strong second quarter, reporting Adjusted EBITDA of $1.767 billion, more than 30% above the second quarter of 2025. Results benefited from contributions across both generation and retail, highlighting the value of the company’s integrated business model and comprehensive hedging program. Generation EBITDA increased to approximately $994 million from $593 million, driven by favorable hedging, roughly 5% higher average realized prices per MWh, higher PJM capacity revenues, optimized dispatch of flexible gas assets, the Martin Lake Unit 1 restart and contributions from assets acquired from Lotus. Retail EBITDA also improved modestly to approximately $773 million from $756 million. Vistra completed three nuclear refueling outages and 92 gas and coal planned outages ahead of summer, helping the fleet achieve more than 97% commercial availability during recent heat waves. Management reaffirmed 2026 guidance of $6.8 billion–$7.6 billion of Adjusted EBITDA and $3.925 billion–$4.725 billion of adjusted free cash flow before growth. Given first-half performance, management expects to finish at or above the midpoint of both ranges. For 2027, Vistra maintained its $7.4 billion–$7.8 billion EBITDA midpoint opportunity range despite materially lower ERCOT forward curves than those underlying the original framework. Higher PJM prices, hedging and nuclear production tax credit protection partly offset ERCOT weakness, although the current outlook trends toward the lower end of the range. Cogentrix and the premium component of the Meta nuclear PPAs remain excluded; together, they could add approximately $700 million to the 2027 midpoint, subject to transaction closing and other market developments. The company continues to see structural power-demand growth. ERCOT and PJM both reached record summer peak loads in July, and Vistra continues to view annual growth estimates of 4%–6% in ERCOT and 2%–3% in PJM through 2030 as reasonable. While data centers are an important longer-term driver, management emphasized industrial reshoring, electrification, population growth and broader economic expansion. ERCOT’s recent price softness reflects additional supply, battery additions and weather-driven variability rather than a deterioration in long-term fundamentals. Management said battery returns have fallen sharply, which should moderate future battery additions, while expected load growth should eventually tighten the market. Texas data-center audits may pause certain queue reviews for several months, but Vistra does not currently expect meaningful delays to Comanche Peak’s late-2027 target or other projects scheduled for next year. The company supports reducing inflated queues to distinguish viable projects from speculative requests. In PJM, Vistra supports bilateral contracting and incentive-based customer flexibility rather than mandatory bring-your-own-new-capacity requirements. Management also expects FERC’s co-location order to provide greater clarity after PJM and transmission owners submit compliance filings. Vistra announced Helix Digital Infrastructure with KKR, NVIDIA and the Kuwait Investment Authority as a new channel for integrated data-center power and infrastructure solutions. Vistra will commit up to $1 billion, with amounts above $500 million dependent on milestones, and act as preferred power partner while retaining the option to provide existing assets, new build or co-location solutions. Capital allocation remains disciplined: approximately $3 billion is targeted for shareholder returns in 2026–2027, $4.5 billion–$5 billion for growth, and $2 billion–$2.5 billion remains available for further buybacks, growth or debt reduction. Vistra has $1.2 billion of current repurchase authorization and may seek additional authorization if market conditions make buybacks attractive, while continuing toward mid-investment-grade credit ratings.
▸Asked whether Texas data-center audits, potential delays and the Batch Zero process were creating commercial or counterparty concerns, and whether near-term outlook pressure required additional hedging for 2027–2028.Constantine · Wells Fargo
▸Asked whether long-term contracts should be priced primarily against new-build costs, roughly $90/MWh, or whether clean-energy premiums and speed-to-market could support higher pricing and margins.Constantine · Wells Fargo
▸Asked whether Vistra’s preferred structure for data-center deals remains a hybrid of new and existing capacity.Constantine · Wells Fargo
▸Asked how PJM and ERCOT compare in terms of market tightness, customer discussions and Vistra’s efforts to secure contracts in each market.Jeremy Tonet · J.P. Morgan
▸Asked about Vistra’s strategy and level of interest as PJM approaches the Reliability Backstop Procurement, including how the RBP compares with bilateral contracting.Jeremy Tonet · J.P. Morgan
▸Asked how Vistra views the proposed Integrated Resource Adequacy Structure and how the company expects the process to evolve.Jeremy Tonet · J.P. Morgan
▸Asked how the Helix platform will develop over time, what milestones would trigger additional investment, and how it will interact with Vistra’s existing data-center commercial discussions.Michael Sullivan · Wolfe Research
▸Asked what is driving confidence around the 2026 midpoint or better and whether 2027 developments imply an upward, downward or neutral bias within the midpoint opportunity range.Michael Sullivan · Wolfe Research
▸Asked whether additional Helix partners are expected and how the platform might raise capital and evolve, including whether it could eventually become a public company.James West · Melius Research
▸Asked whether Governor Abbott’s actions establish a timeline for completing the audit process and clearing or reducing the Texas data-center queue.James West · Melius Research
▸Asked how willing Vistra is to increase share repurchases from the $2–$2.5 billion of remaining cash and whether management might seek additional Board authorization beyond the current $1.2 billion.Carly Davenport · Goldman Sachs
▸Asked for more detail on updated hedging activity, particularly 2028 exposure and changes in ERCOT versus eastern markets during the quarter.Carly Davenport · Goldman Sachs
▸Asked for additional detail on Helix’s project pipeline, including potential megawatts, timing, development progress and return targets relative to Vistra’s internal hurdle rates.David Arcaro · Morgan Stanley
▸Asked whether Vistra has projects beyond Comanche Peak being developed with partners that may be included in the Texas Batch Zero process.David Arcaro · Morgan Stanley
▸Asked about the expected timeline and remaining uncertainty for PJM’s co-location process, particularly in light of the proposed IRAS framework.Rinny Singh · Bank of America
▸Asked whether customers are favoring energy-and-capacity contracts or energy-only arrangements, considering potential bring-your-own-capacity charges and customer flexibility.Rinny Singh · Bank of America
SEC Filing Findings
SEC Filing — material findings
2026-08-10 · depth 9/10risk 6Hidden Liability▸Moss Landing battery fire remediation: EPA ASAOC cost estimate raised to ~$175M (incl. $65M Q2 2026 increase); $85M still unpaid and recorded as current liability; additional litigation, contract settlements and impairments not quantified; Moss Landing 350 MW restart timing uncertain.
Moss Landing battery fire remediation: EPA ASAOC cost estimate raised to ~$175M (incl. $65M Q2 2026 increase); $85M still unpaid and recorded as current liability; additional litigation, contract settlements and impairments not quantified; Moss Landing 350 MW restart timing uncertain.
Options
Chain Snapshot (daily)
| Strike | Call Bid/Ask | Call OI | Put Bid/Ask | Put OI |
|---|---|---|---|---|
| $120.00 | $9.30/$9.80 | 268 | $7.85/$8.95 | 1,846 |
| $125.00 | $7.00/$7.55 | 101 | $10.50/$11.65 | 4,855 |
| $130.00 | $5.25/$5.65 | 198 | $13.35/$14.80 | 5,306 |
| $135.00 | $3.85/$4.35 | 858 | $17.55/$18.65 | 10,565 |
| $140.00 | $2.85/$3.15 | 1,251 | $21.50/$22.55 | 3,246 |
| $145.00 | $1.99/$2.30 | 1,425 | $25.70/$26.80 | 738 |
| $150.00 | $1.43/$1.78 | 2,554 | $30.10/$31.25 | 1,664 |
| $155.00 | $0.95/$1.17 | 1,605 | $34.80/$36.80 | 1,739 |
Short Interest
Web Traffic
Executive Compensation (2023.0-2025.0)
Institutional Ownership
| Fund | $ value | Cost basis | Δ QoQ | Δ YoY | α life | Fund AUM |
|---|---|---|---|---|---|---|
| BlackRock, Inc.Passive | $4.61B | $122.70 | +$92.7M | +$102M | — | $6.70T |
| VANGUARD CAPITAL MANAGEMENT LLCPassive | $3.39B | $150.33 | −$16K | +$3.39B | — | $4.68T |
| VANGUARD PORTFOLIO MANAGEMENT LLCPassive | $2.69B | $150.35 | +$5.9M | +$2.69B | — | $2.22T |
| STATE STREET CORPPassive | $2.67B | $73.33 | +$12.7M | +$30.2M | — | $3.38T |
| FMR LLC | $2.25B | $64.63 | −$261M | −$785M | — | $2.30T |
| GEODE CAPITAL MANAGEMENT, LLCPassive | $1.43B | $83.65 | +$591K | −$5.7M | — | $1.87T |
| MORGAN STANLEY | $1.41B | $86.40 | +$99.0M | +$134M | — | $1.88T |
| NORGES BANK | $922M | $116.08 | +$188M | +$161M | — | $1.00T |
| UBS Group AG | $856M | $113.53 | +$127M | +$375M | — | $627.66B |
| GOLDMAN SACHS GROUP INC | $752M | $128.28 | +$223M | +$401M | — | $953.46B |
Ownership Over Time
5-year share-count history (top 10 holders by peak, incl. exited) + price
Related Stocks
Investors who own this also own
Stocks held by the same active managers as this one, ranked by score — how much more often these appear together than random chance (1× = baseline). Excludes index ETFs and market makers; minimum 3 shared holders.
| Ticker | Name | Co-holders | Score |
|---|---|---|---|
| AAL | American Airlines Group Inc. | 3 | 38.24× |
| TLN | Talen Energy Corporation | 11 | 28.05× |
| NRG | NRG Energy, Inc. | 6 | 25.50× |
| NI | NiSource Inc | 3 | 21.85× |
| KGS | Kodiak Gas Services, Inc. | 3 | 21.85× |
| DTM | DT Midstream, Inc. | 3 | 19.12× |
| CEG | Constellation Energy Corporation | 7 | 18.30× |
| GDS | GDS Holdings Limited | 3 | 18.00× |
| UAL | United Airlines Holdings, Inc. | 5 | 17.00× |
| NCLH | Norwegian Cruise Line Holdings Ltd. | 3 | 17.00× |
| CIFR | Cipher Mining Inc. | 3 | 16.10× |
| MGM | MGM Resorts International | 3 | 16.10× |
Analyst Coverage
| Quarter | Revenue | EBITDA | Net Inc | EPS | EPS Range | # Analysts |
|---|---|---|---|---|---|---|
| 2017 Q1 | 1.3B | 373M | 72M | $0.07 | $0.06 – $0.09 | 17 |
| 2017 Q2 | 1.5B | 198M | -67M | $0.18 | $0.14 – $0.22 | 13 |
| 2017 Q3 | 1.6B | 544M | 239M | $0.34 | $0.27 – $0.41 | 11 |
| 2017 Q4 | 1.2B | -388M | -684M | $0.26 | $0.21 – $0.31 | 14 |
| 2018 Q1 | 140M | -1.8B | -2.1B | $0.87 | $0.70 – $1.05 | 13 |
| 2018 Q2 | 3.5B | 785M | 136M | $0.34 | $0.27 – $0.41 | 7 |
| 2018 Q3 | 4.7B | 1.2B | 432M | $1.14 | $0.91 – $1.37 | 16 |
| 2018 Q4 | 3.5B | 40M | -459M | $1.23 | $0.99 – $1.48 | 7 |
| 2019 Q1 | 2.6B | 803M | 208M | $0.24 | $0.18 – $0.29 | 3 |
| 2019 Q2 | 2.5B | 793M | 246M | $0.26 | $0.20 – $0.31 | 5 |
| 2019 Q3 | 3.4B | 794M | 177M | $0.87 | $0.66 – $1.02 | 4 |
| 2019 Q4 | 3.5B | 978M | 256M | $0.54 | $0.41 – $0.64 | 4 |
| 2020 Q1 | 2.8B | 718M | 86M | $0.35 | $0.26 – $0.41 | 3 |
| 2020 Q2 | 2.8B | 888M | 194M | $0.44 | $0.33 – $0.52 | 2 |
| 2020 Q3 | 3.9B | 1.1B | 362M | $0.76 | $0.58 – $0.90 | 2 |
| 2020 Q4 | 3.4B | 559M | -76M | $0.76 | $0.58 – $0.90 | 2 |
| 2021 Q1 | 1.9B | -609M | -1.2B | $-2.83 | $-3.34 – $-2.15 | 2 |
| 2021 Q2 | 3.3B | 656M | 52M | $0.55 | $0.42 – $0.65 | 1 |
| 2021 Q3 | 5.0B | 712M | 13M | $1.32 | $1.28 – $1.35 | 1 |
| 2021 Q4 | 6.0B | 623M | -84M | $2.50 | $1.89 – $2.94 | 1 |
| 2022 Q1 | 3.8B | -889M | -1.6B | $0.19 | $0.14 – $0.22 | 1 |
| 2022 Q2 | 4.0B | 739M | 57M | $0.24 | $0.18 – $0.29 | 1 |
| 2022 Q3 | 6.6B | 677M | 14M | $1.61 | $1.22 – $1.90 | 1 |
| 2022 Q4 | 6.4B | 795M | -92M | $1.32 | $1.00 – $1.55 | 1 |
| 2023 Q1 | 1.9B | -1.3B | -2.0B | $0.06 | $0.05 – $0.07 | 1 |
| 2023 Q2 | 2.8B | 709M | 63M | $0.88 | $0.66 – $1.03 | 1 |
| 2023 Q3 | 5.1B | 705M | 15M | $1.59 | $1.20 – $1.87 | 1 |
| 2023 Q4 | 3.5B | 558M | -101M | $-0.04 | $-0.05 – $-0.03 | 2 |
| 2024 Q1 | 2.9B | -1.7B | -2.5B | $0.62 | $0.27 – $0.97 | 3 |
| 2024 Q2 | 4.0B | 1.5B | 469M | $1.38 | $1.05 – $1.63 | 1 |
| 2024 Q3 | 5.0B | 1.5B | 394M | $1.16 | $0.83 – $1.35 | 4 |
| 2024 Q4 | 3.9B | 1.9B | 752M | $2.22 | $2.05 – $2.32 | 3 |
| 2025 Q1 | 4.5B | 1.3B | 181M | $0.54 | $0.51 – $0.56 | 3 |
| 2025 Q2 | 4.7B | 1.4B | 296M | $0.88 | $0.43 – $1.07 | 6 |
| 2025 Q3 | 6.1B | 1.9B | 701M | $2.08 | $1.90 – $2.42 | 5 |
| 2025 Q4 | 5.8B | 2.0B | 779M | $2.31 | $0.98 – $5.18 | 6 |
| 2026 Q1 | 5.2B | 1.6B | 447M | $1.32 | $0.64 – $3.44 | 6 |
| 2026 Q2 | 5.5B | 1.7B | 545M | $1.61 | $1.12 – $1.82 | 6 |
| 2026 Q3 | 6.0B | 2.5B | 1.0B | $2.98 | $2.77 – $3.10 | 4 |
| 2026 Q4 | 6.0B | 2.1B | 667M | $1.97 | $1.37 – $2.29 | 4 |
| 2027 Q1 | 5.4B | 2.0B | 593M | $1.76 | $0.90 – $2.61 | 2 |
| 2027 Q2 | 5.4B | 2.3B | 841M | $2.49 | $2.12 – $2.84 | 1 |
| 2027 Q3 | 6.6B | 2.6B | 1.1B | $3.18 | $2.71 – $3.63 | 1 |
| 2027 Q4 | 6.5B | 2.6B | 1.1B | $3.12 | $2.66 – $3.57 | 1 |
| 2028 Q1 | 6.0B | 2.2B | 779M | $2.31 | $1.96 – $2.64 | 1 |
| 2028 Q2 | 5.8B | 2.5B | 1.0B | $3.02 | $2.57 – $3.45 | 1 |
| 2028 Q3 | 7.0B | 2.9B | 1.3B | $3.91 | $3.33 – $4.47 | 1 |
| 2028 Q4 | 6.8B | 2.7B | 1.2B | $3.42 | $2.91 – $3.91 | 1 |
| 2029 Q1 | 3.8B | 1.8B | 456M | $1.35 | $1.15 – $1.54 | 1 |
| 2029 Q2 | 4.9B | 2.3B | 915M | $2.71 | $2.31 – $3.10 | 1 |
| 2029 Q3 | 8.4B | 4.2B | 2.3B | $6.87 | $5.85 – $7.85 | 1 |
| 2029 Q4 | 4.3B | 2.0B | 678M | $2.01 | $1.71 – $2.29 | 1 |
Corporate
Insider Trading (last 12mo)
| Date | Side | Insider | Title | Shares | Price | Dollars | Owned $ |
|---|---|---|---|---|---|---|---|
| 2026-10-07 | SELL | Moldovan Kristopher E. | officer: EVP and CFO | 20,000 | $165.00 | $3.30M | $29.54M |
| 2026-10-06 | SELL | HUDSON SCOTT A | officer: EVP & President Vistra Retail | 22,222 | $160.14 | $3.56M | $49.47M |
| 2026-09-08 | SELL | HUDSON SCOTT A | officer: EVP & President Vistra Retail | 44,444 | $151.82 | $6.75M | $50.27M |
| 2026-09-08 | SELL | Moldovan Kristopher E. | officer: EVP and CFO | 20,000 | $151.03 | $3.02M | $30.06M |
| 2026-09-01 | BUY | BURKE JAMES A | director, officer: President and CEO | 4,465 | $135.25 | $604K | $155.04M |
| 2026-08-31 | BUY | BURKE JAMES A | director, officer: President and CEO | 2,200 | $135.99 | $299K | $155.29M |
| 2026-08-24 | BUY | BURKE JAMES A | director, officer: President and CEO | 2,000 | $135.00 | $270K | $153.86M |
| 2026-06-18 | SELL | SULT JOHN R | director | 6,500 | $170.00 | $1.10M | $12.02M |
| 2026-06-18 | SELL | Acosta Arcilia | director | 15,000 | $167.52 | $2.51M | $5.46M |
| 2026-06-16 | SELL | HELM SCOTT B | director | 25,000 | $160.00 | $4.00M | $37.15M |
| 2026-06-15 | SELL | BARBAS PAUL M | director | 244 | $153.00 | $37K | $8.11M |
| 2026-06-12 | SELL | BARBAS PAUL M | director | 244 | $147.93 | $36K | $7.88M |
| 2026-06-02 | SELL | Montemayor Margaret | officer: SVP, Chief Accounting Officer | 4,600 | $160.00 | $736K | $1.56M |
| 2026-05-27 | SELL | Montemayor Margaret | officer: SVP, Chief Accounting Officer | 5,000 | $164.96 | $825K | $2.37M |
| 2026-03-09 | SELL | Moore Stephanie Zapata | officer: EVP and General Counsel | 10,000 | $160.31 | $1.60M | $18.34M |
| 2025-12-11 | SELL | BURKE JAMES A | director, officer: President and CEO | 22,251 | $162.05 | $3.61M | $48.29M |
| 2025-11-24 | SELL | Moore Stephanie Zapata | officer: EVP and General Counsel | 8,219 | $173.35 | $1.42M | $13.84M |
v2 analysis (legacy, 2026-08-07) — for comparison onlyclick to expand
Thesis
Vistra owns a strategically valuable portfolio of nuclear, gas and retail assets in markets where electricity demand may grow faster than new generation can be built. Its integrated retail-generation model and hedging reduce, but do not eliminate, commodity exposure. PJM capacity prices, nuclear PPAs and the prospect of data-center colocations are substantial positives. The principal risk is that investors capitalize a temporary power-price cycle as if it were permanent, while Vistra continues to consume significant cash in growth capex and acquisitions. The latest quarter supports the structural thesis operationally: generation improved, retail remained solid, fleet availability was high and management reaffirmed 2026 guidance. However, 2027 is trending toward the lower end of the opportunity range because ERCOT forward prices are weaker. Helix is strategically interesting but early, and Cogentrix, Meta-related economics and new data-center projects still carry closing, regulatory and execution risk. I therefore value the company on normalized owner earnings rather than peak adjusted EBITDA.
Trade Signal
No trade: Vistra's strategic power assets and positive operating inflection are real, but the analyst's fair value is essentially the current market cap and the 2% FCF yield leaves inadequate compensation for power-price, capex and execution risk.
Vistra fell from the $190–$210 area in late 2025 to the low $140s by February 2026, recovered toward $170–$173 in February, and then oscillated between roughly $140 and $169 through the spring and summer. The latest leg down from $169 in June to $141 after early-August earnings occurred despite strong Q2 results and reaffirmed guidance; the earnings-day move was effectively flat, indicating that good news was already expected. The decline is partly a durable repricing of high expectations and lower ERCOT forward curves, not pure panic. Still, the market appears to have undershot the improving PJM, nuclear-contract and dispatchable-capacity facts modestly. That gap could close on execution, but there is no sufficiently clear temporary dislocation to make it a trade by itself.
The stock has shifted from a crowded power/data-center winner to a disliked but still widely recommended growth utility. The 1-year analyst target averages $228.78 and the consensus is 20 buys, 2 holds and no sells, yet the shares are down 31% over one year and 35% below the 52-week high. Short interest is only moderate and falling, while put open interest materially exceeds call open interest. Bulls see structural load growth, PJM scarcity and nuclear PPAs; bears see cyclical power prices, high capex, Cogentrix leverage and a large gap between adjusted EBITDA and free cash flow. The bullish consensus may be stale on valuation, but the stock is not hated enough to create a strong contrarian setup.
The operational trajectory is positive: Q2 EBITDA rose more than 30%, PJM capacity prices are exceptional, Cogentrix is pending, and Meta/Helix could improve contract quality. But much of the attractive narrative is already embedded in consensus and the analyst's bull/base cases. The key missing evidence is conversion from EBITDA growth to durable owner earnings after maintenance and growth capex. The first meaningful proof should come from the Q3 print and Cogentrix timing, with a fuller test at 2027 guidance.
- ▲2026-08 · FERC regional-grid compliance filings and clarification of behind-the-meter co-location rules — Expected around the 60-day response period from the June 18 show-cause orders; clearer rules could support premium nuclear/data-center contracts.
- ▲H2 2026 · Cogentrix acquisition closing — The 5.5 GW gas portfolio should add dispatchable PJM/ISO-NE exposure, but leverage and integration execution remain risks.
- ▲2026-11 · Q3 2026 earnings and updated 2027 outlook — A result above the reaffirmed 2026 midpoint, evidence of Cogentrix contribution or stronger hedging could challenge the current cautious valuation.
- ▲Q4 2026–Q1 2027 · 2027 contracting, capacity-price and nuclear PPA updates — Further visibility on PJM capacity revenues, Meta economics and data-center load growth could improve the earnings-quality narrative.
- ▲2027-02 · Q4 2026 earnings and 2027 guidance — This is the clearest near-term test of whether the EBITDA opportunity range converts into owner earnings after growth capex.
Net share count has modestly declined TTM and management has a $1.2 billion repurchase authorization, with additional capital potentially available for buybacks. That is supportive but not yet an aggressive buyback commitment. The offset is substantial insider selling—48 sales totaling about $192 million and no insider purchases—plus acquisition and growth-capex funding needs. Short interest at 4% of float is declining and offers only modest squeeze fuel.
There is no hard floor near the current price. The company is solvent, cash generative and has valuable generation assets, but the reported EV/FCF and 2% FCF yield provide limited valuation support if ERCOT remains weak or capex consumes more cash. The bear case still supports approximately $89 per share, while the main ceiling is the high valuation required for the bullish data-center and power-scarcity scenario; insider selling may also create supply into rallies.
Vistra is a credible, liquid US power-platform investment with real strategic appeal: scarce nuclear and dispatchable generation, improving PJM economics, Meta PPAs and potential data-center demand. However, at roughly 49x EV/FCF and a 2% FCF yield, the next buyer needs to underwrite sustained power scarcity and successful growth capex rather than simply recognize an obvious bargain.
Fear is slightly stronger than greed at this price. The business and strategic assets are attractive, but the stock still requires a great deal of future power-price durability, data-center monetization and cash conversion to justify its valuation. The post-earnings nonreaction suggests the market is not willing to pay more merely for another strong EBITDA print.
Valuation
The Q2 result newly gave the market evidence that generation and retail can both improve despite weaker ERCOT forward curves: generation benefited from hedging, PJM capacity revenue, optimized gas dispatch, the Martin Lake restart and Lotus assets, while fleet availability exceeded 97%. Management also explicitly expressed confidence in finishing 2026 at or above the guidance midpoint. Offsetting new information was that 2027 currently trends toward the low end of its range, and management could not provide detailed regional 2028 hedge information. The Texas queue audit is expected to last months but is not currently expected to delay Comanche Peak.
▸ How the cases moved
Versus the day before the Q2 report, the bear case rises modestly from $28,000M to $30,000M as the quarter confirms operating resilience and liquidity, while its probability falls from 0.23 to 0.20. The base case rises from $57,000M to $60,000M and its probability increases from 0.55 to 0.55, reflecting confidence in at least the 2026 midpoint and stronger PJM/nuclear contributions, partly offset by lower ERCOT forward prices. The bull case rises from $87,000M to $91,000M and its probability increases from 0.22 to 0.25 because Helix, data-center demand and the potential Cogentrix/Meta contribution remain credible upside options. The event does not justify a major re-rating because management guided 2027 toward the lower end and gave limited detail on 2028 hedges and Helix economics.
ERCOT remains oversupplied for longer, data-center projects are delayed or economically repriced, and lower forward power prices offset PJM capacity strength. Cogentrix adds leverage without fully delivering its expected earnings, while maintenance and growth capex keep owner earnings below reported EBITDA. Vistra remains solvent and cash generative, but investors apply a lower-quality power-generator multiple.
▸ Valuation
10x $3,000M owner earnings = $30,000M equity value
Vistra delivers the lower-to-middle portion of its 2027 EBITDA opportunity range, with Cogentrix closing and the Meta-related economics developing but not fully mature. PJM capacity pricing, nuclear PPAs and hedging offset much of ERCOT weakness. The business becomes more contracted and resilient, while disciplined buybacks and moderate deleveraging support a durable owner-earnings stream.
▸ Valuation
12x $5,000M owner earnings = $60,000M equity value
Power demand from data centers, industrial reshoring and electrification tightens both ERCOT and PJM. Cogentrix closes smoothly, Meta and other nuclear PPAs monetize at attractive premiums, and Helix creates a high-return channel for colocated power and infrastructure. Owner earnings approach the company's prospective adjusted free-cash-flow potential as growth spending produces returns, justifying a premium for contracted, scarce dispatchable generation.
▸ Valuation
14x $6,500M owner earnings = $91,000M equity value
▸ Target Rationale
The probability-weighted scenario value discounted at 12% is $49,400M. I set the analytical target at $47,500M, modestly below the model, because the scenario framework does not fully capture the uncertainty around sustaining power prices, the capital intensity of the growth program, Cogentrix integration, and the gap between adjusted EBITDA and cash actually available after reinvestment. This is a business-quality and execution adjustment, not a sentiment discount; sentiment is handled separately in the fear-greed modifier.
Business Quality & Sentiment
Recent Research & News
Recent Research & News
2026-06-21Company news
- Launch of Helix Digital Infrastructure (June 2026): Vistra committed a $1 billion anchor investment to establish Helix Digital Infrastructure alongside partners KKR, Nvidia, and the Kuwait Investment Authority. Helix is a new $10 billion platform engineered to construct integrated infrastructure at the speed and scale required for heavy AI workloads. Crucially, Vistra has been designated as the preferred power provider for the venture, offering a direct strategic channel to contract its existing fleet, leverage hyperscaler relationships, and capture high-return data center opportunities.
- Acquisition of Cogentrix Energy (January 2026): Vistra signed a definitive agreement to acquire Cogentrix Energy's 5.5 GW natural gas generation portfolio for a net value of approximately $4.0 billion. The deal, which adds 10 dispatchable gas plants to VST's fleet, is expected to close in the second half of 2026. These assets provide Vistra with much-needed dispatchable scale in highly constrained power markets such as PJM and ISO-NE, acting as a crucial bridge as grid-connected power demand outpaces infrastructure timelines.
- Meta Nuclear PPAs (Early 2026): Vistra executed long-term, 20-year power purchase agreements (PPAs) with Meta. These agreements contract carbon-free electricity generated from Vistra's nuclear assets in PJM, providing long-term cash flow visibility and securing stable, premium returns to support the operations of large tech infrastructure.
- Q1 2026 Financial Results & Credit Upgrades (May 2026): On May 7, 2026, Vistra reported strong first-quarter results with GAAP net income of $1.029 billion and Ongoing Operations Adjusted EBITDA of $1.494 billion. Management reaffirmed full-year 2026 Adjusted EBITDA guidance of $6.8 billion to $7.6 billion and free cash flow before growth of $3.925 billion to $4.725 billion. Additionally, Fitch upgraded Vistra’s corporate credit rating to Investment Grade, following a similar move by S&P, reflecting the company’s strengthened balance sheet and earnings durability.
▸ Thesis-test Findings
- PJM capacity auction clearing prices 2026 2027: The PJM 2026/2027 Base Residual Auction (BRA) cleared at a record-breaking $329.17/MW-day, hitting the RTO cap of the price collar. In December 2025, the subsequent 2027/2028 BRA also hit the maximum price cap, clearing at $333.44/MW-day as the entire RTO grid operator fell short of its reliability target, securing only a 14.8% reserve margin instead of the targeted 20%. This extreme price action is highly bullish for Vistra. Driven by the combination of fossil-fuel retirements and forecasted data center demand (which accounted for nearly 5,100 MW of the RTO's load growth), back-to-back cap-clearing prices solidify highly lucrative capacity revenue streams for VST's nuclear and newly expanded gas-fired dispatchable assets in the region.
- FERC behind the meter colocation nuclear ruling updates: In December 2025, FERC issued a landmark order directing PJM to reform its "unjust and unreasonable" tariff, requiring the grid operator to establish clear rules, interconnection pathways, and new transmission products for data centers co-locating behind-the-meter (BTM) at power plants. FERC followed this in April 2026 by approving four clear interconnection pathways for BTM configurations under PJM's "Bring Your Own Generation" filings. This regulatory momentum culminated on June 18, 2026, when FERC issued sweeping Section 206 "show-cause" orders to all six major US regional grid operators (excluding ERCOT), giving them 60 days to revise their rules to facilitate BTM co-location and large load integration. This is overwhelmingly bullish for VST's thesis. Standardizing BTM pathways bypasses the grid's massive, multi-year interconnection backlogs, allowing Vistra to directly monetize its nuclear fleet with premium-priced, long-term hyperscaler contracts.
- ERCOT large load interconnection queue data center demand 2026: ERCOT's large-load interconnection queue (tracking energy consumers requiring 75 MW or more) ballooned to over 410–445 GW in early 2026, with data centers making up nearly 87% to 89% of the pending capacity. To manage this massive backlog, the Public Utility Commission of Texas (PUCT) approved ERCOT's first "Batch Zero" framework on June 18, 2026. Under these new rules, ERCOT will study large loads in grouped batches rather than first-come-first-served, requiring developers to show site control, pay nonrefundable fees, and prove financial backing to weed out speculative projects. This development is bullish for Vistra. While the batching process introduces a formal screening hurdle, filtering out speculative "paper" projects stabilizes the queue, and VST's position as the state's leading integrated generator makes it the premier counterparty for the well-capitalized, legitimate hyperscalers that survive the screening process.